


Content
Chapter Title Page
List of Figures
Figure 1.1 General
Layout Plan of the Project Site
Figure 2.1 Locations of
Air Quality Monitoring Stations
Figure 2.2 Locations of
Noise Monitoring Stations
Figure 2.3 Locations of
Water Quality Monitoring Stations
Figure 4.1 Survey Area and
Transect Walked
List of Appendices
Appendix A Project Organization Chart
Appendix B Tentative Construction Programme
Appendix C Action and Limit Levels for Construction Phase
Appendix D Event and Action Plan for Air Quality, Noise and Water Quality
Appendix E Calibration certificates
Appendix F Graphical plots of the monitoring results
Appendix G Weather conditions during the monitoring period
Appendix H Ecological Monitoring conducted
Appendix I Summary of Bird Surveys conducted
Appendix J Summary of Herpetofauna, and Insects
Surveys conducted
Appendix K Summary of Monitoring of Water
Quality associated with Ecological Monitoring conducted
Appendix L Environmental
Mitigation Measures - Implementation Status
Executive Summary
Mott MacDonald
Hong Kong Ltd. (“MMHK”) has been commissioned by Heng Shung Construction Co.
Ltd. (The Contractor) to undertake the Environmental Team (ET) services to
carry out environmental monitoring and audit (EM&A) for both
pre-construction and construction phases of the Proposed Comprehensive
Development at Wo Shang Wai, Yuen Long.
This is the 33rd
EM&A report submitted under the Condition 4.5 of Environmental Permit No.
EP-311/2008/C. This report summarises the findings on EM&A during the
period from 1 to 31 January 2013.
Exceedance of Action and Limit
Levels
There was no
breach of Action or Limit levels for Air Quality (1-hr TSP and 24-hr TSP) and
Noise level (as Leq) in the reporting month.
Exceedances of pH,
DO and SS were observed at MP3 to MP6 in January 2013. Action Level exceedances
of pH were observed at MP5 and MP6. DO exceedance was observed once each at
MP3, MP4 and MP5. SS exceedance was recorded on one monitoring date at MP4 and
two monitoring dates at MP5. Exceedance of turbidity was recorded once each at
MP3, MP4 and MP5 during the reporting month.
The summary of measured water quality is
presented in Section 3.2.3.
Investigations have been carried out
to identify the causes of exceedance. From investigation, the Contractor has
implemented water quality mitigation measures as recommended in the EIA report.
With external factors affecting the adjacent
environments, such as natural variations and pond fish culture activities, the
exceedances were considered not due to construction works.
Implementation of mitigation
measures
Site audits were carried out on
8, 17, 22 and 30 January 2013 to
confirm the implementation measures undertaken by the Contractor in the
reporting month. The outcomes are presented in Section 6 and the status of implementation of mitigation measures
in the site is shown in Appendix L.
Record of Complaints
On 28 January 2013, a complaint was
lodged with the Environmental Protection Department (EPD) on dust impact near
Record of Notification of summons
and successful prosecution
There was no
record of Notification of summons and successful prosecution in the reporting
month.
Reporting Changes
There was no
reporting change in the reporting month.
Future Key Issues
The
major site works scheduled to be commissioned in the coming three months include
site
formation and foundation work. Potential environmental impacts due to the
construction activities, including air quality, noise, water quality, ecology
and landscape and visual, will be monitored.
Environmental mitigation measures will be
implemented on site as recommended and weekly site audits will be carried out
to ensure that the environmental conditions are acceptable.
In March 2005, the Project Proponent, Profit Point Enterprises Limited, acquired the development site at Wo Shang Wai in Yuen Long. An Environmental Impact Assessment (EIA) was then carried out and approved under the EIA Ordinance (EIAO), and the Environmental Permit (EP-311/2008) for construction of the comprehensive development in Wo Shang Wai was first granted by EPD on 9 September 2008 and has been subsequently varied, with the current version (EP-311/2008/C) issued by EPD on 2 November 2012.
The
Project involves the residential development and associated
infrastructure and wetland restoration area and linear
landscape area. The construction works under the Environmental Permit commenced
on 12 May 2010. The site formation construction works of the Wetland Restoration Area (hereafter WRA) were completed on 15 November
2010, while the 30-month establishment period of the WRA was concluded in
August 2012 – this indicated that planting works as scheduled in the approved
Wetland Restoration and Creation Scheme (WRCS; Nov 2009) was complete, except
along the western and southern boundary where the planting is affected by the
existing site boundary and noise barrier, and for which an approved Variation
to Environmental Permit (EP-311/2008/C) to defer planting at the location
applies.
Mott MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by the Contractor, Heng Shung Construction Co. Ltd., to undertake the Environmental Team (ET) services to carry out environmental monitoring and audit (EM&A) for both pre-construction and construction phases of the Proposed Comprehensive Development at Wo Shang Wai, Yuen Long.
According to the EP Condition 4.5, the monthly EM&A Report shall be submitted to the Director within two weeks after the end of the reporting month. This report summarises the findings during the period from 1 January to 31 January 2013.
The organization
chart and lines of communication with respect to the on-site environmental
management structure together with the contact information of the key personnel
are shown in Appendix A.
During the reporting period, construction works
of the Project undertaken include:
¡
Site formation
¡
Foundation
Work
The Construction Works Programme of the
Project is provided in Appendix B. The
general layout plan of the Project site is shown in Figure 1.1.
The EM&A programme requires environmental monitoring of air quality, noise, water quality, ecology and landscape and visual as specified in the approved EM&A Manual.
A summary of impact EM&A requirements is presented in Table 1.1:
Table 1.1: Summary of Impact EM&A Monitoring Requirements
|
Parameters |
Descriptions |
Locations |
Frequencies |
|
Air Quality |
24-Hour TSP |
ASR1, ASR2A, ASR3, ASR4 |
Once every 6 days |
|
1-Hour TSP |
ASR1, ASR2A, ASR3, ASR4 |
3 times every 6 days |
|
|
Noise |
Leq, 30min |
NSR1, NSR3, NSR5, NSR7 |
Weekly |
|
Water Quality |
Dissolved Oxygen (DO), temperature, pH, suspended solids (SS) and Biological Oxygen Demand (BOD) |
MP1 to MP6 |
3 days per week |
|
Ecology |
Birds |
Within the Project Area and Assessment Area of 500m |
Weekly |
|
Dragonflies and Butterflies |
Within the Project Area and Assessment Area of 500m |
Once per month during Mar and Sep to Nov, and twice per month during Apr to Aug |
|
|
Herpetofauna |
Within the Project Area and Assessment Area of 500m |
Once per month during Apr to Nov |
|
|
Water quality of Wetland Restoration Area (WRA) |
Wetland Restoration Area |
After filling of WRA with water, monthly for in situ water quality and every six months (end of wet season and end of dry season) for laboratory testing |
|
|
Site Inspections |
Within the Project Area and Assessment Area of 500m |
Weekly |
|
|
Landscape and Visual |
Auditing of protection of existing trees,
the transplanting of existing trees, the creation of new wetland, the
planting of new trees and shrubs and other landscape and visual mitigation
measures |
CM1 to CM10 and OM1 to OM7 within the
Project Area |
Site inspections once every two weeks
during construction phase; once every two months during operational phase |
The Environmental Quality Performance Limits for air quality, noise and water quality are shown in Appendix C.
The
Event and Action Plan for air quality, noise
and water quality are shown in Appendix D.
The monitoring schedule for the reporting
month is shown in Table 1.2 below:
Table 1.2: Environmental Monitoring and Audit Schedule for January 2013

2.
Impact Monitoring Methodology
|
For air
quality, construction noise and water quality, ecology,
landscape and visual monitoring methodology, including the monitoring
locations, monitoring equipments used, monitoring parameters, and frequency and
duration etc., are detailed in this Chapter.
In accordance with the EM&A Manual, 1-hour and 24-hour TSP levels monitoring are to be conducted during the construction phase. Table 2.1 summarizes the monitoring parameters, frequency and duration of air quality monitoring.
Table 2.1: Air Quality Monitoring Parameters, Frequency and
Duration
|
Parameter |
Frequency and Duration |
|
|
ASR1, ASR2A, ASR3 & ASR4 |
24-hour TSP |
At least once in every six-days |
|
1-hour TSP |
3 times every six-days |
The
four air quality monitoring stations were established in the EM&A manual
and were slightly adjusted during the baseline monitoring phase. Locations of
the agreed air quality monitoring stations are listed in Table 2.2 and as shown in Figure
2.1.
