|
Heng Shung Construction Co. Ltd. Mott MacDonald, 20/F Two Landmark East, 100 How Ming Street, Kwun Tong, Kowloon, Hong Kong T +852 2828 5757 F |
This document is issued for the party which commissioned it and for specific purposes connected with the above-captioned project only. It should not be relied upon by any other party or used for any other purpose. We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it. |
Pursuant to Condition 4.5 of
Environmental Permit No. EP-311/2008/A,
this Monthly EM&A Report for
May 2010 has been reviewed, certified by Environmental Team Leader (ETL) and
verified by the Independent Environmental Checker (IEC)
Certified by:
Environmental
Team Leader (ETL)
Mott MacDonald Hong
Kong Ltd.
Date 14 Jun 2010
Verified by:
David Yeung
Independent
Environmental Checker (IEC)
ENVIRON Hong Kong Limited
Date 15
Jun 2010
Content
Chapter Title Page
List of Figures
Figure 1.1 General
Layout Plan of the Project Site
Figure 2.1 Locations of
Air Quality Monitoring Stations
Figure 2.2 Locations of
Noise Monitoring Stations
Figure 2.3 Locations of
Water Quality Monitoring Stations
Figure 4.1 Survey Area
and Transect Walked
List of Appendices
Appendix A Project Organization Chart
Appendix B Tentative Construction Programme
Appendix C Action and Limit Levels for Construction Phase
Appendix D Event and Action Plan for Air Quality, Noise and Water Quality
Appendix E Calibration certificates
Appendix F Graphical plots of the monitoring results
Appendix G Weather conditions during the monitoring period
Appendix H Ecological Monitoring conducted in May 2010
Appendix I Summary of Bird Surveys conducted in May 2010
Appendix J Summary of Herpetofauna, and Insects Surveys conducted in May 2010
Appendix K Environmental Mitigation Measures - Implementation Status
Executive Summary
Mott MacDonald
Hong Kong Ltd. (“MMHK”) has been commissioned by Heng Shung Construction Co.
Ltd. to undertake the Environmental Team (ET) services to carry out
environmental monitoring and audit (EM&A) for both pre-construction and
construction phases of the Proposed Comprehensive Development at Wo Shang Wai,
Yuen Long.
This is the 1st
EM&A report submitted under the Condition 4.5 of Environmental Permit No.
EP-311/2008/A. This report summarises the findings on EM&A during the period
from 12 May to 31 May 2010.
Exceedance of Action and Limit
Levels
There was no
breach of Action or Limit levels for Air Quality (1-hr TSP and 24-hr TSP) and
Noise level (as Leq) in the reporting month.
Exceedances of Action and Limit Levels were
recorded for Water Quality at MP2, MP3, MP4, MP5 and MP6 on different
monitoring dates.
Exceedances
of pH, DO, turbidity and SS were observed. For MP2, there was exceedance of
action level for SS on 20 May 2010. For MP3, there were exceedances of pH, DO,
turbidity and SS (action and limit levels) on different monitoring dates. At
MP4, there were exceedances of limit level for turbidity and SS on 20 May 2010.
At MP5, pH, turbidity and SS were exceeded on 12 and 20 May 2010 (action level
for pH, limit levels for turbidity and SS). There were frequent action and
limit level exceedances of pH at MP6 during the monitoring period and
exceedances of limit levels of turbidity and SS on 12 and 14 May 2010. For MP4,
MP5, MP6, the DO were exceeded on most of the monitoring dates. The
summary of measured water quality is presented in Section 3.2.3.
Investigations
have been carried out to identify the causes of exceedance. From investigation,
the Contractor has implemented water quality mitigation measures as recommended
in the EIA report. With external factors affect the adjacent environments, such
as the re-profiling works carried out at the fish ponds and natural variations,
the exceedances were considered not due to construction works.
Implementation of mitigation
measures
Site audits were carried out on 12, 20 and 26 May 2010 to
confirm the implementation measures undertaken by the Contractor in the
reporting months. The outcomes are presented in Section 6
and the status of implementation of mitigation measures in the site is shown in
Appendix K.
Record of Complaints
There was no
record of complaints received in the reporting month.
Record of Notification of summons
and successful prosecution
There was no
record of Notification of summons and successful prosecution in the reporting
month.
Reporting Changes
There are no
changes to be reported this month.
Future Key Issues
The
major site works to be commissioned in the coming month include Site
formation and drainage work for Wetland Restoration Area (WRA), Installation
of Band Drain;
and Trial
Embankment
for Ground Improvement. Potential environmental impacts due to the construction
activities, including air quality, noise, water quality, ecology and landscape
and visual, will be monitored.
Environmental mitigation measures will be
implemented on site as recommended and weekly site audits will be carried out
to ensure that the environmental conditions are acceptable.
In March 2005, the Project Proponent, Profit
Point Enterprises Limited, acquired the development site in Yuen Long at
Wo Shang Wai. An Environmental Impact Assessment (EIA) was carried out under the
EIA Ordinance (EIAO) since then and the Environmental Permit (EP-311/2008A) for
construction of the comprehensive development in Wo Shang Wai was granted by
EPD on 9 September 2008. The Project involves the residential development and associated
infrastructure and wetland restoration area and linear
landscape area. The construction works under the Environmental Permit commenced
on 12 May 2010.
Heng Shung Construction Co. Ltd. was commissioned as the Contractor for the Project. Mott MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by Heng Shung Construction Co. Ltd. to undertake the Environmental Team (ET) services to carry out environmental monitoring and audit (EM&A) for both pre-construction and construction phases of the Proposed Comprehensive Development at Wo Shang Wai, Yuen Long.
According to the EP Condition 4.5, the monthly EM&A Report shall be submitted to the Director within 2 weeks after the end of the reporting month. This report summarises the findings during the period from 12 May to 31 May 2010.
The
organisation chart and lines of communication with respect to the on-site
environmental management structure together with the contact information of the
key personnel are shown in Appendix A.
During the reporting period, construction works
of the Project undertaken include:
¡
Site formation for Wetland Restoration Area (WRA);
¡
Band
drain work preparation; and
¡
Temporary drainage work
The Construction Works Programme of the
Project is provided in Appendix B. The
general layout plan of the Project site is shown in Figure 1.1.
The EM&A programme requires environmental monitoring of air quality, noise, water quality, ecology and landscape and visual as specified in the approved EM&A Manual.
A summary of impact EM&A requirements is presented in Table 1.1.
Table 1.1: Summary of Impact EM&A Requirements
|
Parameters |
Descriptions |
Locations |
Frequencies |
|
Air Quality |
24-Hour TSP |
ASR1, ASR2A, ASR3, ASR4 |
Once every 6 days |
|
1-Hour TSP |
ASR1, ASR2A, ASR3, ASR4 |
3 times every 6 days |
|
|
Noise |
Leq, 30min |
NSR1, NSR3, NSR5, NSR7 |
Weekly |
|
Water Quality |
Dissolved Oxygen (DO), temperature, pH, suspended solids (SS) and Biological Oxygen Demand (BOD) |
MP1 to MP6 |
3 days per week |
|
Ecology |
Birds |
Within the Project Area and Assessment Area of 500m |
Weekly |
|
Dragonflies and Butterflies |
Within the Project Area and Assessment Area of 500m |
Once per month during Mar and Sep to November, and twice per month during Apr to Aug |
|
|
Herpetofauna |
Within the Project Area and Assessment Area of 500m |
Once per month during Apr to Nov |
|
|
Water quality of WRA |
Wetland Restoration Area |
After filling of WRA with water, monthly for in situ water quality and every size months (end of wet season and end of dry season) for laboratory testing |
|
|
Site Inspections |
Within the Project Area and Assessment Area of 500m |
Weekly |
|
|
Landscape and Visual |
Auditing of protection of existing trees,
the transplanting of existing trees, the creation of new wetland, the
planting of new trees and shrubs and other landscape and visual mitigation measures
|
CM1
to CM10 and OM1 to OM7 within the Project Area |
Site inspections once every two weeks
during construction phase; once every two months during operational phase |
The Environmental Quality Performance Limits for air quality, noise and water quality are shown in Appendix C.
The Event and Action Plan for air quality, noise and water quality are shown in Appendix D.
2.
Impact Monitoring Methodology
|
For air
quality, construction noise and water quality, ecology,
landscape and visual monitoring methodology, including the monitoring
locations, monitoring equipments used, monitoring parameters, and frequency and
duration etc., are detailed in this Chapter.
In accordance with the EM&A Manual, 1-hour and 24-hour TSP levels monitoring are to be conducted during the construction phase. Table 2.1 summarizes the monitoring parameters, frequency and duration of air quality monitoring.
Table 2.1: Air Quality Monitoring Parameters, Frequency and Duration
|
Parameter |
Frequency and Duration |
|
|
ASR1, ASR2A, ASR3 & ASR4 |
24-hour TSP |
At least once in every six-days |
|
1-hour TSP |
3 times every six-days |
The
4 air quality monitoring stations were established in the EM&A manual and
were slightly adjusted during the baseline monitoring phase. Locations of the
agreed air quality monitoring stations are listed in Table 2.2 and as shown in Figure
2.1.
Table 2.2: Air monitoring stations
|
Monitoring Stations |
Locations |
|
ASR1 |
Works Site Boundary |
|
ASR2A |
At the rooftop of refuse collection point, which
is located at the southwest of the project area |
|
ASR3 |
At the commercial centre at |
|
ASR4 |
Works Site Boundary |
Continuous 24-hour TSP air quality
monitoring is
conducted using High Volume Sampler (HVS) (Model: GMWS-2310 Accu-vol). The HVS
meets all the requirements of the EM&A Manual. Portable direct reading dust
meters were used to carry out the 1-hour TSP monitoring. Table 2.3
summarizes the equipment used in the impact
air quality monitoring.
Table 2.3: TSP Monitoring Equipment
|
Equipment |
Model |
|
24-hr TSP monitoring |
|
|
High Volume
Sampler |
GMWS 2310
Accu-vol |
|
Calibrator |
GMW 25 |
|
1-hr TSP monitoring |
|
|
Portable direct
reading dust meter |
8520 Dust Track
Aerosol Monitor |
24-hour
TSP Monitoring
Installation
The HVS was installed in the vicinity of the air sensitive receiver. The following criteria were considered in the installation of the HVS.
· A horizontal platform with appropriate support to secure the sampler against gusty wind was provided.
· The distance between the HVS and any obstacles, such as buildings, was at least twice the height that the obstacle protrudes above the HVS.
· A minimum of 2 meters separation from walls, parapets and penthouse was required for rooftop sampler.
· A minimum of 2 meters separation from any supporting structure, measured horizontally was required.
· No furnace or incinerator flues or building vent were nearby.
· Airflow around the sampler was unrestricted.
· The sampler has been more than 20 metres from any drip line.
· Permission was obtained to set up the samplers and to obtain access to the monitoring stations.
· A secured supply of electricity is needed to operate the samplers.
Preparation of Filter Papers
· Glass fibre filters, were labelled and sufficient filters that were clean and without pinholes were selected.
· All filters were equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature was around 25 °C and not variable by more than ±3 °C with relative humidity (RH) < 50% and was not variable by more than ±5 %. A convenient working RH was 40%.
Field Monitoring
· The power supply was checked to ensure the HVS works properly.
· The filter holder and the area surrounding the filter were cleaned.
· The filter holder was removed by loosening the four bolts and a new filter, with stamped number upward, on a supporting screen was aligned carefully.
· The filter was properly aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.
· The swing bolts were fastened to hold the filter holder down to the frame. The pressure applied should be sufficient to avoid air leakage at the edges.
· The shelter lid was closed and was secured with the aluminium strip.
· The HVS was warmed-up for about 5 minutes to establish run-temperature conditions.
· A new flow rate record sheet was set into the flow recorder.
· The flow rate of the HVS was checked and adjusted at around 1.1 m3/min. The range specified in the EM&A Manual was between 0.6-1.7 m3/min.
· The programmable timer was set for a sampling period of 24 hrs + 1 hr, and the starting time, weather condition and the filter number were recorded.
· The initial elapsed time was recorded.
· At the end of sampling, the sampled filter was removed carefully and folded in half length so that only surfaces with collected particulate matter were in contact.
· It was then placed in a clean plastic envelope and sealed.
· All monitoring information was recorded on a standard data sheet.
· Filters were sent to a HOKLAS accredited laboratory for analysis.
Maintenance and Calibration
· The HVS and its accessories are maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.
· HVSs were calibrated prior to the commencement of baseline monitoring.
· Calibration records for HVSs are shown in Appendix E.
1-hour
TSP Monitoring
Field Monitoring
The measuring procedures of the 1-hour dust meter are in accordance with the Manufacturer’s Instruction Manual as follows:
·
Set POWER to “ON”, push
· Push the knob at MEASURE position.
· Push “O-ADJ” button. (Then meter’s indication is 0).
· Push the knob at SENSI ADJ position and set the meter’s indication to S value described on the Test Report using the trimmer for SENSI ADJ.
· Pull out the knob and return it to MEASURE position.
· Push “START” button.
Maintenance and Calibration
· The 1-hour dust meter would be checked at 3-month intervals and calibrated at 1-year intervals throughout all stages of the air quality baseline monitoring.
· Calibration records for HVS and direct dust meters are shown in Appendix E.
Following the requirements in the EM&A Manual for noise, noise monitoring has to be carried out during the construction phase. Continuous noise monitoring for the A-weighted levels Leq, L10 and L90 is undertaken once per every week.
Table 2.4 summarizes the monitoring parameters, frequency and duration of air quality monitoring.
Table 2.4: Noise Monitoring Parameters, Frequency and Duration
|
Monitoring Stations |
Parameter |
Frequency and Duration |
|
NSR1, NSR3, NSR5, NSR7 |
Leq, L90 & L10 |
Once every week |
The
4 noise
quality monitoring stations were established in the EM&A manual and were
slightly adjusted during the baseline monitoring phase. Locations of the agreed
noise
quality monitoring stations are listed in Table
2.5 and as shown in Figure
2.2.
Table 2.5: Noise monitoring stations
|
Monitoring Stations |
Locations |
Type of measurement |
|
NSR1 |
Noise monitoring equipment was set up near the
boundary wall at |
Free-field |
|
NSR3 |
The monitoring station was located next to the
guard house at |
Facade |
|
NSR5 |
The monitoring station was located within the work
site boundary. |
Free-field |
|
NSR7 |
The monitoring station was located near the
boundary wall of the house of Mai Po San Tsuen. |
Free-field |
Integrating Sound Level Meter will be used for noise monitoring. It is a Type 1 sound level meter capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx). They comply with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1). Table 2.6 summarizes the noise monitoring equipment model being used.
Table 2.6: Noise Monitoring Equipment
|
Monitoring locations |
Equipment Model |
|
|
Integrating Sound
Level Meter |
Calibrator |
|
|
NSR1 |
Rion NL-31 |
Rion NC-73 |
|
NSR3 |
||
|
NSR5 |
||
|
NSR7 |
||
Field Monitoring
· The Sound Level Meter was set on a tripod at a height of at least 1.2 m above the ground.
· Façade and free-field measurements were made at the monitoring locations.
· The battery condition was checked to ensure the correct functioning of the meter.
· Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:
- frequency weighting: A
- time weighting: Fast
- time measurement: 30 minutes intervals (between 0700 and 1900)
· Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94 dB at 1 kHz. If the difference in the calibration level before and after measurement was more than 1 dB, the measurement would be considered invalid has to be repeated after re-calibration or repair of the equipment.
· During the monitoring period, the Leq, L10 and L90 were recorded. In addition, any site observations and noise sources were recorded on a standard record sheet.
Maintenance and Calibration
· The microphone head of the sound level meter and calibrator is cleaned with soft cloth at quarterly intervals.
·
The meter and calibrator are sent to the
supplier or HOKLAS laboratory to check and calibrate at yearly intervals.
·
Calibration records are shown in Appendix E.
In
accordance with the requirements in the EM&A Manual for water quality, water quality parameters including Dissolved Oxygen
(DO), temperature, pH, turbidity, suspended solids (SS) and Biochemical Oxygen
Demand (BOD) have to be monitored at designated monitoring stations during
construction of the Project. DO, temperature and
pH were measured in-situ whereas SS and BOD were analysed in a laboratory. The measurements should be taken at all designated monitoring
stations, 3 days per week. The interval between any two sets of monitoring was
not less than 36 hours. Table
2.7 summarizes
the monitoring parameters, frequency and duration of water quality monitoring.
Table 2.7: Water Quality Monitoring Parameters, Frequency and Duration
|
Monitoring Stations |
Parameter |
Frequency and Duration |
|
MP1, MP2, MP3, MP4, MP5
& MP6 |
DO, temperature, pH, SS, turbidity,
BOD |
Three days every week |
The
6 water quality monitoring stations were
established in the EM&A manual. Locations of the agreed water quality monitoring stations are listed in
Table 2.8 and as shown in Figure
2.3.
Table 2.8: Water quality monitoring stations
|
Monitoring Stations |
Easting |
Northing |
|
MP1 |
838 730.50 |
822 862.25 |
|
MP2 |
838 933.26 |
823 247.41 |
|
MP3 |
839 107.17 |
823 596.84 |
|
MP4 |
839 286.14 |
823 638.55 |
|
MP5 |
839 134.35 |
823 722.99 |
|
MP6 |
839 063.02 |
823 842.25 |
The Water Quality Monitoring Equipments and Analytical Methods applied to Water Quality Samples are given in Table 2.9 and Table 2.10 respectively. Details of which are discussed below.
Table 2.9: Water Quality Monitoring Equipments
|
Equipment |
Model |
Equipment /Serial Number |
|
Dissolved oxygen, temperature & pH Measuring Meter |
YSI Professional Plus |
09K100735 |
|
Turbidimeter |
Hach 2100Q |
09120C000514 |
|
Global Positioning System (GPS) |
Garmin eTrex
|
ENO 007 |
Table 2.10: Analytical Methods applied to Water Quality Samples
|
Determinant, unit |
Standard Method |
|
Total Suspended Solids, mg/L |
In house method based on APHA 2540D; ALS Method Code: EA-025 |
|
Biochemical Oxygen Demand (BOD), mg/L |
In house method based on APHA 5210B; ALS Method Code: EP-030 |
All
in-situ monitoring instruments were checked, calibrated and certified by a
laboratory accredited
under HOKLAS or any other international accreditation scheme before use.
Dissolved
Oxygen (DO), temperature and pH measuring equipment
A portable, weatherproof multiparameter instrument YSI 556 MPS was used in the baseline monitoring. It can be capable for measuring dissolved oxygen (DO), pH, and temperature simultaneously with the following limits:
· a dissolved oxygen level in the range of 0-50 mg/L and 0-500 % saturation;
· a temperature of -5 to 45 degree Celsius; and
· pH value of 0-14 with 0.1 as the base unit.
Turbidity
Measurement Instrument
Portable and weatherproof turbidity meter (HACH model 2100P) was used during impact monitoring. It has a photoelectric sensor capable of measuring turbidity between 0-1000 NTU. Response of the sensor was checked with certified standard turbidity solutions before the start of measurement.
Global
Positioning System
A
hand-held GPS navigator (Garmin eTrex
Suspended Solids and BOD Measurements (Sample
Containers and Storage)
Water samples for SS analysis were stored in
high density polythene bottles with no preservative added, packed in ice
(cooled to 4oC without being frozen), delivered to the laboratory,
and analysed as soon as possible after collection. Analysis was carried out in a
HOKLAS accredited laboratory.
Detection Limit
The limits of
detection for the in-situ and laboratory measurements are shown in Table 2.11.
Table 2.11: Detection
Limits for Water Quality Determinants
|
Determinant |
Limit of Detection |
|
Dissolved Oxygen |
0.1 mg/L |
|
Temperature |
0.1
degree Celsius |
|
pH |
0.01 unit |
|
Turbidity |
0.1 NTU |
|
Suspended Solids |
1 mg/L |
|
BOD |
2 mg/L |
In situ measurement
All pH meters, DO/ temperature meters had
been checked and calibrated prior to use. Standard buffer solution of at least 2
pH levels (either pH 4 and pH 7 or pH 7 and pH 10) had been used for
calibration of the instrument before and after use.
DO meters had been calibrated by a laboratory
accredited under HOKLAS or any other international accreditation scheme, and
subsequently re-calibrated at 3 monthly intervals throughout all stages of the
water quality monitoring. Responses of sensors and electrodes had been checked
with certified standard solutions before each use. Wet bulb calibrations for
all DO meters had been carried out before measurement at each monitoring
location. For the on site calibration of field equipment, BS 127:1993,
"Guide to field and on-site test methods for the analysis of waters"
had been observed.
Measurements shall be at 3 water depths,
namely, 1m below water surface, mid-depth and 1m above stream bed/pond bed,
except where the water depth less that 6m, the middepth station maybe omitted.
Should the water depth be less than 3m, only the mid-depth station will be
monitored.
Replicates in-situ measurements and samples
collected from each independent monitoring event are required for all
parameters to ensure a robust statistically interpretable dataset.