Table 2.2: Air Monitoring Stations
|
Monitoring Stations |
Locations |
|
ASR1 |
Works Site Boundary |
|
ASR2A |
At the rooftop of refuse collection point, which
is located at the southwest of the project area |
|
ASR3 |
At the commercial centre at |
|
ASR4 |
Works Site Boundary |
Continuous 24-hour TSP air quality
monitoring is
conducted using High Volume Sampler (HVS) (Model: GMWS-2310 Accu-vol). The HVS
meets all the requirements of the EM&A Manual. Portable direct reading dust
meters were used to carry out the 1-hour TSP monitoring. Table 2.3 summarizes the equipment used in the impact
air quality monitoring.
Table 2.3: TSP Monitoring Equipment
|
Equipment |
Model |
|
24-hr TSP monitoring |
|
|
High Volume
Sampler |
GMWS 2310
Accu-vol |
|
Calibrator |
GMW 25 |
|
1-hr TSP monitoring |
|
|
Portable direct
reading dust meter |
AM510 SidePak
Personal Aerosol Monitor Dust Trak 8520
& 8532 |
24-hour
TSP Monitoring
Installation
The HVS was installed in the vicinity of the air sensitive receiver. The following criteria were considered in the installation of the HVS.
· A horizontal platform with appropriate support to secure the sampler against gusty wind was provided.
· The distance between the HVS and any obstacles, such as buildings, was at least twice the height that the obstacle protrudes above the HVS.
· A minimum of two metres separation from walls, parapets and penthouse was required for rooftop sampler.
· A minimum of two metres separation from any supporting structure, measured horizontally was required.
· No furnace or incinerator flues or building vent were nearby.
· Airflow around the sampler was unrestricted.
· The sampler has been more than 20 metres from any drip line.
· Permission was obtained to set up the samplers and to obtain access to the monitoring stations.
· A secured supply of electricity is needed to operate the samplers.
Preparation of Filter Papers
· Glass fibre filters, were labelled and sufficient filters that were clean and without pinholes were selected.
· All filters were equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature was around 25 °C and not variable by more than ±3 °C with relative humidity (RH) < 50 % and was not variable by more than ±5 %. A convenient working RH was 40 %.
Field Monitoring
· The power supply was checked to ensure the HVS works properly.
· The filter holder and the area surrounding the filter were cleaned.
· The filter holder was removed by loosening the four bolts and a new filter, with stamped number upward, on a supporting screen was aligned carefully.
· The filter was properly aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.
· The swing bolts were fastened to hold the filter holder down to the frame. The pressure applied should be sufficient to avoid air leakage at the edges.
· The shelter lid was closed and was secured with the aluminium strip.
· The HVS was warmed-up for about 5 minutes to establish run-temperature conditions.
· A new flow rate record sheet was set into the flow recorder.
· The flow rate of the HVS was checked and adjusted at around 1.1 m3/min. The range specified in the EM&A Manual was between 0.6-1.7 m3/min.
· The programmable timer was set for a sampling period of 24 hrs + 1 hr, and the starting time, weather condition and the filter number were recorded.
· The initial elapsed time was recorded.
· At the end of sampling, the sampled filter was removed carefully and folded in half length so that only surfaces with collected particulate matter were in contact.
· It was then placed in a clean plastic envelope and sealed.
· All monitoring information was recorded on a standard data sheet.
· Filters were sent to a HOKLAS accredited laboratory for analysis.
Maintenance and Calibration
· The HVS and its accessories are maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.
· HVSs were calibrated at two-month intervals.
· Calibration records for HVSs are shown in Appendix E.
1-hour
TSP Monitoring
Field Monitoring
The measuring procedures of the 1-hour dust meter are in accordance with the Manufacturer’s Instruction Manual as follows:
·
Set POWER to “ON”, push
·
Push the knob at MEASU
· Push “O-ADJ” button. (Then meter’s indication is 0).
· Push the knob at SENSI ADJ position and set the meter’s indication to S value described on the Test Report using the trimmer for SENSI ADJ.
·
Pull out the knob and return it to MEASU
· Push “START” button.
Maintenance and Calibration
· The 1-hour dust meter would be checked at 3-month intervals and calibrated at 1-year intervals throughout all stages of the air quality monitoring.
· Calibration records for direct dust meters are shown in Appendix E.
Following the requirements in the EM&A Manual for noise, noise monitoring has to be carried out during the construction phase. Continuous noise monitoring for the A-weighted levels Leq, L10 and L90 is undertaken once per every week.
Table 2.4 summarizes the monitoring parameters, frequency and duration of air quality monitoring.
Table 2.4: Noise Monitoring Parameters, Frequency and Duration
|
Monitoring Stations |
Parameter |
Frequency and Duration |
|
NSR1, NSR3, NSR5, NSR7 |
Leq, L90 & L10 |
Once every week |
The
four noise
quality monitoring stations were established in the EM&A manual and were
slightly adjusted during the baseline monitoring phase. Locations of the agreed
noise
quality monitoring stations are listed in Table
2.5 and as shown in Figure
2.2.
Table 2.5: Noise Monitoring Stations
|
Monitoring Stations |
Locations |
Type of measurement |
|
NSR1 |
Noise monitoring equipment was set up near the
boundary wall at |
Free-field |
|
NSR3 |
The monitoring station was located next to the
guard house at |
Facade |
|
NSR5 |
The monitoring station was located within the work
site boundary. |
Free-field |
|
NSR7 |
The monitoring station was located near the
boundary wall of the house of Mai Po San Tsuen. |
Free-field |
Integrating Sound Level Meter will be used for noise monitoring. It is a Type 1 sound level meter capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx). They comply with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1). Table 2.6 summarizes the noise monitoring equipment model being used.
Table 2.6: Noise Monitoring Equipment
|
Monitoring Stations |
Equipment Model |
|
|
Integrating Sound
Level Meter |
Calibrator |
|
|
NSR1 |
Rion NL-31 |
Rion NC-73 |
|
NSR3 |
||
|
NSR5 |
||
|
NSR7 |
||
Field Monitoring
· The Sound Level Meter was set on a tripod at a height of at least 1.2 m above the ground.
· Façade and free-field measurements were made at the monitoring locations.
· The battery condition was checked to ensure the correct functioning of the meter.
· Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:
- frequency weighting: A
- time weighting: Fast
- time measurement: 30 minutes intervals (between 07:00 and 19:00)
· Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94 dB at 1 kHz. If the difference in the calibration level before and after measurement was more than 1 dB, the measurement would be considered invalid has to be repeated after re-calibration or repair of the equipment.
· During the monitoring period, the Leq, L10 and L90 were recorded. In addition, any site observations and noise sources were recorded on a standard record sheet.
Maintenance and Calibration
· The microphone head of the sound level meter and calibrator is cleaned with soft cloth at quarterly intervals.
·
The meter and calibrator are sent to the
supplier or HOKLAS laboratory to check and calibrate at yearly intervals.
·
Calibration records are shown in Appendix E.
In
accordance with the requirements in the EM&A Manual for water quality, water quality parameters including Dissolved Oxygen
(DO), temperature, pH, turbidity, suspended solids (SS) and Biochemical Oxygen
Demand (BOD) have to be monitored at designated monitoring stations during
construction of the Project. DO, temperature and
pH were measured in-situ whereas SS and BOD were analysed in a laboratory. The measurements should be taken at all designated monitoring
stations, three days per week. The interval between any two sets of monitoring
was not less than 36 hours. Table 2.7 summarizes
the monitoring parameters, frequency and duration of water quality monitoring.
Table 2.7: Water Quality Monitoring Parameters, Frequency and
Duration
|
Monitoring Stations |
Parameter |
Frequency and Duration |
|
MP1, MP2, MP3, MP4, MP5
& MP6 |
DO, temperature, pH, SS,
turbidity, BOD |
Three days every week |
The
six water quality monitoring stations were
established in the EM&A manual. Locations of the agreed water quality monitoring stations are listed in
Table 2.8
and as shown in Figure
2.3.
Table 2.8: Water Quality Monitoring Stations
|
Monitoring Stations |
Easting |
Northing |
|
MP1 |
838 730.50 |
822 862.25 |
|
MP2 |
838 933.26 |
823 247.41 |
|
MP3 |
839 107.17 |
823 596.84 |
|
MP4 |
839 286.14 |
823 638.55 |
|
MP5 |
839 134.35 |
823 722.99 |
|
MP6 |
839 063.02 |
823 842.25 |
The Water Quality Monitoring Equipments and Analytical Methods applied to Water Quality Samples are given in Table 2.9 and Table 2.10 respectively. Details of which are discussed below.
Table 2.9: Water Quality Monitoring Equipments
|
Equipment |
Model |
Equipment /Serial Number |
|
Conductivity, Dissolved oxygen, pH, Salinity and Temperature Measuring
Meter |
YSI Professional Plus |
10D101565, 10D101567 |
|
Turbidity Meter |
Hach 2100QIS |
11050C001264 |
|
|
Hach 2100Q |
12010C015757 |
|
Global Positioning System (GPS) |
Garmin eTrex
|
ENO 007 |
Table 2.10: Analytical Methods applied to Water Quality Samples
|
Determinant, unit |
Standard Method |
|
Total Suspended Solids, mg/L |
In house method based on APHA 2540D; ALS Method Code: EA-025 |
|
Biochemical Oxygen Demand (BOD), mg/L |
In house method based on APHA 5210B; ALS Method Code: EP-030 |
All
in-situ monitoring instruments were checked, calibrated and certified by a
laboratory accredited
under HOKLAS or any other international accreditation scheme before use.
Dissolved Oxygen (DO), temperature and pH measuring equipment
A portable, weatherproof multiparameter instrument (YSI Professional Plus) was used in the monitoring. It can be capable for measuring dissolved oxygen (DO), pH, and temperature simultaneously with the following limits:
· a dissolved oxygen level in the range of 0-50 mg/L and 0-500 % saturation;
· a temperature of -5 to 45 degree Celsius; and
· pH value of 0-14 with 0.1 as the base unit.
Turbidity
Measurement Instrument
Portable and weatherproof turbidity meter (HACH model 2100QIS / 2100Q) was used during impact monitoring. It has a photoelectric sensor capable of measuring turbidity between 0-1000 NTU. Response of the sensor was checked with certified standard turbidity solutions before the start of measurement.
Global
Positioning System
A
hand-held GPS navigator (Garmin eTrex
Suspended Solids and BOD Measurements (Sample
Containers and Storage)
Water samples for SS analysis were stored in
high density polythene bottles with no preservative added, packed in ice
(cooled to 4oC without being frozen), delivered to the laboratory,
and analysed as soon as possible after collection. Analysis was carried out in a
HOKLAS accredited laboratory.
Detection Limit
The limits of
detection for the in-situ and laboratory measurements are shown in Table
2.11.
Table 2.11: Detection Limits for Water Quality Determinants
|
Determinant |
Limit of Detection |
|
Dissolved Oxygen |
0.1 mg/L |
|
Temperature |
0.1 degree Celsius |
|
pH |
0.01 unit |
|
Turbidity |
0.1 NTU |
|
Suspended Solids |
1 mg/L |
|
BOD |
2 mg/L |
In situ measurement
All pH meters, DO/ temperature meters had
been checked and calibrated prior to use. Standard buffer solution of at least two
pH levels (either pH 4 and pH 7, or pH 7 and pH 10) had been used for
calibration of the instrument before and after use.
DO meters had been calibrated by a laboratory
accredited under HOKLAS or any other international accreditation scheme, and
subsequently re-calibrated at three-monthly intervals throughout all stages of
the water quality monitoring. Responses of sensors and electrodes had been
checked with certified standard solutions before each use. Wet bulb
calibrations for all DO meters had been carried out before measurement at each
monitoring location. For the on site calibration of field equipment, BS
127:1993, "Guide to field and on-site test methods for the analysis of
waters" had been observed.
Measurements shall be at three water depths,
namely, 1m below water surface, mid-depth and 1m above stream bed/pond bed,
except where the water depth less that 6m, the mid-depth
station maybe omitted. Should the water depth be less than 3m, only the
mid-depth station will be monitored.
Replicates in-situ measurements and samples
collected from each independent monitoring event are required for all
parameters to ensure a robust statistically interpretable dataset.
Water Samples Preparation and Analysis
For collection of water sampling within the
water courses, a 500ml clean plastic beaker was used. After collection, the
water samples were stored in high-density polythene bottles. The sample
container was rinsed with a portion
of the water sample. The water sample was then transferred to the container,
labelled with a unique sample ID and sealed with a
screw cap. The water samples were stored in a cool box maintained
at 4oC. The water samples were then delivered to a local
HOKLAS-accredited laboratory (ALS) on
the same day for analysis.
The testing methods of testing parameters as
recommended by EIA or required by EPD,
with the QA/QC results are in accordance with the requirement of HOKLAS or
international accredited scheme.
The calibration certificates for equipments used for in-situ
monitoring of water quality are attached in Appendix E.
Target species and certain other fauna will
be monitored within the Project Area and Assessment Area during the wetland and
residential construction phase. This will be important to ensure that any
unexpected events or impacts either on- or off-site are quickly identified so
that remedial action can be taken. The
groups to be monitored and frequency of monitoring are shown in Table 2.12.
Table 2.12: Summary of Construction Phase Ecological Monitoring
for the Wo Shang Wai Wetland Restoration Area (WRA)
|
Species / Parameter |
Construction Phase
Ecological Monitoring |
|
Birds |
Weekly (including Assessment Area). |
|
Dragonflies and Butterflies |
Once per month during March and September to November, and
twice per month during April to August. |
|
Herpetofauna |
Once per month during April to November. |
|
Water
Quality |
After filling of WRA with water, monthly for in situ water quality and every six
months (end of the wet season and end of the dry season) for laboratory
testing. |
|
Site Inspections |
Weekly. |
Ecological
monitoring locations during
construction phase are shown in Figure 4.1 and the methodology for ecological monitoring
is detailed in Section 4.
·
The extent of the agreed works area should be regularly
checked during the construction phase. Any trespass by the Contractor outside
the limit of the works, including any damage to existing trees and woodland
shall be noted;
·
The progress of the engineering works should be regularly
reviewed on site to identify the earliest practical opportunities for the
landscape works to be undertaken;
·
All existing vegetation, streams and other features within
the study area which are not directly affected by the works are retained and
protected;
·
The methods of protecting existing vegetation proposed by the
Contractor are acceptable and enforced;
·
Preparation, lifting transport and re-planting operations for
any transplanted trees;
·
The layout, design and construction of buildings conforms to
requirements specified in the EIA report;
·
All landscaping works are carried out in accordance with the
EIA recommendations and with specifications;
·
The planting of new trees, shrubs, groundcover, climbers,
grasses and other plans, together with the replanting of any transplanted trees
are carried out properly and within the right season;
·
All necessary horticultural operations and replacement
planting are undertaken throughout the Establishment Period to ensure the
healthy establishment and growth of both transplanted trees and all newly
establishment plants.