Water Samples Preparation and Analysis
For collection of water sampling within the
water courses, a 500ml clean plastic beaker was used. After collection, the
water samples were stored in high-density polythene bottles. The sample
container was rinsed with a portion
of the water sample. The water sample was then transferred to the container,
labelled with a unique sample ID and sealed with a
screw cap. The water samples were stored in a cool box maintained
at 4oC. The water samples were then delivered to a local
HOKLAS-accredited laboratory (ALS) on
the same day for analysis.
The testing methods of testing parameters as
recommended by EIA or required by EPD,
with the QA/QC results are in accordance with the requirement of HOKLAS or
international accredited scheme.
The calibration certificates for equipments used for in-situ
monitoring of water quality are attached in Appendix E.
Target species and certain other fauna will
be monitored within the Project Area and Assessment Area during the wetland and
residential construction phase. This
will be important to ensure that any unexpected events or impacts either on- or
off-site are quickly identified so that remedial action can be taken. The groups to be monitored and frequency of
monitoring are shown in Table 2.12.
Table 2.12: Summary of Construction Phase Ecological Monitoring
for the Wo Shang Wai WRA
|
|
Construction
Phase Ecological Monitoring |
|
Birds |
Weekly (including Assessment
Area). |
|
Dragonflies and Butterflies |
Once per month during March
and September to November, and twice per month during April to August. |
|
Herpetofauna |
Once per month during April
to November. |
|
Water Quality |
After filling of WRA with
water, monthly for in situ water
quality and every six months (end of the wet season and end of the dry
season) for laboratory testing. |
|
Site Inspections |
Weekly. |
Ecological
monitoring locations during
construction phase are shown in Figure 4.1 and the methodology for ecological monitoring
is detailed in Section 4.
·
The extent of the agreed works area should be regularly
checked during the construction phase.
Any trespass by the Contractor outside the limit of the works, including
any damage to existing trees and woodland shall be noted;
·
The progress of the engineering works should be regularly
reviewed on site to identify the earliest practical opportunities for the
landscape works to be undertaken;
·
All existing vegetation, streams and other features within
the study area which are not directly affected by the works are retained and
protected;
·
The methods of protecting existing vegetation proposed by the
Contractor are acceptable and enforced;
·
Preparation, lifting transport and re-planting operations for
any transplanted trees;
·
The layout, design and construction of buildings conforms to
requirements specified in the EIA report;
·
All landscaping works are carried out in accordance with the
EIA recommendations and with specifications;
·
The planting of new trees, shrubs, groundcover, climbers,
grasses and other plans, together with the replanting of any transplanted trees
are carried out properly and within the right season;
·
All necessary horticultural operations and replacement
planting are undertaken throughout the Establishment Period to ensure the
healthy establishment and growth of both transplanted trees and all newly
establishment plants.
Table 2.13: Construction and Operation
Phase Audit Checklist
|
Area of Works |
Items to be Monitored |
|
Works Area |
Check the extent of the Works to ensure that the Works Area
is not exceeded |
|
Protection of all trees and woodland blocks to be retained |
Identification and demarcation of trees / vegetation to be
retained, erection of physical protection (e.g. fencing), monitoring against
possible incursion, physical damage, fire, pollution, surface erosion, etc. |
|
Streams |
Ensure no run-off into existing streams |
|
Clearance of existing vegetation |
Identification and demarcation of trees / vegetation to be
cleared, checking of extent of works to minimize damage, monitoring of
adjacent areas against possible incursion, physical damage, fire, pollution,
surface erosion, etc. |
|
Transplanting of trees |
Identification and demarcation of trees / vegetation to be
transplanted, monitoring of extent of pruning / lifting works to minimize
damage, timing of operations implementation of all stages of preparatory and
translocation works, and maintenance of transplanted vegetation, etc. |
|
Topsoil stripping |
Ensuring existing topsoil is stripped and stored under
recognized good practice and is hydroseeded and regularly turned to prevent
anaerobic conditions |
|
New buildings |
Ensure that building finishes accord with mitigation
proposals with regard to colour and albedo. |
|
Boundaries |
Ensuring hoarding are erected as required |
|
Noise Barrier |
Ensure noise barrier design accords with the mitigation
proposals with regard to location, materials and finishes. |
|
Night-time lighting |
Ensuring night-time lighting is directional, hooded and
shielded away from VSRs |
|
Plant supply |
Monitoring of operations relating to the supply of
specialist plant material (including the collecting, germination and growth
of plants from seed) to ensure that plants will be available in time to be
used within the construction works. |
|
Landscape and wetland treatments generally |
Check that wetland, and hard / soft landscape designs
conform to intent of mitigation measures and agreed designs |
|
Soiling, planting, etc. |
Monitoring of implementation and maintenance of soiling and
planting works against possible incursion, physical damage, fire, pollution,
surface erosion, etc. |
|
Establishment Works |
Monitoring of implementation of maintenance operation
during Establishment Period |
The monitoring locations should check
against the mitigation measures proposed under the approved Environmental
Impact Assessment, which are summarised as follows:
Table 2.14: Proposed Construction Phase
Mitigation Measures
|
ID No. |
Landscape and Visual
Mitigation Measure |
|
CM1 |
The construction area and contractor’s temporary works
areas should be minimised to avoid impacts on adjacent landscape. |
|
CM2 |
Screening of construction works by hoardings/noise barriers
around Works area in visually unobtrusive colours, to screen Works. |
|
CM3 |
Reduction of construction period to practical minimum. |
|
CM4 |
Topsoil, where identified, should be stripped and stored
for re-use in the construction of the soft landscape works, where the soil
material meets acceptable criteria and where practical. The Contract Specification shall include
storage and reuse of topsoil as appropriate. |
|
CM5 |
Hydroseeding or sheeting of soil stockpiles with visually
unobtrusive material (in earth tone). |
|
CM6 |
Advance screen planting to noise barriers. |
|
CM7 |
Control night-time lighting and glare by hooding all
lights. |
|
CM8 |
Ensure no run-off into streams adjacent to Project Area. |
|
CM9 |
Protection of existing trees on boundary of project area
shall be carefully protected during construction. Detailed Tree Protection Specification
shall be provided in the Contract Specification. Under this specification,
the Contractor shall be required to submit, for approval, a detailed working
method statement for the protection of trees prior to undertaking any works
adjacent to all retained trees, including trees in contractor’s works
areas. (Tree protection measures will
be detailed at S16 and Tree Removal Application stage). |
|
CM10 |
Trees unavoidably affected by the works shall be
transplanted where practical. Trees
should be transplanted straight to their destinations and not held in a
nursery. A detailed Tree Transplanting
Specification shall be provided in the Contract Specification, if applicable.
Sufficient time for necessary tree root and crown preparation periods shall
be allowed in the project programme. |
Table 2.15: Proposed Operation Phase
Mitigation Measures
|
ID
No. |
Landscape
Mitigation Measure |
|
OM1 |
Compensatory Tree Planting for all felled trees shall be
provided to the satisfaction of relevant Government departments. Required numbers and locations of
compensatory trees shall be determined and agreed separately with Government
during the Tree Felling Application process under ETWBTC 3/2006. |
|
OM2 |
A continuous belt of screen planting along southern
perimeter of project area with fast growing tree species. At least 450 trees capable of reaching a
height > 10m within 10 years should be planted. Planting of the belt of trees shall be
carried out as advance works ahead of other site formation and building
works. |
|
OM3 |
Maximise soft landscape and amenity water bodies in
residential areas of the development.
Approximately 750 of trees (of Heavy Standard size) should be
planted. Where space permits, roadside
berms should be created. Street trees should be of species that reach a
mature height of no less than 15m. |
|
OM4 |
Maximise freshwater habitat wetland creation consistent
with achieving other parameters. Min
4.74 ha to be provided. Wetlands must
have natural edge profiles with >1m wide emergent zone. No access to the wetland by residents and
all wetlands must be screened from residential development by a continuous
tree screen at interface with residential development or earth mounding such
that disturbance is minimised. Implementation of the wetland shall be carried
out as advance works. |
|
OM5 |
Use appropriate (visually unobtrusive and non-reflective)
building materials and colours in built structures. |
|
OM6 |
During detailed design, refine building layout to create a
min 10m wide gap between buildings north of Wo Shang Wai pond and also two
min 10m wide gaps in the row of buildings adjacent to Royal Palms. |
|
OM7 |
Streetscape elements (e.g. paving, signage, street furniture,
lighting etc.) shall be sensitively designed in a manner that responds to the
local context, and minimises potential negative landscape and visual
impacts. Lighting units should be
directional and minimise unnecessary light spill. |
Impact
monitoring for air quality (dust), noise and water quality due to the construction
work were undertaken during the reporting month in compliance with the EM&A
manual in the reporting period. Regular site inspections were carried out on 12,
20 and 26 May 2010 in the reporting month to assess the compliance with
environmental requirements.
Results of 1-hour TSP at the four monitoring locations are summarised in Table 3.1. Graphical plots of the monitoring results are shown in Appendix F.
Table 3.1: Summary
of 1-hour TSP monitoring results
|
Monitoring Date |
Start Time |
1-hr TSP (μg/m3) |
Range (μg/m3) |
Action Level (μg/m3) |
Limit Level (μg/m3) |
|||
|
1st Result |
2nd Result |
3rd Result |
||||||
|
ASR1 |
||||||||
|
12-May-10 |
12:50 |
87 |
81 |
77 |
48 - 87 |
378 |
500 |
|
|
18-May-10 |
12:55 |
56 |
58 |
52 |
||||
|
24-May-10 |
12:50 |
61 |
58 |
57 |
||||
|
28-May-10 |
12:54 |
48 |
56 |
52 |
||||
|
ASR2A |
||||||||
|
13-May-10 |
12:45 |
82 |
86 |
89 |
42 - 89 |
357 |
500 |
|
|
19-May-10 |
12:45 |
51 |
61 |
68 |
||||
|
25-May-10 |
12:48 |
51 |
49 |
53 |
||||
|
31-May-10 |
12:50 |
42 |
52 |
47 |
||||
|
ASR3 |
||||||||
|
13-May-10 |
8:40 |
87 |
78 |
72 |
41 - 87 |
358 |
500 |
|
|
19-May-10 |
8:55 |
63 |
62 |
58 |
||||
|
25-May-10 |
8:57 |
69 |
65 |
59 |
||||
|
31-May-10 |
9:03 |
50 |
41 |
45 |
||||
|
ASR4 |
||||||||
|
12-May-10 |
8:10 |
107 |
101 |
121 |
36 - 121 |
372 |
500 |
|
|
18-May-10 |
8:48 |
56 |
72 |
61 |
||||
|
24-May-10 |
9:02 |
91 |
100 |
87 |
||||
|
28-May-10 |
9:09 |
36 |
42 |
59 |
||||
Results of 24-hour TSP at the four monitoring locations are summarised in Table 3.2. Graphical plots of the monitoring results are shown in Appendix F.