Table 2.13: Construction and Operation
Phase Audit Checklist
|
Area
of Works |
Items
to be Monitored |
|
Works Area |
Check the extent of the Works to ensure that the
Works Area is not exceeded |
|
Protection of all
trees and woodland blocks to be retained |
Identification and
demarcation of trees / vegetation to be retained, erection of physical
protection (e.g. fencing), monitoring against possible incursion, physical
damage, fire, pollution, surface erosion, etc. |
|
Streams |
Ensure no run-off
into existing streams |
|
Clearance of
existing vegetation |
Identification and
demarcation of trees / vegetation to be cleared, checking of extent of works
to minimize damage, monitoring of adjacent areas against possible incursion,
physical damage, fire, pollution, surface erosion, etc. |
|
Transplanting of
trees |
Identification and
demarcation of trees / vegetation to be transplanted, monitoring of extent of
pruning / lifting works to minimize damage, timing of operations
implementation of all stages of preparatory and translocation works, and
maintenance of transplanted vegetation, etc. |
|
Topsoil stripping |
Ensuring existing
topsoil is stripped and stored under recognized good practice and is
hydroseeded and regularly turned to prevent anaerobic conditions |
|
New buildings |
Ensure that
building finishes accord with mitigation proposals with regard to colour and
albedo. |
|
Boundaries |
Ensuring hoarding
are erected as required |
|
Noise Barrier |
Ensure noise
barrier design accords with the mitigation proposals with regard to location,
materials and finishes. |
|
Night-time
lighting |
Ensuring
night-time lighting is directional, hooded and shielded away from VSRs |
|
Plant supply |
Monitoring of
operations relating to the supply of specialist plant material (including the
collecting, germination and growth of plants from seed) to ensure that plants
will be available in time to be used within the construction works. |
|
Landscape and
wetland treatments generally |
Check that
wetland, and hard / soft landscape designs conform to intent of mitigation
measures and agreed designs |
|
Soiling, planting,
etc. |
Monitoring of
implementation and maintenance of soiling and planting works against possible
incursion, physical damage, fire, pollution, surface erosion, etc. |
|
Establishment
Works |
Monitoring of
implementation of maintenance operation during Establishment Period |
The monitoring locations should check
against the mitigation measures proposed under the approved Environmental Impact
Assessment, which are summarised as follows:
Table 2.14: Proposed Construction Phase
Mitigation Measures
|
ID No. |
Landscape and Visual Mitigation Measure |
|
CM1 |
The construction area and contractor’s temporary
works areas should be minimised to avoid impacts on adjacent landscape. |
|
CM2 |
Screening of construction works by hoardings/noise
barriers around Works area in visually unobtrusive colours, to screen Works. |
|
CM3 |
Reduction of construction period to practical
minimum. |
|
CM4 |
Topsoil, where identified, should be stripped and
stored for re-use in the construction of the soft landscape works, where the
soil material meets acceptable criteria and where practical. The Contract Specification shall include
storage and reuse of topsoil as appropriate. |
|
CM5 |
Hydroseeding or sheeting of soil stockpiles with
visually unobtrusive material (in earth tone). |
|
CM6 |
Advance screen planting to noise barriers. |
|
CM7 |
Control night-time lighting and glare by hooding all
lights. |
|
CM8 |
Ensure no run-off into streams adjacent to Project
Area. |
|
CM9 |
Protection of existing trees on boundary of project
area shall be carefully protected during construction. Detailed Tree Protection Specification
shall be provided in the Contract Specification. Under this specification,
the Contractor shall be required to submit, for approval, a detailed working
method statement for the protection of trees prior to undertaking any works
adjacent to all retained trees, including trees in contractor’s works areas. (Tree protection measures will be detailed
at S16 and Tree Removal Application stage). |
|
CM10 |
Trees unavoidably affected by the works shall be
transplanted where practical. Trees
should be transplanted straight to their destinations and not held in a nursery. A detailed Tree Transplanting Specification
shall be provided in the Contract Specification, if applicable. Sufficient
time for necessary tree root and crown preparation periods shall be allowed
in the project programme. |
Table 2.15: Proposed Operation Phase
Mitigation Measures
|
ID No. |
Landscape Mitigation Measure |
|
OM1 |
Compensatory Tree Planting for all felled trees shall
be provided to the satisfaction of relevant Government departments. Required numbers and locations of
compensatory trees shall be determined and agreed separately with Government
during the Tree Felling Application process under ETWBTC 3/2006. |
|
OM2 |
A continuous belt of screen planting along southern
perimeter of project area with fast growing tree species. At least 450 trees capable of reaching a
height > 10m within 10 years should be planted. Planting of the belt of trees shall be
carried out as advance works ahead of other site formation and building
works. |
|
OM3 |
Maximise soft landscape and amenity water bodies in
residential areas of the development.
Approximately 750 trees (of Heavy Standard size) should be
planted. Where space permits, roadside
berms should be created. Street trees should be of species that reach a
mature height of no less than 15m. |
|
OM4 |
Maximise freshwater habitat wetland creation
consistent with achieving other parameters.
Minimum 4.74 ha to be provided.
Wetlands must have natural edge profiles with >1m wide emergent
zone. No access to the wetland by
residents and all wetlands must be screened from residential development by a
continuous tree screen at interface with residential development or earth
mounding such that disturbance is minimised. Implementation of the wetland
shall be carried out as advance works. |
|
OM5 |
Use appropriate (visually unobtrusive and
non-reflective) building materials and colours in built structures. |
|
OM6 |
During detailed design, refine building layout to
create a min. 10m wide gap between buildings north of Wo Shang Wai pond and
also two min. 10m wide gaps in the row of buildings adjacent to Royal Palms. |
|
OM7 |
Streetscape elements (e.g. paving, signage, street
furniture, lighting etc.) shall be sensitively designed in a manner that
responds to the local context, and minimises potential negative landscape and
visual impacts. Lighting units should
be directional and minimise unnecessary light spill. |
Impact
monitoring for air quality (dust), noise and water quality due to the
construction work were undertaken during the reporting month in compliance with
the EM&A manual in the reporting period. Regular site inspections were
carried out on 8, 17, 22 and 30 January 2012 in
the reporting month to assess the compliance with environmental requirements.
Results of 1-hour TSP at the four monitoring locations are summarised in Table 3.1. Graphical plots of the monitoring results are shown in Appendix F. The weather conditions in the reporting period are provided in Appendix G.
Table 3.1: Summary
of 1-hour TSP Monitoring Results
|
Monitoring Date |
Start Time |
1-hr TSP (μg/m3) |
Range (μg/m3) |
Action Level
(μg/m3) |
Limit Level
(μg/m3) |
|||
|
1st
Result |
2nd
Result |
3rd
Result |
||||||
|
ASR1 |
||||||||
|
02-Jan-13 |
13:13 |
100 |
122 |
114 |
100 – 150 |
378 |
500 |
|
|
08-Jan-13 |
13:29 |
104 |
108 |
116 |
||||
|
14-Jan-13 |
13:11 |
132 |
150 |
144 |
||||
|
18-Jan-13 |
13:20 |
106 |
113 |
128 |
||||
|
24-Jan-13 |
13:09 |
110 |
106 |
100 |
||||
|
30-Jan-13 |
13:15 |
102 |
112 |
108 |
||||
|
ASR2A |
||||||||
|
02-Jan-13 |
12:48 |
106 |
112 |
120 |
102 – 162 |
357 |
500 |
|
|
08-Jan-13 |
12:46 |
102 |
114 |
118 |
||||
|
14-Jan-13 |
12:49 |
162 |
150 |
142 |
||||
|
18-Jan-13 |
12:49 |
120 |
114 |
103 |
||||
|
24-Jan-13 |
12:47 |
126 |
120 |
118 |
||||
|
30-Jan-13 |
12:47 |
110 |
122 |
118 |
||||
|
ASR3 |
||||||||
|
02-Jan-13 |
12:33 |
112 |
106 |
118 |
104 – 160 |
358 |
500 |
|
|
08-Jan-13 |
12:33 |
106 |
114 |
120 |
||||
|
14-Jan-13 |
12:33 |
152 |
160 |
148 |
||||
|
18-Jan-13 |
12:34 |
108 |
114 |
122 |
||||
|
24-Jan-13 |
12:33 |
122 |
112 |
104 |
||||
|
30-Jan-13 |
12:33 |
120 |
118 |
106 |
||||
|
ASR4 |
||||||||
|
02-Jan-13 |
13:06 |
130 |
128 |
124 |
102 – 177 |
372 |
500 |
|
|
08-Jan-13 |
13:22 |
102 |
116 |
122 |
||||
|
14-Jan-13 |
13:05 |
152 |
168 |
177 |
||||
|
18-Jan-13 |
13:07 |
134 |
126 |
116 |
||||
|
24-Jan-13 |
13:03 |
130 |
118 |
126 |
||||
|
30-Jan-13 |
13:05 |
126 |
122 |
118 |
||||
Results of 24-hour TSP at the four monitoring locations are summarised in Table 3.2. Graphical plots of the monitoring results are shown in Appendix F. The weather conditions in the reporting period are provided in Appendix G.
Table 3.2: Summary
of 24-hour TSP Monitoring Results
|
Monitoring Date |
Monitoring Results
(μg/m3) |
Range (μg/m3) |
Action Level
(μg/m3) |
Limit Level
(μg/m3) |
|
ASR1 |
|
|
|
|
|
02-Jan-13 |
85 |
85 – 98 |
226 |
260 |
|
08-Jan-13 |
87 |
|||
|
14-Jan-13 |
85 |
|||
|
18-Jan-13 |
98 |
|||
|
24-Jan-13 |
93 |
|||
|
30-Jan-13 |
92 |
|||
|
ASR2A |
|
|
|
|
|
02-Jan-13 |
93 |
86 – 98 |
213 |
260 |
|
08-Jan-13 |
86 |
|||
|
14-Jan-13 |
92 |
|||
|
18-Jan-13 |
98 |
|||
|
24-Jan-13 |
96 |
|||
|
30-Jan-13 |
95 |
|||
|
ASR3 |
|
|
|
|
|
02-Jan-13 |
83 |
82 – 97 |
205 |
260 |
|
08-Jan-13 |
92 |
|||
|
14-Jan-13 |
82 |
|||
|
18-Jan-13 |
97 |
|||
|
24-Jan-13 |
90 |
|||
|
30-Jan-13 |
90 |
|||
|
ASR4 |
|
|
|
|
|
02-Jan-13 |
90 |
90 – 102 |
237 |
260 |
|
08-Jan-13 |
97 |
|||
|
14-Jan-13 |
94 |
|||
|
18-Jan-13 |
100 |
|||
|
24-Jan-13 |
102 |
|||
|
30-Jan-13 |
94 |
No exceedance of 1-hour and 24-hour TSP (Action or Limit Level) was recorded in the reporting period.
The construction noise monitoring results are summarized in Table 3.3. Graphical plots of the monitoring data are shown in Appendix F. The weather conditions in the reporting period are provided in Appendix G.
Table 3.3: Summary
of Construction Noise
Monitoring Results
|
Monitoring Date |
Start Time |
Mean & Range
of Noise Levels, dB(A) |
Limit Level for Leq
(dB) |
||
|
Leq |
L10 |
L90 |
|||
|
NSR1 |
|
|
|
|
> 75 |
|
02-Jan-13 |
14:46 |
56 |
58 |
48 |
|
|
08-Jan-13 |
15:41 |
59 |
62 |
51 |
|
|
14-Jan-13 |
14:50 |
59 |
62 |
53 |
|
|
24-Jan-13 |
14:38 |
57 |
59 |
48 |
|
|
30-Jan-13 |
13:20 |
59 |
61 |
55 |
|
|
NSR3 |
|
|
|
|
|
|
02-Jan-13 |
15:27 |
56 |
59 |
52 |
|
|
08-Jan-13 |
15:01 |
57 |
62 |
52 |
|
|
14-Jan-13 |
15:30 |
51 |
57 |
55 |
|
|
24-Jan-13 |
13:58 |
55 |
58 |
51 |
|
|
30-Jan-13 |
15:02 |
56 |
58 |
46 |
|
|
NSR5 |
|
|
|
|
|
|
02-Jan-13 |
13:16 |
54 |
57 |
48 |
|
|
08-Jan-13 |
13:38 |
57 |
60 |
56 |
|
|
14-Jan-13 |
13:15 |
56 |
60 |
59 |
|
|
24-Jan-13 |
13:12 |
59 |
62 |
56 |
|
|
30-Jan-13 |
15:45 |
51 |
53 |
46 |
|
|
NSR7 |
|
|
|
|
|
|
02-Jan-13 |
13:59 |
68 |
71 |
66 |
|
|
08-Jan-13 |
14:19 |
65 |
68 |
58 |
|
|
14-Jan-13 |
14:00 |
62 |
68 |
66 |
|
|
24-Jan-13 |
13:54 |
68 |
71 |
67 |
|
|
30-Jan-13 |
14:10 |
64 |
67 |
60 |
|
No exceedance (Action/Limit Level) of construction noise was recorded in the reporting period.
The water quality monitoring results are summarized in Table 3.4. Graphical plots of the monitoring data are shown in Appendix F. The weather conditions in the reporting period are provided in Appendix G.
Table 3.4: Summary of Water Quality Monitoring Results
|
Monitoring Date |
Temp (oC) |
pH |
Dissolved Oxygen (DO) (mg/L) |
DO (%) |
Turbidity (NT) |
BOD (mg/L) (1) |
Suspended Solids
(mg/L) |
|
MP3 |
|
|
|
|
|
|
|
|
02/01/2013 |
15.2 |
7.1 |
9.6 |
95.6 |
44.8 |
4 |
43 |
|
04/01/2013 |
14.9 |
7.3 |
10.7 |
105.9 |
30.0 |
3.5 |
19 |
|
07/01/2013 |
16.2 |
7.3 |
7.8 |
81.4 |
44.0 |
6 |
42 |
|
09/01/2013 |
14.8 |
7.4 |
7.8 |
78.4 |
42.4 |
3 |
47.5 |
|
11/01/2013 |
18.7 |
7.3 |
7.1 |
84.9 |
72.3 |
4 |
62 |
|
14/01/2013 |
20.1 |
7.3 |
8.5 |
102.8 |
33.1 |
<2 |
28 |
|
16/01/2013 |
21.2 |
7.3 |
8.5 |
96.0 |
23.4 |
5.5 |
18 |
|
18/01/2013 |
16.5 |
7.2 |
6.9 |
76.1 |
46.6 |
7 |
40.5 |
|
21/01/2013 |
24.6 |
7.3 |
7.2 |
81.9 |
58.9 |
14.5 |
40 |
|
23/01/2013 |
18.9 |
7.3 |
5.9 |
63.9 |
53.2 |
4.5 |
34 |
|
25/01/2013 |
22.3 |
7.2 |
7.2 |
85.2 |
38.7 |
7.5 |
29.5 |
|
28/01/2013 |
18.4 |
7.3 |
7.0 |
81.9 |
37.7 |
7.5 |
30.5 |
|
30/01/2013 |
21.4 |
7.3 |
7.8 |
90.8 |
36.3 |
9.5 |
26.5 |
|
Action Level |
- |
<5.5 or >7.5 |
<6.85 |
- |
>64 |
- |
>65 |
|
Limit Level |
- |
<4.0 or >8.0 |
<6.65 |
- |
>67 |
- |
>66 |
|
|
|
|
|
|
|
|
|
|
MP4 |
|
|
|
|
|
|
|
|
02/01/2013 |
15.3 |
7.3 |
8.7 |
88.0 |
13.0 |
3 |
12 |
|
04/01/2013 |
16.4 |
7.2 |
2.2 |
22.4 |
14.1 |
<2 |
8 |
|
07/01/2013 |
15.4 |
7.5 |
8.8 |
90.1 |
11.7 |
4 |
26.5 |
|
09/01/2013 |
14.5 |
7.3 |
5.8 |
56.7 |
12.8 |
<2 |
22.5 |
|
11/01/2013 |
18.5 |
7.2 |
8.2 |
97.9 |
12.3 |
4 |
15 |
|
14/01/2013 |
20.4 |
7.4 |
8.2 |
97.3 |
14.6 |
3 |
18 |
|
16/01/2013 |
21.0 |
7.2 |
7.4 |
88.0 |
27.2 |
4.5 |
24 |
|
18/01/2013 |
16.3 |
7.3 |
7.2 |
83.0 |
98.4 |
10.5 |
68 |
|
21/01/2013 |
24.2 |
7.4 |
6.9 |
77.0 |
37.1 |
5 |
30.5 |
|
23/01/2013 |
19.0 |
7.4 |
7.2 |
81.9 |
29.4 |
2.5 |
16 |
|
25/01/2013 |
22.5 |
7.4 |
7.8 |
91.9 |
16.5 |
3 |
12 |
|
28/01/2013 |
18.7 |
7.5 |
7.8 |
90.9 |
16.7 |
2.5 |
13.5 |
|
30/01/2013 |
21.2 |
7.4 |
9.3 |
113.9 |
14.2 |
3 |
10 |
|
Action Level |
- |
<5.5 or >7.5 |
<3.91 |
- |
>60 |
- |
>50 |
|
Limit Level |
- |
<4.0 or >8.0 |
<3.82 |
- |
>64 |
- |
>53 |
|
|
|
|
|
|
|
|
|
|
MP5 |
|
|
|
|
|
|
|
|
02/01/2013 |
15.5 |
7.4 |
9.1 |
92.3 |
40.9 |
4 |
55 |
|
04/01/2013 |
15.4 |
7.3 |
3.9 |
39.6 |
25.8 |
2 |
34.5 |
|
07/01/2013 |
14.9 |
7.4 |
8.6 |
86.9 |
34.0 |
5 |
67 |
|
09/01/2013 |
14.8 |
7.3 |
5.8 |
56.7 |
32.7 |
3 |
84.5 |
|
11/01/2013 |
18.6 |
7.4 |
7.4 |
89.0 |
15.7 |
6 |
13 |
|
14/01/2013 |
20.2 |
7.6 |
8.6 |
105.3 |
12.9 |
<2 |
11 |
|
16/01/2013 |
21.1 |
7.3 |
8.5 |
102.1 |
17.3 |
3 |
14 |
|
18/01/2013 |
16.6 |
7.4 |
6.9 |
76.5 |
91.3 |
11.5 |
65 |
|
21/01/2013 |
24.2 |
7.4 |
7.1 |
80.2 |
40.5 |
8 |
30.5 |
|
23/01/2013 |
18.9 |
7.4 |
6.7 |
75.8 |
31.1 |
3 |
22.5 |
|
25/01/2013 |
22.3 |
7.5 |
7.2 |
87.2 |
25.1 |
4.5 |
19 |
|
28/01/2013 |
18.8 |
7.5 |
7.9 |
92.8 |
19.6 |
6.5 |
30 |
|
30/01/2013 |
21.2 |
7.5 |
9.1 |
108.0 |
19.7 |
4.5 |
16.5 |
|
Action Level |
- |
<5.5 or >7.5 |
<4.13 |
- |
>81 |
- |
>66 |
|
Limit Level |
- |
<4.0 or >8.0 |
<3.87 |
- |
>84 |
- |
>69 |
|
|
|
|
|
|
|
|
|
|
MP6 |
|
|
|
|
|
|
|
|
02/01/2013 |
15.4 |
7.4 |
9.2 |
93.7 |
14.8 |
3.5 |
18.5 |
|
04/01/2013 |
16.6 |
7.4 |
6.6 |
68.3 |
12.6 |
3 |
59 |
|
07/01/2013 |
14.8 |
7.4 |
8.7 |
87.8 |
15.6 |
7 |
15 |
|
09/01/2013 |
14.2 |
7.3 |
5.6 |
54.7 |
14.2 |
2.5 |
14.5 |
|
11/01/2013 |
18.4 |
7.4 |
7.6 |
91.9 |
11.7 |
6.5 |
17.5 |
|
14/01/2013 |
19.9 |
7.6 |
8.2 |
98.7 |
12.4 |
<2 |
11 |
|
16/01/2013 |
21.3 |
7.4 |
8.4 |
96.7 |
16.3 |
3.5 |
12 |
|
18/01/2013 |