Table 3.2: Summary
of 24-hour TSP monitoring results
|
Monitoring Date |
Monitoring Results (μg/m3) |
Range (μg/m3) |
Action Level (μg/m3) |
Limit Level (μg/m3) |
|
ASR1 |
|
|
|
|
|
12-May-10 |
50 |
50 - 75 |
226 |
260 |
|
18-May-10 |
75 |
|||
|
25-May-10 |
91 |
|||
|
28-May-10 |
90 |
|||
|
ASR2A |
|
|
|
|
|
13-May-10 |
60 |
60 - 83 |
213 |
260 |
|
19-May-10 |
69 |
|||
|
25-May-10 |
83 |
|||
|
31-May-10 |
79 |
|||
|
ASR3 |
|
|
|
|
|
13-May-10 |
45 |
45 - 100 |
205 |
260 |
|
18-May-10 |
83 |
|||
|
25-May-10 |
93 |
|||
|
31-May-10 |
100 |
|||
|
ASR4 |
|
|
|
|
|
12-May-10 |
45 |
45 - 97 |
237 |
260 |
|
18-May-10 |
72 |
|||
|
25-May-10 |
97 |
|||
|
28-May-10 |
88 |
No exceedance of 1-hour and 24-hour TSP (Action or Limit Level) was recorded in the reporting period.
The weather conditions in the reporting period are provided in Appendix G.
The
construction noise monitoring results are summarized in Table 3.3. Graphical plots of the monitoring data are
shown in Appendix F.
Table 3.3: Summary
of Construction noise
monitoring results
|
Monitoring Date |
Start Time |
Mean & Range
of Noise Levels, dB(A) |
Limit Level for Leq
(dB) |
||
|
Leq |
L10 |
L90 |
|||
|
NSR1 |
|
|
|
|
> 75 |
|
13-May-10 |
13:10 |
58 |
61 |
52 |
|
|
19-May-10 |
10:12 |
51 |
54 |
46 |
|
|
25-May-10 |
13:55 |
56 |
57 |
52 |
|
|
31-May-10 |
13:10 |
58 |
62 |
50 |
|
|
NSR3 |
|
|
|
|
|
|
13-May-10 |
8:55 |
68 |
74 |
49 |
|
|
19-May-10 |
9:12 |
52 |
55 |
48 |
|
|
25-May-10 |
9:14 |
57 |
58 |
47 |
|
|
31-May-10 |
9:28 |
54 |
55 |
48 |
|
|
NSR5* |
|
|
|
|
|
|
12-May-10 |
13:08 |
58 |
59 |
56 |
|
|
18-May-10 |
13:05 |
56 |
58 |
53 |
|
|
24-May-10 |
13:08 |
58 |
59 |
56 |
|
|
NSR7* |
|
|
|
|
|
|
12-May-10 |
9:22 |
66 |
69 |
63 |
|
|
18-May-10 |
10:55 |
65 |
67 |
62 |
|
|
24-May-10 |
11:10 |
63 |
65 |
59 |
|
* Only 3 monitoring events in May 2010 and monitoring to be carried out in the first week of June 2010.
No exceedance (Action/Limit Level) of construction noise was recorded in the reporting period.
The water quality monitoring results are summarized in Table 3.4. Graphical plots of the monitoring data are shown in Appendix F.
Table 3.4: Summary of Water quality monitoring results
|
Monitoring Date |
Temp (oC) |
pH |
Dissolved Oxygen (mg/L) |
DOS (%) |
Turbidity (NT) |
BOD (mg/L) |
Suspended Solids (mg/L) |
|
MP1 |
|
|
|
|
|
|
|
|
12/5/2010 |
25.4 |
7.3 |
1.6 |
19.8 |
19.7 |
4.0 |
27.5 |
|
14/5/2010 |
26.4 |
7.3 |
2.2 |
27.9 |
30.5 |
5.0 |
34.0 |
|
18/5/2010 |
26.4 |
7.3 |
2.5 |
30.6 |
88.9 |
3.0 |
82.0 |
|
20/5/2010 |
26.7 |
7.5 |
1.3 |
16.5 |
102.0 |
3.0 |
95.0 |
|
22/5/2010 |
28.0 |
7.4 |
2.8 |
35.5 |
21.3 |
4.0 |
24.0 |
|
24/5/2010 |
25.5 |
7.4 |
2.8 |
34.2 |
22.9 |
4.0 |
23.5 |
|
26/5/2010 |
28.0 |
7.4 |
1.8 |
23.3 |
27.6 |
4.0 |
26.0 |
|
28/5/2010 |
27.4 |
7.3 |
1.7 |
21.4 |
22.7 |
4.0 |
36.5 |
|
31/5/2010 |
26.8 |
7.3 |
2.1 |
26.8 |
26.8 |
4.5 |
35.0 |
|
Action Level |
- |
<5.5 or
>7.5 |
<1.23 |
- |
>173 |
- |
>231 |
|
Limit Level |
- |
<4.0 or
>8.0 |
<1.17 |
- |
>177 |
- |
>299 |
|
|
|
|
|
|
|
|
|
|
MP2 |
|
|
|
|
|
|
|
|
12/5/2010 |
26.7 |
7.5 |
5.1 |
64.2 |
26.7 |
4.0 |
18.5 |
|
14/5/2010 |
25.7 |
7.4 |
2.3 |
28.2 |
18.7 |
5.0 |
17.0 |
|
18/5/2010 |
26.6 |
7.4 |
4.9 |
60.4 |
21.4 |
2.0 |
23.0 |
|
20/5/2010 |
26.1 |
7.5 |
4.1 |
51.0 |
106.5 |
4.5 |
180.0 |
|
22/5/2010 |
27.0 |
7.4 |
2.8 |
35.0 |
25.0 |
2.0 |
21.0 |
|
24/5/2010 |
24.7 |
7.3 |
2.1 |
25.4 |
29.7 |
5.0 |
29.0 |
|
26/5/2010 |
27.6 |
7.5 |
3.2 |
41.3 |
25.5 |
5.0 |
25.5 |
|
28/5/2010 |
27.2 |
7.4 |
2.8 |
36.5 |
16.4 |
4.0 |
19.0 |
|
31/5/2010 |
26.7 |
7.3 |
2.1 |
26.1 |
30.6 |
<0.2 |
31.5 |
|
Action Level |
- |
<5.5 or
>7.5 |
<1.04 |
- |
>132 |
- |
>170 |
|
Limit Level |
- |
<4.0 or
>8.0 |
<0.89 |
- |
>163 |
- |
>209 |
|
|
|
|
|
|
|
|
|
|
MP3 |
|
|
|
|
|
|
|
|
12/5/2010 |
25.9 |
9.0 |
11.1 |
138.4 |
123.5 |
16.0 |
125.5 |
|
14/5/2010 |
25.9 |
7.8 |
6.3 |
78.5 |
136.5 |
13.5 |
135.5 |
|
18/5/2010 |
29.0 |
8.3 |
10.0 |
132.0 |
70.7 |
15.0 |
79.0 |
|
20/5/2010 |
27.2 |
8.5 |
10.0 |
126.3 |
148.0 |
12.5 |
180.0 |
|
22/5/2010 |
28.3 |
7.4 |
4.5 |
58.8 |
74.9 |
11.0 |
73.0 |
|
24/5/2010 |
24.7 |
7.6 |
4.9 |
59.5 |
120.5 |
11.0 |
115.0 |
|
26/5/2010 |
27.7 |
8.0 |
8.2 |
104.7 |
108.5 |
18.0 |
103.5 |
|
28/5/2010 |
28.3 |
7.8 |
4.8 |
63.4 |
59.2 |
7.0 |
67.0 |
|
31/5/2010 |
27.5 |
8.1 |
7.2 |
91.8 |
60.9 |
7.0 |
71.0 |
|
Action Level |
- |
<5.5 or
>7.5 |
<6.85 |
- |
>64 |
- |
>65 |
|
Limit Level |
- |
<4.0 or
>8.0 |
<6.65 |
- |
>67 |
- |
>66 |
|
|
|
|
|
|
|
|
|
|
MP4 |
|
|
|
|
|
|
|
|
12/5/2010 |
26.0 |
7.4 |
4.8 |
58.9 |
36.1 |
5.0 |
31.5 |
|
14/5/2010 |
26.6 |
7.2 |
5.2 |
64.1 |
37.1 |
5.0 |
31.0 |
|
18/5/2010 |
27.9 |
7.0 |
0.8 |
10.2 |
45.4 |
4.0 |
30.5 |
|
20/5/2010 |
25.3 |
7.3 |
1.2 |
15.0 |
72.9 |
4.5 |
78.0 |
|
22/5/2010 |
27.5 |
7.0 |
0.8 |
9.9 |
27.5 |
2.5 |
23.0 |
|
24/5/2010 |
25.5 |
7.0 |
1.1 |
13.8 |
29.4 |
5.0 |
21.5 |
|
26/5/2010 |
26.4 |
7.0 |
0.9 |
10.5 |
40.4 |
4.0 |
19.0 |
|
28/5/2010 |
27.7 |
7.1 |
1.3 |
17.2 |
28.6 |
4.0 |
31.0 |
|
31/5/2010 |
26.7 |
7.1 |
1.2 |
15.7 |
22.3 |
<2 |
25.5 |
|
Action Level |
- |
<5.5 or
>7.5 |
<3.91 |
- |
>60 |
- |
>50 |
|
Limit Level |
- |
<4.0 or
>8.0 |
<3.82 |
- |
>64 |
- |
>53 |
|
|
|
|
|
|
|
|
|
|
MP5 |
|
|
|
|
|
|
|
|
12/5/2010 |
25.3 |
7.7 |
3.7 |
43.9 |
101.6 |
8.0 |
74.5 |
|
14/5/2010 |
26.4 |
7.4 |
2.4 |
30.2 |
53.0 |
5.0 |
37.0 |
|
18/5/2010 |
28.2 |
7.4 |
2.7 |
33.9 |
34.8 |
6.0 |
18.5 |
|
20/5/2010 |
26.2 |
7.6 |
1.8 |
22.2 |
111.5 |
3.0 |
83.5 |
|
22/5/2010 |
28.1 |
7.2 |
1.4 |
18.3 |
48.9 |
3.5 |
48.5 |
|
24/5/2010 |
25.3 |
7.2 |
1.2 |
14.9 |
27.9 |
5.0 |
18.5 |
|
26/5/2010 |
27.6 |
7.3 |
2.8 |
34.6 |
39.7 |
5.5 |
33.0 |
|
28/5/2010 |
27.7 |
7.4 |
3.3 |
41.6 |
33.6 |
6.0 |
30.0 |
|
31/5/2010 |
26.8 |
7.3 |
2.0 |
25.8 |
48.4 |
3.5 |
43.5 |
|
Action Level |
- |
<5.5 or
>7.5 |
<4.13 |
- |
>81 |
- |
>66 |
|
Limit Level |
- |
<4.0 or
>8.0 |
<3.87 |
- |
>84 |
- |
>69 |
|
|
|
|
|
|
|
|
|
|
MP6 |
|
|
|
|
|
|
|
|
12/5/2010 |
25.6 |
7.9 |
2.8 |
34.2 |
232.0 |
9.0 |
224.5 |
|
14/5/2010 |
26.1 |
7.6 |
1.0 |
12.0 |
123.0 |
12.0 |
84.5 |
|
18/5/2010 |
29.0 |
8.1 |
4.4 |
57.2 |
61.9 |
10.5 |
49.5 |
|
20/5/2010 |
26.9 |
7.8 |
3.7 |
46.4 |
62.8 |
2.0 |
52.0 |
|
22/5/2010 |
27.6 |
7.9 |
1.7 |
20.6 |
31.2 |
4.0 |
19.5 |
|
24/5/2010 |
25.6 |
7.6 |
1.4 |
16.9 |
24.2 |
4.0 |
13.0 |
|
26/5/2010 |
27.3 |
7.5 |
2.0 |
24.3 |
32.8 |
3.0 |
22.0 |
|
28/5/2010 |
28.2 |
7.7 |
3.1 |
39.6 |
41.4 |
5.0 |
38.5 |
|
31/5/2010 |
26.7 |
7.6 |
1.7 |
22.7 |
86.4 |
<2 |
72.0 |
|
Action Level |
- |
<5.5 or
>7.5 |
<4.61 |
- |
>94 |
- |
>75 |
|
Limit Level |
- |
<4.0 or
>8.0 |
<4.52 |
- |
>96 |
- |
>75 |
Notes:
Values Bold indicate Action Level exceedance.