16.3 |
7.5 |
7.6 |
92.0 |
57.5 |
6 |
39 |
|
21/01/2013 |
24.3 |
7.5 |
7.9 |
95.9 |
27.3 |
4 |
20.5 |
|
23/01/2013 |
19.1 |
7.5 |
7.8 |
91.9 |
17.8 |
3 |
13.5 |
|
25/01/2013 |
22.3 |
7.5 |
8.6 |
101.9 |
10.5 |
<2 |
6 |
|
28/01/2013 |
18.5 |
7.6 |
8.3 |
97.4 |
21.9 |
5.5 |
33 |
|
30/01/2013 |
21.3 |
7.5 |
11.2 |
135.6 |
8.5 |
<2 |
3.5 |
|
Action Level |
- |
<5.5 or >7.5 |
<4.61 |
- |
>94 |
- |
>75 |
|
Limit Level |
- |
<4.0 or >8.0 |
<4.52 |
- |
>96 |
- |
>75 |
Notes:
(1)
“<2 “ : BOD value is too low to indicate (<2mg/L).
(2)
Values Bold
indicate Action Level exceedance.
(3)
Values Underlined
and Bold indicate Limit Level exceedance.
Exceedance Investigation and Findings
Exceedances of pH, DO and SS were observed at MP3
to MP6 in January 2013. Action Level exceedances of pH were observed at MP5 and
MP6. DO exceedance was observed once each at MP3, MP4 and MP5. SS exceedance
was recorded on one monitoring date at MP4 and two monitoring dates at MP5.
Exceedance of turbidity was recorded once each at MP3, MP4 and MP5 during the
reporting month.
The Event and Action Plan in Appendix D was
followed under these cases of exceedances.
From investigation, construction activities
during the period of exceedance included mainly site formation and foundation
work. It was observed that the Contractor has implemented water quality
mitigation measures as recommended in the EIA report, including the provision
of temporary drainage facility and associated treatment facility. Sand bags are
in place in the temporary drainage channel to enhance the desilting efficiency.
The Contractor further enhanced the water quality mitigation measures by
erecting several segments of rock bunds at the discharge outlet to avoid site
runoff draining directly to the northern ditches.
Exceedances
of DO, turbidity and SS at MP3
Exceedances
of the Action Level of pH were not observed, while Limit Level exceedance of DO
was recorded on one monitoring date at MP3. Also, Limit Level exceedance of
turbidity was observed on one monitoring date but SS exceedance was not
observed at MP3. As understood, the fish pond near the site (represented by
MP3) was being separated from the construction site by the WRA since November
2010, so the exceedances were not considered to be related to the construction
activities. The exceedances of DO, turbidity and SS may be due to external
factors such as pond fish culture activities which were out of the control of
the project.
Exceedances
of pH, DO, turbidity and SS at MP4 to MP6
A total of three exceedances of
Action Level of pH were observed at MP5 on 14 January 2013 and at MP6 on 14 and
28 January 2013. Action/Limit Levels of DO were exceeded once on the same
monitoring date (4 January 2013) at each of MP4 and MP5. Limit Level exceedance
of turbidity was observed on the same monitoring date (18 January 2013) at MP4
and MP5. Action/Limit Level exceedance of SS was observed at MP4 on 18 January 2013 and at MP5 on 7 and
9 January 2013.
From Hong Kong
Observatory (HKO) records, total rainfall recorded at HKO during the reporting
month was 3.4 mm, which was below the 1981-2010 climatological normal for the
same month of 24.7 mm. The heaviest rain fell on 26 January 2013 when 2.8 mm of
rain was recorded at HKO. Also, no Strong Monsoon Signal, Rainstorm Warning
signal, Special Announcement on Flooding in the northern
No rain was
recorded by HKO on the days of turbidity and/or SS exceedance. The cause for these exceedances may have been
fish movements.
Starting from early May 2011, the DO measured at the ditch
has fallen significantly due to microbe growth (including algae). The ditch
continued to be affected by this factor (respiration and degradation of
microbes which consumed oxygen). However, on sunny days, photosynthesis of the
algae sometimes increases the DO sharply in the water. As algae grows
further and dies, it may lead to an increase in suspended solids and a decrease
in DO in the water.
The
recorded exceedances of pH during the reporting period could be due to
natural variations as the values were slightly outside the acceptable pH range
stated in the EM&A Manual. Also, the site effluent was effectively treated by the
AquaSed system and discharged from the site at a low, controlled rate during
the reporting month.
Conclusion
As a result, the abovementioned exceedances are
unlikely to be due to the construction works and therefore not considered to be
related to the project.
This report documents surveys
conducted in the Survey Area between 1 and 31 January 2013. The Wetland
Restoration Area (WRA) is also surveyed as the area is accessible and site
formation works for WRA has been completed.
The updated survey transect is provided in Figure 4.1. Dates and ecological surveys conducted during this period are
summarised in Appendix H.
Monitoring was undertaken following
the survey methodology in the EM&A Manual. A transect was followed in the
bird surveys (see Figure 4.1). All bird species were identified to species and all bird species of
conservation importance and/or wetland dependent were enumerated and recorded
to the habitats in which they were observed. Flying birds were not recorded
unless they were foraging and/or associated with the habitat (such as swifts).
Further, notable bird observations during other surveys were also recorded.
Bird surveys were conducted on a
weekly basis. In the
Survey Area (excluding WRA), 24 bird species of
conservation importance and/or wetland-dependence were recorded. Within the
WRA, 15 bird species of conservation importance and/or wetland-dependent
species were recorded, including two of the target species (i.e. Little Egret
and Chinese Pond Heron). A summary of survey data is provided in Appendix I.
No
herpetofauna surveys were scheduled in the period. No amphibian species or
reptile species were recorded in other surveys.
No
Odonates and Butterflies surveys were scheduled in the reporting month.