Values Underlined and Bold indicate
Limit Level exceedance.
Exceedances of pH, DO, turbidity and
SS were observed. For MP2, there was exceedance of action level for SS on 20
May 2010. For MP3, there were exceedances of pH, DO, turbidity and SS (action
and limit levels) on different monitoring dates. At MP4, there were exceedances
of limit level for turbidity and SS on 20 May 2010. At MP5, pH, turbidity and
SS were exceeded on 12 and 20 May 2010 (action level for pH, limit levels for turbidity
and SS). There were frequent action and limit level exceedances of pH at MP6
during the monitoring period and exceedances of limit levels of turbidity and
SS on 12 and 14 May 2010. For MP4, MP5, MP6, the DO were exceeded on most of
the monitoring dates.
The Event and Action Plan in Appendix D was followed under these cases of exceedances.
From investigation, the Contractor
has implemented water quality mitigation measures as recommended in the EIA
report, including the provision of temporary drainage facility and associated
treatment facility. Sand bags are in place in the temporary drainage channel to
enhance the desilting efficiency. The Contractor further enhanced the water
quality mitigation measures by erecting several segments of rock bunds at the
discharge outlet to avoid site runoff draining directly to the northern
ditches.
Moreover, re-profiling earthworks
were observed at the adjacent fish ponds by the fish pond owner so the
exceedances at MP3 were considered invalid. The exceedance of SS and turbidity
at MP4 and MP5 on 20 May 2010 were considered not due to construction works as
the location of MP6, which is close to the discharge outlet at the east of
construction site, both SS and turbidity level are less than MP4 and MP5
(Turbidity and SS level at MP6 are 62.8 NTU and 53 mg/L respectively). Moreover,
as noted by monitoring team during on-site sampling, no direct muddy water
discharge was observed from the site. The exceedances were considered not due
to construction works. However, possible source of discharge which may give
rise to the exceedance was unknown. Subsequent water quality monitoring results
carried out from 22 May 2010 onward indicated that no exceedance for SS and
turbidity for MP4, MP5 and MP6 except DO / pH.
DO and pH exceedance may be due to the
natural variation, as the temperature was higher when compared with baseline
monitoring period. The exceedances were considered not due to construction
works.
The Contractor was reminded to
implement the water quality mitigation measures in accordance with the
recommendation stated in Section 5.6.1 – 5.6.4 of the EIA Report as far as
practicable and regular spot check would be conducted on the nearby discharge
by Contractor and inform ET for investigation. As wet weather is coming, to
cater for the increase of site runoff, the Contractor would further enhance the
water quality mitigation measures by erecting several segments of rock bunds at
the discharge outlet to avoid site runoff draining directly to the northern
ditches.
Construction phase ecological
monitoring commenced on 12 May 2010. This report documents surveys conducted in
the Survey Area between 12 May and 31 May 2010. Survey Area is provided in Figure 4.1. Dates and ecological surveys conducted during this period are given in
Appendix H.
Monitoring was undertaken following
the survey methodology in the EM&A Manual. A transect was followed in the
bird surveys (see Figure 4.1). All bird species of conservation importance and/or wetland dependent
were identified and enumerated. Flying birds were not recorded unless they were
foraging and associated with the habitat (such as swifts). Further, notable
bird observations during other surveys were also recorded.
Bird surveys were conducted on a
weekly basis. A total of 21 bird species of conservation importance and/or
wetland-dependence were recorded using the ponds within 500 m of the Project
Site. A summary of survey data is provided in Appendix I.
Species and numbers recorded in this
survey period are typical of fish pond area in May, as the migratory season for
most species has passed. Survey findings indicate that the fish ponds within
the Survey Area continue to attract species that are typical of the area in
early summer months and are not adversely affected by the construction.
One day time and one night time
herpetofauna survey were conducted in the survey period. Only one amphibian
species (Günther’s Frog) was recorded in this month. This is a very common and
widespread species in northwestern
Monitoring of dragonfly and
butterfly was conducted on a bi-monthly basis. A total of 13 dragonfly species
and 6 butterfly species were recorded. All observations were of common and
widespread species recorded in low to very low numbers. A summary of the survey
findings are provided in Appendix J.
Monitoring of mammal was conducted
concurrently with other surveys. No mammals were recorded in the survey period.
Ecological monitoring were carried
out following the survey methodology and frequency outlined in the EM&A
Manual (March 2008) in May 2010.
A total of 21 bird species, 1
amphibian species, 13 dragonfly species and 6 butterfly species were recorded.
Survey findings indicate that the ponds within the Survey Area supported
numbers and diversity of wetland-dependent birds and other species of
conservation importance typical of the fish pond areas in the early summer
months.
The EM&A programme for Landscape and
Visual impact due to the construction commenced in May 2010. Site inspection was
carried out on 26 May 2010 to confirm the implementation of mitigation measures
at construction stage.
The audit
was undertaken with references to the specific checklists provided in Tables 2.13 – 2.15 and audit results are summarized as below:
Table 5.1: Construction and Operation Phase Audit Summary
|
Area of Works |
Items to be Monitored |
|
Works Area |
The
works area was confined by site hoardings and noise barriers at the site
boundaries. No works exceeded the site boundaries was observed. |
|
Protection of all trees and
woodland blocks to be retained |
An area
of reedbed was preserved and confined with fencing on site as nursery for the
replanting to future wetland restoration area. Trees retained and
transplanted were fenced off by site hoardings and noise barriers. |
|
Streams |
Mitigation
measures including sand bags and aqua sed were provided to avoid site run-off
and treatment of discharge. |
|
Clearance of existing vegetation |
Site
clearance was completed prior to the commencement of construction. An area of
reedbed was preserved and confined with fencing on site. |
|
Transplanting of trees |
Trees
transplanting was completed with strip planting along the southern site
boundary. |
|
Topsoil stripping |
Topsoils
to be reused on site were stockpiled on site with taupaulin sheet covered or
compacted and keep moist to minimize dust generation. |
|
New buildings |
Not
relevant |
|
Boundaries |
Hoardings
were erected as required |
|
Noise Barrier |
Noise
barriers design accords with the mitigation proposals with upper 7 or 6 m
portion in translucent material with green tinted to match with the
environment. All noise barriers were constructed at locations according to
the mitigation proposals. |
|
Night-time lighting |
No
night-time works were carried out during the monitoring period. |
|
Plant supply |
The
advance strip plantings were supplied by landscape contractor and the
planting period is in appropriate season to facilitate the establishment of
the plants. |
|
Landscape and wetland treatments
generally |
The
wetland restoration area is under construction. |
|
Soiling, planting, etc. |
The
strip planting with compensatory and transplanted trees has not been hand
over for maintenance, the planting works are under supervision on-site to
ensure meeting the requirement in the approved planting proposal. |
|
Establishment Works |
The
strip planting has not been hand over. Monitoring will be carried out in next
phase. |
The ET had carried out pre-construction
phase weekly site inspections on 12, 20
and 26 May 2010. All observations have been
recorded in the site inspection checklist and passed to the Contractor together
with the appropriate recommended mitigation measures where necessary. The key
observations from site inspections and associated recommendations are
summarized in Table 6.1.
Table 6.1: Summary of Site Inspections and Recommendations
|
Key Observations |
ET Recommendation |
Contractor’s Responses / Action(s) Undertaken |
Close-out (Date) |
|
Water ponding in the site |
To clear stagnant water regularly |
Agreed and on-going |
- |
|
Un-used drainage channel |
To backfill the channel |
Agreed and action taken |
26 May 2010 |
|
Mud track on the haul road |
To clear the mud track and avoid
site vehicles from using the haul road |
Agreed and action taken |
20 May 2010 |
|
Muddy water inside wheel wash
facility |
To clean the water for improving
the washing efficiency |
Agreed and action taken |
3 Jun 2010 |
|
Discharge point under modification |
To reinstate the rock filter and
avoid runoff from direct discharge |
Agreed and action taken |
3 Jun 2010 |
|
Stockpiles in the site |
To provide appropriate covering
(e.g. tarpaulin sheet) |
Agreed and action taken |
3 Jun 2010 |
The Contractor has been registered as a
chemical waste producer for the Project. Construction and demolition (C&D)
material sorting was carried out on site. A sufficient number of receptacles were
available for general refuse collection.
As advised by the Contractor, 0 tonnes of
C&D material were generated on site and disposed off at Public Fill
Reception Facilities at Tuen Mun Area 38 during the period. No metals was
generated and collected by registered recycling collector. No paper cardboard
packing and plastic were generated on site and collected by registered
recycling collector. No chemical waste was generated and collected by licensed
chemical waste collector. 4.2 tonnes of other types of wastes (e.g. general
refuse) was generated on site and disposed of at North East New Territories (NENT)
Landfill.