Monitoring of
mammals was conducted concurrently with other surveys. No mammals species was
recorded in other survey.
A small
During
the reporting period, pH of Cells 1, 2 and 4 reached the Action Level. No
measures are proposed at the moment, but the condition will be monitored. Monitoring data are
presented in Appendix K.
Removal
of exotic vegetation in all cells was undertaken; these included but not
limited to Ipomoes sp. and Pennisetum sp.
The routine vegetation management
activities undertaken at the site primarily involved watering of plants, tree
pruning, weeding and grass cutting.
Removal of
Golden Apple Snail was undertaken on an “as-seen” basis.
All
sighted red fire ant nests were treated with approved pesticide.
Ecological monitoring during January 2013 was carried out according to
the survey methodology and frequency outlined in the EM&A Manual.
Summary of survey findings is listed
as follows:
Table 4.1: Summary of Ecological Monitoring in WRA and Survey Area
|
Species |
Survey Area (excluding WRA) |
WRA |
|
Birds of conservation importance and/or
wetland-dependence |
24 |
17 |
|
Amphibians |
* |
* |
|
Reptiles |
* |
* |
|
Mammals |
0 |
0 |
|
Odonates |
* |
* |
|
Butterflies |
* |
* |
Note: * Survey for this species was not conducted during the reporting month.
Survey
findings indicate that the ponds within the Survey Area supported numbers and
diversity of wetland-dependent birds typical of fish pond areas. The WRA continues to attract wetland
dependent fauna and serves as a buffer between the residential portion and the
fishponds in the north.
The EM&A programme for Landscape and
Visual impact due to the construction commenced in May 2010 and continued
during the reporting period. Site inspections on Landscape and Visual impact were
carried out on 14 January and 1 February 2013 to confirm the implementation of
mitigation measures at construction stage.
The audit
was undertaken with references to the specific checklists provided in Tables 2.13 – 2.15 and audit results
are summarized as below:
Table 5.1: Construction and Operation Phase Audit Summary
|
Area
of Works |
Items
to be Monitored |
|
Works Area |
The
boundaries of the works area have been established on site in accordance
with the contract documents and approved plans (EP), and the limit of
current heavy construction activity is now confined to within the site
hoardings (North side of the site / access road) and the noise barriers
(other sides of the site). Minor works such as horticultural maintenance of
the planting and transplanted trees, and boundary fence repair was
proceeding along the Royal Palms - No construction works were
observed to have exceeded the site boundaries. No construction was carried out at the wetland restoration area after 15 November 2010. |
|
Protection of all trees and
woodland blocks to be retained |
Trees retained within the
site along the northeast boundary, beside wetland restoration area, have
been identified and protected by temporary protective fencing. |
|
Streams |
The works site is partly
encircled by a berm / perimeter channel to intercept surface water and
prevent it from washing off into any of the neighboring sites. Surface water is collected within the site
in a temporary drainage channel.
Gravels beds and barriers have been installed to filter site runoff,
sedimentation ponds have been provided to enable primary treatment before
discharge to mains drains. |
|
Clearance of existing vegetation |
Site clearance was completed
prior to the commencement of construction.
|
|
Transplanting of trees |
Tree transplanting has been
completed, with the trees relocated to various points within the planting
strip along the southern boundary of the site, outside the noise
barrier. The trees continue to
re-establish well. |
|
Topsoil stripping |
Suitable pond bund and soil material which had been excavated and
stockpiled from the original site, has now been re-used within the landscape
works Dust suppression measures are
active along all internal site access tracks. |
|
New buildings |
No new permanent buildings
have yet been constructed on site |
|
Boundaries |
Hoardings have been erected
along most of the boundaries of the site.
Installation of new screen fence between the future residential sites
and the constructed wetland restoration areas is complete. Fence has been
painted green to match with the surrounding vegetated environment. |
|
Noise Barrier |
Noise barriers have been
installed along the southern and western boundaries of the site in
accordance with the contract requirements.
Their design complies with the mitigation requirements, with upper 6
to 7m portion of the barrier being made from a translucent material with
green tinted (to match with the environment). Supporting GMS structure,
likewise, has been painted green. |
|
Night-time lighting |
No night-time works were
reported to have been carried out during the monitoring period |
|
Landscape and wetland treatments
generally |
Continuous belt of screen planting along the southern and western
boundaries of the site has been completed.
The formation, soiling and water control structures of the wetland
restoration area have been completed. The wetland areas are being
established, with the ponds are being seasonally filled with rain
water. Planting of areas around the
WRA cells is complete. No
construction was carried out at the wetland restoration area after 15
November 2010. |
|
Soiling, etc. |
The soiling for the advance
planting strip has been completed.
The soil placement and grading for each of the wetland restoration
areas has been completed. |
|
Plant supply |
The plant material used in the Advance Planting Strip and in the WRA
are all commonly available species and came from commercial sources. Transplanted reeds (Phragmites
australis) at the wetland habitat came from the temporary holding
nursery onsite. |
|
Planting |
The total number of trees that will reach a minimum of 10m in the
advance planting strip meets the contract requirements. The tree species are all from the approved
list. This planting should achieve the
required screening effect within the required time period. Some of the trees that were identified as dead in previous month or
having defects (i.e. extensive bark damage, cavities, fungal growths etc)
still need to be replaced with new specimens. Some of the recently planted
trees are still in poor condition, but are showing small signs of graduate
improvement Seedling trees and shrubs,
have been established at the margins of the wetland cells. Some additional
fill-in planting has been undertaken. |
|
Establishment
Works |
The advance planting, the compensatory planting and transplanted
trees are generally in accordance with the specification. Some of the taller trees (Eucalyptus
sp.) that had been partially blown over, or are growing into the noise
barrier structure, have been set upright and supported with rope cables and
bamboo stakes, but many trees still need to be
rectified. Precautions should be
taken to prevent damage to the trees by the structure. Trees (T21 and T364) have lost
their leader and are no longer viable, so should be removed and replaced. Branches broken during the typhoon
on trees have been pruned away. Workmanship of some pruning works did not
comply with proper arboricultural practice resulting in bark tearing. A number of trees are missing/
removed, and their replacement remains outstanding. T 400 have been replaced
with juvenile specimen which is unlikely to meet EP requirements. T98, T117 and T136 have been replaced with
new Acacia mangium trees. Profuse fungal growth was noted on trunk
of T292. Tree is irreparably damaged / rotten and should be removed and
replaced immediately. Some of the trees from outside the
site which fell on top of trees in the advance planting strip, have been
removed but no rectification of affected trees has been undertaken. Low coverage of some areas of shrubs need to be rectified with
further infill shrubs planting. Minor
areas of shrubs have been cleared and these need to be replaced. Pruning of tall shrubs (e.g. Ligustrum
sinensis) needs to be undertaken Extensive areas of weeds and invasive climbers still exist in the
space behind screen noise barrier which may be inhibiting the advance
planting. Complete clearance needs to
be carried out on a monthly basis. Regular horticultural maintenance (grass cutting, weeding, watering
etc.) in the shrubs and tree seedling areas around the WRA cells is being
undertaken, but needs to continue on a regular basis. Phragmites australis reeds (translocated from the
original site) had been partially cleared but are still
growing profusely and urgently need active management. Hydroseeded grass has been established along the access path around
the WRA cells. The trees / shrubs planted
along the northern site boundary are in good condition. Growth of shrubs / seedlings on the north
side of WRA1 is, however, unsatisfactory. Big broken branch noted on tree behind the
newly planted shrubs near WRA cell 4. Big hanger noted on T266 and should be
removed immediately. |
The ET had carried out construction phase
weekly site inspections on 8, 17, 22 and 30 January 2013. All observations have
been recorded in the site inspection checklist and passed to the Contractor
together with the appropriate recommended mitigation measures where necessary.
The key observations from site inspections and associated recommendations are
summarized in Table 6.1.