The Contractor is advised to maintain on
site waste sorting and recording system and maximize reuse/recycling of C&D
wastes.
The environmental permits, licenses, and/or
notifications on environmental protection for this Project which were valid during
the period is summarised in Table 6.2.
Table 6.2: Status of Environmental Submissions, Licenses and Permits
|
Statutory Reference |
Description |
Permit /Reference No. |
Status |
|
EIAO |
Environmental Permit |
EP-311/2008A |
Valid |
|
APCO |
Notification of Construction Work under
APCO |
316688 (27 Apr
2010) |
Valid |
|
WPCO |
Discharge License |
(Application
no.: 313815) |
Under
Application (Submitted
on 22 Jan 2010) |
|
WDO |
Registration as Chemical
Waste Producer |
WPN0000-542-H3083-04 |
Valid |
|
WDO |
Bill Account for disposal |
700945423 |
Valid |
Legend: EIAO – Environmental Impact Assessment
Ordinance
APCO – Air Pollution Control Ordinance
WPCO – Water Pollution Control Ordinance
WDO – Waste Disposal Ordinance
The EM&A
programme followed the recommended mitigation measures in the EM&A manual.
The EM&A requirements as well as the summary of implementation status of
the environmental mitigation measures are provided in Appendix
K. In particular, the following mitigation measures
were brought to attention during the site audits:
Air
Quality
·
All stockpiles should be covered by tarpaulin or kept
wet by water spraying;
·
All
vehicles should be washed to remove any dusty materials before leaving the
construction sites;
·
the
portion of road leading the construction site that is within
·
Sufficient water spraying should be provided at haul
road to reduce dust emission; and
·
Ensure proper functioning of the wheel wash facility.
Noise
·
Mobile plant should be sited as far away from NSRs as
possible;
·
Plant
known to emit noise strongly in one direction should be orientated to direct
noise away from the NSRs; and
·
The construction activities should be better scheduled
to reduce noise nuisance.
Water
Quality
·
Water accumulated in the site (including water inside
drip trays) should be cleared frequently;
·
Ensure
proper functioning of the wastewater
treatment facility;
·
Silt and debris should be removed from the temporary
drainage channel regularly; and
·
Any soil contaminated with chemicals/oils shall be
removed from site and the void created shall be filled with suitable materials.
Waste
management
·
Reuse the excavated materials as far as practical to
reduce the amount of waste disposal;
·
Ensure drip trays are provided for chemical containers
to prevent leakage or soil contamination;
·
All
plants and vehicles should be properly maintained to prevent oil leakage;
·
Oil
stains on soil should be cleared by disposal of contaminated soil; and
·
Ventilation
should be provided for the Chemical Store Room.
There is no breach of Action or Limit Levels for Air Quality and Noise monitoring in the reporting month.
Exceedances of Action and Limit Levels were recorded for Water Quality at MP2, MP3, MP4, MP5 and MP6 on different monitoring dates.
Exceedances of pH, DO, turbidity and SS were observed. For MP2, there was exceedance of action level for SS on 20 May 2010. For MP3, there were exceedances of pH, DO, turbidity and SS (action and limit levels) on different monitoring dates. At MP4, there were exceedances of limit level for turbidity and SS on 20 May 2010. At MP5, pH, turbidity and SS were exceeded on 12 and 20 May 2010 (action level for pH, limit levels for turbidity and SS). There were frequent action and limit level exceedances of pH at MP6 during the monitoring period and exceedances of limit levels of turbidity and SS on 12 and 14 May 2010. For MP4, MP5, MP6, the DO were exceeded on most of the monitoring dates. Table 7.1 provides summary of exceedance of Action and Limit Levels for water quality in the reporting month.
Table 7.1: Summary of exceedances in Water Quality
|
Monitoring Date |
pH |
Dissolved Oxygen (mg/L) |
Turbidity (NT) |
Suspended Solids (mg/L) |
|
MP2 |
|
|
|
|
|
20/5/2010 |
7.5 |
4.1 |
106.5 |
180.0 |
|
Action Level |
<5.5 or
>7.5 |
<1.04 |
>132 |
>170 |
|
Limit Level |
<4.0 or
>8.0 |
<0.89 |
>163 |
>209 |
|
|
|
|
|
|
|
MP3 |
|
|
|
|
|
12/5/2010 |
9.0 |
11.1 |
123.5 |
125.5 |
|
14/5/2010 |
7.8 |
6.3 |
136.5 |
135.5 |
|
18/5/2010 |
8.3 |
10.0 |
70.7 |
79.0 |
|
20/5/2010 |
8.5 |
10.0 |
148.0 |
180.0 |
|
22/5/2010 |
7.4 |
4.5 |
74.9 |
73.0 |
|
24/5/2010 |
7.6 |
4.9 |
120.5 |
115.0 |
|
26/5/2010 |
8.0 |
8.2 |
108.5 |
103.5 |
|
28/5/2010 |
7.8 |
4.8 |
59.2 |
67.0 |
|
31/5/2010 |
8.1 |
7.2 |
60.9 |
71.0 |
|
Action Level |
<5.5 or
>7.5 |
<6.85 |
>64 |
>65 |
|
Limit Level |
<4.0 or
>8.0 |
<6.65 |
>67 |
>66 |
|
|
|
|
|
|
|
MP4 |
|
|
|
|
|
18/5/2010 |
7.0 |
0.8 |
45.4 |
30.5 |
|
20/5/2010 |
7.3 |
1.2 |
72.9 |
78.0 |
|
22/5/2010 |
7.0 |
0.8 |
27.5 |
23.0 |
|
24/5/2010 |
7.0 |
1.1 |
29.4 |
21.5 |
|
26/5/2010 |
7.0 |
0.9 |
40.4 |
19.0 |
|
28/5/2010 |
7.1 |
1.3 |
28.6 |
31.0 |
|
31/5/2010 |
7.1 |
1.2 |
22.3 |
25.5 |
|
Action Level |
<5.5 or
>7.5 |
<3.91 |
>60 |
>50 |
|
Limit Level |
<4.0 or
>8.0 |
<3.82 |
>64 |
>53 |
|
|
|
|
|
|
|
MP5 |
|
|
|
|
|
12/5/2010 |
7.7 |
3.7 |
101.6 |
74.5 |
|
14/5/2010 |
7.4 |
2.4 |
53.0 |
37.0 |
|
18/5/2010 |
7.4 |
2.7 |
34.8 |
18.5 |
|
20/5/2010 |
7.6 |
1.8 |
111.5 |
83.5 |
|
22/5/2010 |
7.2 |
1.4 |
48.9 |
48.5 |
|
24/5/2010 |
7.2 |
1.2 |
27.9 |
18.5 |
|
26/5/2010 |
7.3 |
2.8 |
39.7 |
33.0 |
|
28/5/2010 |
7.4 |
3.3 |
33.6 |
30.0 |
|
31/5/2010 |
7.3 |
2.0 |
48.4 |
43.5 |
|
Action Level |
<5.5 or
>7.5 |
<4.13 |
>81 |
>66 |
|
Limit Level |
<4.0 or
>8.0 |
<3.87 |
>84 |
>69 |
|
|
|
|
|
|
|
MP6 |
|
|
|
|
|
12/5/2010 |
7.9 |
2.8 |
232.0 |
224.5 |
|
14/5/2010 |
7.6 |
1.0 |
123.0 |
84.5 |
|
18/5/2010 |
8.1 |
4.4 |
61.9 |
49.5 |
|
20/5/2010 |
7.8 |
3.7 |
62.8 |
52.0 |
|
22/5/2010 |
7.9 |
1.7 |
31.2 |
19.5 |
|
24/5/2010 |
7.6 |
1.4 |
24.2 |
13.0 |
|
26/5/2010 |
7.5 |
2.0 |
32.8 |
22.0 |
|
28/5/2010 |
7.7 |
3.1 |
41.4 |
38.5 |
|
31/5/2010 |
7.6 |
1.7 |
86.4 |
72.0 |
|
Action Level |
<5.5 or
>7.5 |
<4.61 |
>94 |
>75 |
|
Limit Level |
<4.0 or
>8.0 |
<4.52 |
>96 |
>75 |
Notes:
Values Bold indicate Action Level exceedance.
Values Underlined and Bold indicate
Limit Level exceedance.
No environmental complaint was received this month.
No notifications of summons or successful prosecution were received this month.
Investigations have been carried out to identify
the causes of exceedance. The investigation reports for the exceedances
happened during the reporting period have been sent to the IEC for review.
Currently the investigation report for exceedances from 20 to 31 May 2010 is
under review and revision.
From investigation, construction activities
during the period of exceedance included mainly site clearance, site formation,
and drainage work. It was observed that the Contractor has implemented water
quality mitigation measures as recommended in the EIA report, including the
provision of temporary drainage facility and associated treatment facility.
Sand bags are in place in the temporary drainage channel to enhance the
desilting efficiency. The Contractor further enhanced the water quality
mitigation measures by erecting several segments of rock bunds at the discharge
outlet to avoid site runoff draining directly to the northern ditches.
With external factors affect the adjacent environments, such as the re-profiling works carried out at the fish ponds and natural variations, the exceedances were considered not due to construction works.
As non-compliances have been recorded, The
Event and Action Plan has been followed. Although it is considered that the
exceedances were not related to the Project, the Contractor was reminded to
implement the water quality mitigation measures in accordance with the
recommendation stated in Section 5.6.1 – 5.6.4 of the EIA Report as far as
practicable and regular spot check would be conducted on the nearby discharge
by Contractor and inform ET for investigation.
As wet weather is coming, to cater for the
increase of site runoff, the Contractor would further enhance the water quality
mitigation measures by erecting several segments of rock bunds at the discharge
outlet to avoid site runoff draining directly to the northern ditches.
The major site works to be commissioned in the coming month include:
¡
Site formation and drainage work for Wetland
Restoration Area (WRA);
¡
Installation of Band Drain; and
¡
Trial Embankment for Ground Improvement
Key issues to be considered in the coming month include:
¡
Generation
of dust from activities on-site (esp. for Trial Embankment);
¡
Noise
impact from operating equipment and machinery on-site;
¡
Generation
of site surface runoffs and wastewater from activities on-site;
¡
Sorting,
recycling, storage and disposal of general refuse and construction waste from
activities on-site; and
¡
Management
of chemicals and avoidance of oil spillage on-site.
The environmental site inspection and environmental monitoring will be continued in the coming month. Impact monitoring for air, noise, water quality, ecology and landscape and visual in accordance with the approved EM&A Manual has commenced since 12 May 2010. The tentative monitoring schedule for June 2010 is shown in the Table 8.1.
Table 8.1: Tentative
Environmental Monitoring and Audit Schedule for June 2010

The EM&A programme as recommended in the EM&A manual has been undertaken in the reporting month since 12 May 2010.
Monitoring of Air Quality, Noise, Water Quality, Ecology and Landscape and Visual impacts due to the Project was under way. In particular, the 1-hr TSP, 24-hr TSP, noise level (as Leq) and water quality parameters (such as pH, DO and SS) under monitoring have been checked against established Action and Limit levels.
There was no breach of Action and Limit Levels for 1-hr TSP,
24-hr TSP and noise in the
reporting month.
Action and Limit Level exceedances of pH, DO, turbidity and SS were
recorded at water quality monitoring stations including MP2, MP3, MP4, MP5 and
MP6. However, Investigations on the exceedance showed that the exceedances were
not related to the Project and may have been due to external factors such as
the re-profiling works in the fish ponds and natural variations.
With considerations on the construction activities and environment, the
following recommendations were provided:
Air Quality
·
All stockpiles should be covered by tarpaulin or kept
wet by water spraying;
·
All
vehicles should be washed to remove any dusty materials before leaving the
construction sites;
·
the
portion of road leading the construction site that is within
·
Sufficient water spraying should be provided at haul
road to reduce dust emission; and
·
Ensure proper functioning of the wheel wash facility.
Noise
·
Mobile plant should be sited as far away from NSRs as
possible;
·
Plant
known to emit noise strongly in one direction should be orientated to direct
noise away from the NSRs; and
·
The construction activities should be better scheduled
to reduce noise nuisance.
Water Quality
·
Water accumulated in the site (including water inside
drip trays) should be cleared frequently;
·
Ensure
proper functioning of the wastewater treatment facility;
·
Silt and debris should be removed from the temporary
drainage channel regularly; and
·
Any soil contaminated with chemicals/oils shall be
removed from site and the void created shall be filled with suitable materials.
Waste management
·
Reuse the excavated materials as far as practical to
reduce the amount of waste disposal;
·
Ensure drip trays are provided for chemical containers
to prevent leakage or soil contamination;
·
All
plants and vehicles should be properly maintained to prevent oil leakage;
·
Oil
stains on soil should be cleared by disposal of contaminated soil;
·
Ventilation
should be provided for the Chemical Store Room.

Contact information:
|
Company |
Position |
Name |
Telephone / |
|
Heng Shung Construction Co. Ltd. (The Contractor) |
Assistant Construction
Manager |
Ms Lynne Hung |
2908 2391 |
|
Heng Shung Construction Co. Ltd. (The Contractor) |
Site Agent |
Mr Poon Man Ho |
9426 3533 |
|
Heng Shung Construction Co. Ltd. (The Contractor) |
Environmental Officer |
Mr. Lun Ho Yin |
9866 7497 |
|
ENVIRON Hong
Kong Ltd (IEC) |
Independent Environmental
Checker |
Mr David Yeung |
3743 0788 |
|
Mott MacDonald Hong Kong Ltd. (ET) |
ET Team Leader |
Ms Florence Yuen |
2828 5768 |
Appendix C.
Action and
Limit Levels for Construction Phase
|
Air
Quality
Action
and Limit Levels for 24-hour TSP
|
Monitoring Station |
Action Level (mg/m3) |
Limit Level (mg/m3) |
|
ASR1 |
226 |
260 |
|
ASR2A |
213 |
260 |
|
ASR3 |
205 |
260 |
|
ASR4 |
237 |
260 |
Action and Limit Levels for 1-hour TSP
|
Monitoring Station |
Action Level (mg/m3) |
Limit Level (mg/m3) |
|
ASR1 |
378 |
500 |
|
ASR2A |
357 |
500 |
|
ASR3 |
358 |
500 |
|
ASR4 |
372 |
500 |
Noise
Action and Limit Levels for
Construction Noise
|
Time Period |
Action Level |
Limit Level |
|
NSR1, NSR3, NSR5, NSR7 |
||
|
0700 – 1900 hours on
normal weekdays |
When one documented
complaint is received from any one of the sensitive receivers |
75 dB(A) |
Water Quality
Action and Limit
Levels for Water Quality
|
Parameters |
DO in mg/L |
Turbidity in NTU |
SS in mg/L |
pH |
||||
|
|
Action
Level |
Limit
Level |
Action
Level |
Action
Level |
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
|
MP1 |
1.23 |
1.17 |
173 |
177 |
231 |
299 |
< 5.5 or > 7.5 |
< 4.0 or > 8.0 |
|
MP2 |
1.04 |
0.89 |
132 |
163 |
170 |
209 |
||
|
MP3 |
6.85 |
6.65 |
64 |
67 |
65 |
66 |
||
|
MP4 |
3.91 |
3.82 |
60 |
64 |
50 |
53 |
||
|
MP5 |
4.13 |
3.87 |
81 |
84 |
66 |
69 |
||
|
MP6 |
4.61 |
4.52 |
94 |
96 |
75 |
75 |
||
Appendix D.
Event
and Action Plan for Air Quality, Noise, Water Quality, Ecology and Landscape
& Visual
|
Air Quality
|
Event |
Action |
|||
|
ET
Leader |
IEC |
ER |
Contractor |
|
|
Action
Level |
|
|
|
|
|
1. Exceedance for one
sample |
1. Identify source,
investigate the causes of exceedance and propose remedial measures. 2. Inform IEC and ER. 3. Repeat measurement to
confirm finding. 4. Increase monitoring
frequency to daily. |
1. Check monitoring data
submitted by ET. 2. Check Contractor’s
working method. |
1. Notify Contractor. |
1. Rectify any
unacceptable practice. 2. Amend working methods
if appropriate. |
|
2. Exceedance for two or
more consecutive samples |
1. Identify the source. 2. Inform IEC and ER. 3. Advise ER on the effectiveness of the
proposed remedial measures 4. Repeat measurements to
confirm findings. 5. Increase monitoring
frequency to daily. 6. Discuss with IEC and
the Contractor on remedial actions required. 7. If exceedance
continues, arrange meeting with IEC and ER. 8. If exceedance stops,
cease additional monitoring. |
1. Check monitoring data
submitted by ET. 2. Check the Contractor’s
working method. 3. Discuss with ET Leader
and the Contractor on possible remedial measures. 4. Advise ER on the
effectiveness of the proposed remedial measures. 5. Supervise
implementation of remedial measures. |
1. Confirm receipt of
notification of exceedance in writing. 2. Notify the Contractor. 3. Ensure remedial
measures properly implemented. |
1. Submit proposals for
remedial actions to IEC within 3 working days of notification. 2. Implement the agreed
proposals. 3. Amend proposal if
appropriate. |
|
Limit
Level |
|
|
|
|
|
1. Exceedance for one
sample |
1. Identify source,
investigate the causes of exceedance and propose remedial measures. 2. Inform ER and EPD. 3. Repeat measurement to
confirm finding. 4. Increase monitoring
frequency to daily. 5. Assess effectiveness of
Contractor’s remedial actions and keep IEC, EPD and ER informed of the
results. |
1. Check monitoring data
submitted by ET. 2. Check the Contractor’s
working method. 3. Discuss with ET Leader
and the Contractor on possible remedial measures. 4. Advise ER on the
effectiveness of the proposed remedial measures. 5. Supervise implementation
of remedial measures. |
1. Confirm receipt of
notification of exceedance in writing. 2. Notify the Contractor. 3. Ensure remedial
measures properly implemented. |
1. Take immediate action
to avoid further exceedance. 2. Submit proposals for
remedial actions to IEC within 3 working days of notification. 3. Implement the agreed
proposals. 4. Amend proposal if
appropriate. |
|
2. Exceedance for two or
more consecutive samples |
1. Notify IEC, ER, EPD and
the Contractor. 2. Identify the source. 3. Repeat measurements to
confirm findings. 4. Increase monitoring
frequency to daily. 5. Carry out analysis of
the Contractor’s working procedures to determine possible mitigation to be
implemented. 6. Arrange meeting IEC and
ER to discuss the remedial actions to be taken. 7. Assess effectiveness of
the Contractor’s remedial actions and keep IEC, EPD and ER informed of the
results. 8. If exceedance stops,
cease additional monitoring. |
1. Discuss amongst ER, ET
Leader and the Contractor on the potential remedial actions. 2. Review the Contractor’s
remedial actions whenever necessary and advise ER accordingly. 3. Supervise the
implementation of remedial measures. |
1. Confirm receipt of
notification of exceedance in writing. 2. Notify the Contractor. 3. In consultation with
IEC, agree with the remedial measures to be implemented. 4. Ensure remedial
measures are properly implemented. 5. If exceedance
continues, consider what activity of the work is responsible and instruct the
Contractor to stop that activity of work until the exceedance is abated. |
1. Take immediate action
to avoid further exceedance. 2. Submit proposals for
remedial actions to IEC within 3 working days of notification. 3. Implement the agreed
proposals. 4. Resubmit proposals if
problem still not under control. 5. Stop the relevant
activity of works as determined by ER until the exceedance is abated. |
Construction Noise
|
Event |
Action |
|||
|
ET Leader |
IEC |
ER |
Contractor |
|
|
Action Level |
1. Notify IEC and the Contractor. 2. Carry out investigation. 3. Report the results of investigation to IEC and the Contractor. 4. Discuss with the Contractor and formulate remedial measures. 5. Increase monitoring frequency to check mitigation measures. |
1. Review with analysed results submitted by ET. 2. Review the proposed remedial measures by the Contractor and advise ER
accordingly. 3. Supervise the implement of remedial measures. |
1. Confirm receipt of notification of exceedance in writing. 2. Notify the Contractor. 3. Require the Contractor to propose remedial measures for the analysed
noise problem. 4. Ensure remedial measures are properly implemented. |
1. Submit noise mitigation proposals to IEC. 2. Implement noise mitigation proposals. |
|
Limit Level |
1. Identify the source. 2. Notify IEC, ER, EPD and the Contractor. 3. Repeat measurement to confirm findings. 4. Increase monitoring frequency. 5. Carry out analysis of Contractor’s working procedures to determine
possible mitigation to be implemented. 6. Inform IEC, ER, and EPD the causes & actions taken for the
exceedances. 7. Assess effectiveness of the Contractor’s remedial actions and keep
IEC, EPD and ER informed of the results. 8. If exceedance stops, cease additional monitoring. |
1. Discuss amongst ER, ET Leader and the Contractor on the potential
remedial actions. 2. Review the Contractor’s remedial actions whenever necessary to assure
their effectiveness and advise ER accordingly. 3. Supervise the implementation of remedial measures. |
1. Confirm receipt of notification of exceedance in writing. 2. Notify the Contractor. 3. Require the Contractor to propose remedial measures for the analysed
noise problem. 4. Ensure remedial measures are properly implemented. 5. If exceedance continues, consider what activity of the work is
responsible and instruct the Contractor to stop that activity of work until
the exceedance is abated. |
1. Take immediate action to avoid further exceedance. 2. Submit proposals for remedial actions to IEC within 3 working days of
notification. 3. Implement the agreed proposals. 4. Resubmit proposals if problem still not under control. 5. Stop the relevant activity of works as determined by the ER until the
exceedance is abated. |
Water Quality
|
Event |
Action |
|||
|
ET Leader |
IEC |
ER |
Contractor |
|
|
Action Level |
|
|
|
|
|
1. Exceedance for one sample |
1. Repeat
in-situ measurement to confirm finding; 2. Identify
source(s) of impact; 3. Inform
IEC and Contractor; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with IEC and Contractor; and 6. Repeat
measurement on next day of exceedance. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC on the proposed mitigation measures; and 2. Make
agreement on the mitigation measures to be implemented. |
1. Inform
the ER and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and propose mitigation measures to IEC and ER; and 6. Implement
the agreed mitigation measures. |
|
2. Exceedance for two or more consecutive samples |
1. Repeat
in-situ measurement to confirm finding; 2. Identify
source(s) of impact; 3. Inform
IEC and Contractor; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with IEC and Contractor; 6. Ensure
mitigation measures are implemented; 7. Prepare
to increase the monitoring frequency to daily; and 8. Repeat
measurement on next day of exceedance. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC on the proposed mitigation measures; 2. Make
agreement on the mitigation measures to be implemented; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Inform
the Engineer and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and propose mitigation measures to IEC and ER within 3
working days; and 6. Implement
the agreed mitigation measures. |
|
Limit Level |
|
|
|
|
|
1. Exceedance for one sample |
1. Repeat
in-situ measurement to confirm finding; 2. Identify
source(s) of impact; 3. Inform
IEC, Contractor and EPD; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with IEC, ER and Contractor; 6. Ensure
mitigation measures are implemented; and 7. Increase
the monitoring frequency to daily until no exceedance of Limit level. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC, ET and Contractor on the proposed mitigation measures; and 2. Request
Contractor to critically review the working methods; 3. Make
agreement on the mitigation measures to be implemented; and 4. Assess
the effectiveness of the implemented mitigation measures. |
1. Inform
the Engineer and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and ER and propose mitigation measures to IEC and ER within 3
working days; and 6. Implement
the agreed mitigation measures. |
|
2. Exceedance for two or more consecutive samples |
1. Repeat
in-situ measurement to confirm finding; 2. Identify
source(s) of impact; 3. Inform
IEC, Contractor and EPD; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with IEC, ER and Contractor; 6. Ensure
mitigation measures are implemented; and 7. Increase
the monitoring frequency to daily until no exceedance of Limit level for two
consecutive days. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC, ET and Contractor on the proposed mitigation measures; and 2. Request
Contractor to critically review the working methods; 3. Make
agreement on the mitigation measures to be implemented; 4. Assess
the effectiveness of the implemented mitigation measures; and 5. Consider
and instruct, if necessary, the Contractor to slow down or to stop all or
part of the marine work until no exceedance of Limit Level. |
1. Inform
the ER and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and ER and propose mitigation measures to IEC and ER within 3
working days; 6. Implement
the agreed mitigation measures; and 7. As
directed by the Engineer, to slow down or to stop all or part of the marine
work or construction activities. |
Appendix E.
Calibration
certificates
|
Appendix F.
Graphical plots of the
monitoring results
|
Appendix G.
Weather conditions
during the monitoring period
|
Appendix H.
Ecological
Monitoring conducted in May 2010
|
|
May 2010 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
|
Mammals |
ü |
ü |
ü |
ü |
|
ü |
ü |
ü |
ü |
|
ü |
|
ü |
ü |
ü |
|
Birds |
ü |
|
|
|
|
ü |
|
|
|
|
|
|
ü |
|
|
|
Herpetofauna |
|
ü |
|
|
|
|
|
|
|
|
|
|
|
|
ü |
|
Dragonflies
& butterflies |
|
ü |
|
|
|
|
|
|
|
|
|
|
|
|
ü |
|
Inspection
Visits |
ü |
ü |
ü |
ü |
|
ü |
ü |
ü |
ü |
|
ü |
|
ü |
ü |
ü |
|
May 2010 |
27 |
28 |
29 |
30 |
31 |
|
Mammals |
ü |
ü |
ü |
|
ü |
|
Birds |
|
|
|
|
|
|
Herpetofauna |
|
|
|
|
|
|
Dragonflies
& butterflies |
|
|
|
|
|
|
Inspection
Visits |
ü |
ü |
ü |
|
ü |
*
Light grey cells indicated public holidays or Sundays.
Appendix I.
Summary of Bird Surveys
conducted in May 2010
|
|
|
Conservation
Status (2) |
May |
||
|
Species Name |
Scientific Name |
Survey (3) |
Mean (4) |
|
|
Little
Grebe |
Tachybaptus
ruficollis |
LC, (1) |
3 |
14.67 |
|
Great
Egret |
Egretta
alba |
PRC, (1) |
3 |
26.33 |
|
Intermediate Egret |
Egretta intermedia |
RC, (1) |
1 |
0.33 |
|
Little Egret |
Egretta
garzetta |
PRC, (1) |
3 |
71.67 |
|
Cattle Egret |
Bubulcus
ibis |
(LC), (1) |
2 |
2.00 |
|
Chinese Pond Heron |
Ardeola
bacchus |
PRC, (1) |
3 |
23.67 |
|
Black-crowned
Night Heron |
Nycticorax
nycticorax |
LC, (1) |
3 |
3.00 |
|
Black
Kite |
Milvus
migrans |
(RC) |
1 |
0.33 |
|
White-breasted
Waterhen |
Amaurornis
phoenicurus |
(1) |
3 |
4.33 |
|
Black-winged Stilt |
Himantopus himantopus |
RC, (1) |
1 |
0.67 |
|
Little
Ringed Plover |
Charadrius
dubius |
LC, (1) |
3 |
5.33 |
|
Common
Greenshank |
Tringa nebularia |
RC, (1) |
1 |
0.33 |
|
Common
Sandpiper |
Actitis
hypoleucos |
(1) |
3 |
5.67 |
|
Whiskered Tern |
Chlidonias hybridus |
(1) |
2 |
3.00 |
|
White-winged Tern |
Chlidonias leucopterus |
(1) |
1 |
14.00 |
|
Pied
Kingfisher |
Ceryle
rudis |
LC, (1) |
1 |
0.33 |
|
Common
Kingfisher |
Alcedo
atthis |
(1) |
3 |
3.33 |
|
Yellow
Wagtail |
Motacilla
flava |
(1) |
1 |
12.67 |
|
Oriental
Reed Warbler |
Acrocephalus
orientalis |
(1) |
1 |
0.33 |
|
Zitting
Cisticola |
Cisticola
juncidis |
LC, (1) |
2 |
1.33 |
|
White-shouldered
Starling |
Sturnus
sinensis |
(LC) |
3 |
3.67 |
|
|
|
|
21 |
|
(1) indicates wetland-dependant or -associated species.
(2) Conservation status follows that of Fellowes et al. (2002) and BirdLife International
listing (2010).
(3) indicates number of
surveys recorded within the survey period.
(4) equals the average
number of individual species surveyed in each survey (i.e. total counts in all
surveys divided by number of surveys)
Table J1. Summary of
herpetofauna surveys conducted between 12 and 31 May 2010
|
Species Name |
Scientific Name |
Conservation Status(1) |
May |
|
|
|
|
Survey(2) |
Mean(3) |
|
|
Amphibians |
|
|
1 |
|
|
Günther’s Frog |
Rana
guentheri |
- |
1 |
9.5 |
|
|
|
|
Survey(2) |
Mean(3) |
|
Reptile |
|
|
0 |
|
|
(No Records between 12 and
31 May 2010) |
||||
(1) Conservation status
follows that of Fellowes et al. (2002),
Chan et al. (2005) and Karsen et al. (1998).
(2)
indicates number of surveys recorded within the survey period.
(3) equals the average number of individual species
surveyed in each survey (i.e. total counts in all surveys divided by number of
surveys)
Table J2. Summary of mammal
observed conducted between 12 and 31 May 2010
|
Species
Name |
Scientific Name |
Conservation Status(1) |
May |
|
(No Records in May 2010) |
|||
Table J3. Summary of insect
surveys conducted between 12 and 31 May 2010
|
Common Name |
Scientific Name |
Conservation
Status(1) |
May |
|
|
|
|
Survey(2) |
Mean(3) |
|
|
Odonate |
|
|
13 |
|
|
Orange-tailed Sprite |
Ceriagrion auranticum |
|
1 |
0.5 |
|
Common
Bluetail |
Aschnura
senegalensis |
- |
1 |
4.5 |
|
Common
Flangetail |
Ictinogomphus
pertinax |
- |
1 |
0.5 |
|
Golden Flangetail |
Sinictinogomphus
clavatus |
|
1 |
0.5 |
|
Blue
Dasher |
Brachydiplax
chalybea |
- |
1 |
0.5 |
|
Asian Amberwing |
Brachythemis
contaminata |
- |
1 |
10 |
|
Crimson
Darter |
Crocothemis
servilia |
- |
1 |
0.5 |
|
Amber-winged
Glider |
Hydrobasileus
croceus |
- |
1 |
0.5 |
|
Coastal
Glider |
Macrodiplax
cora |
LC |
1 |
2.5 |
|
Green Skimmer |
Orthetrum sabina |
- |
1 |
3.5 |
|
Wandering Glider |
Pantala flavescens |
- |
1 |
1.5 |
|
Variegated
Flutterer |
Rhyothemis
variegata |
- |
1 |
4 |
|
Saddlebag Glider |
Tramea virginia |
- |
1 |
3.5 |
|
Butterfly |
|
|
5 |
|
|
|
Papilio paris |
|
1 |
0.5 |
|
Mottled Emigrant |
Catopsilia pyranthe |
- |
1 |
1 |
|
Red-base Jezebel |
Delias pasithoe |
- |
1 |
0.5 |
|
Indian Cabbage White |
Pieris canidia |
- |
1 |
1.5 |
|
Pale Grass Blue |
Zizeeria maha |
- |
1 |
3 |
|
Dark-brand
Bush Brown |
Mycalesis
mineus |
- |
1 |
1.5 |
(1) Conservation status
follows that of Fellowes et al.
(2002), Lo & Hui (2004), Wilson (2004) and Young & Yiu (2002).
(2)
indicates number of surveys recorded within the survey period.
(3) equals the average number of individual species
surveyed in each survey (i.e. total counts in all surveys divided by number of
surveys)