Table 6.1: Summary of Site Inspections and Recommendations
|
Key
Observations |
ET Recommendation |
Contractor’s Responses / Action(s) Undertaken |
Close-out (Date) |
|
Stockpile of construction waste
was not covered |
To cover stockpile with tarpaulin
covering |
Agreed and followed up |
22 Jan 2013 |
|
Oil stain was observed on the
ground |
To remove oil stain and handle any
affected soil as chemical waste |
Agreed and followed up |
22 Jan 2013 |
|
Dry haul road observed at southern
site boundary |
To improve frequency of water
spray as necessary |
Agreed and followed up |
30 Jan 2013 |
|
Oil stain (fuel) was observed on
the ground |
To remove oil stain and handle any
affected soil as chemical waste |
Agreed and followed up |
5 Feb 2013 |
|
General refuse bins were full |
To clear general refuse bins |
Agreed and followed up |
30 Jan 2013 |
|
Refuse stockpile observed |
To clear refuse at regular
intervals |
Agreed and followed up |
5 Feb 2013 |
|
Air compressor without noise
emission label |
To provide noise emission label |
Agreed and followed up |
5 Feb 2013 |
The Contractor has been registered as a
chemical waste producer for the Project. Construction and demolition (C&D)
material sorting was carried out on site. A sufficient number of receptacles were
available for general refuse collection.
As advised by the Contractor, no
C&D material was generated on site during the period. No metals was
generated and collected by registered recycling collector. No paper cardboard
packing and plastic were generated on site and collected by registered
recycling collector. No chemical waste was generated and collected by licensed
chemical waste collector. 7.1 tonnes of other types
of wastes (e.g. general refuse) was generated on site and disposed of at public
landfill facility.
The Contractor is advised to maintain on
site waste sorting and recording system and maximize reuse/recycling of C&D
wastes.
The environmental permits, licenses, and/or
notifications on environmental protection for this Project which were valid during
the reporting period is summarised in Table
6.2.
Table 6.2: Status of Environmental Submissions, Licenses and Permits
|
Statutory Reference |
Description |
Permit/Reference
No. |
Status |
|
EIAO |
Environmental Permit |
EP-311/2008/C |
Valid |
|
APCO |
Notification of Construction Work under
APCO |
316688 (27
Apr 2010) |
Valid |
|
WPCO |
Discharge License |
WT00007442-2010
(2 Nov 2010) |
Valid |
|
WDO |
Registration as Chemical
Waste Producer |
WPN0000-542-H3083-04 |
Valid |
|
WDO |
Bill Account for disposal |
700945423 |
Valid |
Legend: EIAO – Environmental Impact Assessment
Ordinance
APCO – Air Pollution Control Ordinance
WPCO – Water Pollution Control Ordinance
WDO – Waste Disposal Ordinance
The EM&A programme followed the
recommended mitigation measures in the EM&A manual. The EM&A
requirements as well as the summary of implementation status of the
environmental mitigation measures are provided in Appendix L. In particular, the following mitigation
measures were brought to attention during the site audits:
Air Quality
·
All
stockpiles should be
covered by tarpaulin or kept wet by water spraying;
·
All
vehicles should be washed to remove any dusty materials before leaving the
construction sites;
·
The portion
of road leading the construction site that is within
·
During the dry season, sufficient water spraying
should be provided at haul road to reduce dust emission; and
·
Ensure proper functioning of the wheel wash facility.
Noise
·
Mobile
plant should be sited
as far away from NSRs as possible;
·
Plant
known to emit noise strongly in one direction should be orientated to direct
noise away from the NSRs; and
·
The construction activities should be better scheduled to reduce noise nuisance.
Water Quality
·
Water accumulated in the site (including water inside
drip trays) should be cleared frequently;
·
Ensure
proper functioning of the wastewater
treatment facility; and
·
Silt and debris should be removed from the temporary
drainage channel regularly.
Waste Management
·
Reuse the excavated materials as far as practical to
reduce the amount of waste disposal;
·
Ensure drip trays are provided for chemical containers
to prevent leakage or soil contamination;
·
All
plants and vehicles should be properly maintained to prevent oil leakage; and
·
Oil
stains on soil should be cleared by disposal of contaminated soil.
There is no breach of Action or Limit Levels for Air Quality and Noise monitoring in the reporting month.
Exceedances of pH, DO and SS were observed at MP3
to MP6 in January 2013. Action Level exceedances of pH were observed at MP5 and
MP6. DO exceedance was observed once each at MP3, MP4 and MP5. SS exceedance
was recorded on one monitoring date at MP4 and two monitoring dates at MP5.
Exceedance of turbidity was recorded once each at MP3, MP4 and MP5 during the
reporting month.
Table 7.1: Summary of Exceedances in Water Quality
|
Monitoring Date |
pH |
Dissolved Oxygen
(mg/L) |
Turbidity (NT) |
Suspended Solids
(mg/L) |
|
MP3 |
|
|
|
|
|
02/01/2013 |
7.1 |
9.6 |
44.8 |
43 |
|
04/01/2013 |
7.3 |
10.7 |
30.0 |
19 |
|
07/01/2013 |
7.3 |
7.8 |
44.0 |
42 |
|
09/01/2013 |
7.4 |
7.8 |
42.4 |
47.5 |
|
11/01/2013 |
7.3 |
7.1 |
72.3 |
62 |
|
14/01/2013 |
7.3 |
8.5 |
33.1 |
28 |
|
16/01/2013 |
7.3 |
8.5 |
23.4 |
18 |
|
18/01/2013 |
7.2 |
6.9 |
46.6 |
40.5 |
|
21/01/2013 |
7.3 |
7.2 |
58.9 |
40 |
|
23/01/2013 |
7.3 |
5.9 |
53.2 |
34 |
|
25/01/2013 |
7.2 |
7.2 |
38.7 |
29.5 |
|
28/01/2013 |
7.3 |
7.0 |
37.7 |
30.5 |
|
30/01/2013 |
7.3 |
7.8 |
36.3 |
26.5 |
|
Action Level |
<5.5 or >7.5 |
<6.85 |
>64 |
>65 |
|
Limit Level |
<4.0 or >8.0 |
<6.65 |
>67 |
>66 |
|
|
|
|
|
|
|
MP4 |
|
|
|
|
|
02/01/2013 |
7.3 |
8.7 |
13.0 |
12 |
|
04/01/2013 |
7.2 |
2.2 |
14.1 |
8 |
|
07/01/2013 |
7.5 |
8.8 |
11.7 |
26.5 |
|
09/01/2013 |
7.3 |
5.8 |
12.8 |
22.5 |
|
11/01/2013 |
7.2 |
8.2 |
12.3 |
15 |
|
14/01/2013 |
7.4 |
8.2 |
14.6 |
18 |
|
16/01/2013 |
7.2 |
7.4 |
27.2 |
24 |
|
18/01/2013 |
7.3 |
7.2 |
98.4 |
68 |
|
21/01/2013 |
7.4 |
6.9 |
37.1 |
30.5 |
|
23/01/2013 |
7.4 |
7.2 |
29.4 |
16 |
|
25/01/2013 |
7.4 |
7.8 |
16.5 |
12 |
|
28/01/2013 |
7.5 |
7.8 |
16.7 |
13.5 |
|
30/01/2013 |
7.4 |
9.3 |
14.2 |
10 |
|
Action Level |
<5.5 or >7.5 |
<3.91 |
>60 |
>50 |
|
Limit Level |
<4.0 or >8.0 |
<3.82 |
>64 |
>53 |
|
|
|
|
|
|
|
MP5 |
|
|
|
|
|
02/01/2013 |
7.4 |
9.1 |
40.9 |
55 |
|
04/01/2013 |
7.3 |
3.9 |
25.8 |
34.5 |
|
07/01/2013 |
7.4 |
8.6 |
34.0 |
67 |
|
09/01/2013 |
7.3 |
5.8 |
32.7 |
84.5 |
|
11/01/2013 |
7.4 |
7.4 |
15.7 |
13 |
|
14/01/2013 |
7.6 |
8.6 |
12.9 |
11 |
|
16/01/2013 |
7.3 |
8.5 |
17.3 |
14 |
|
18/01/2013 |
7.4 |
6.9 |
91.3 |
65 |
|
21/01/2013 |
7.4 |
7.1 |
40.5 |
30.5 |
|
23/01/2013 |
7.4 |
6.7 |
31.1 |
22.5 |
|
25/01/2013 |
7.5 |
7.2 |
25.1 |
19 |
|
28/01/2013 |
7.5 |
7.9 |
19.6 |
30 |
|
30/01/2013 |
7.5 |
9.1 |
19.7 |
16.5 |
|
Action Level |
<5.5 or >7.5 |
<4.13 |
>81 |
>66 |
|
Limit Level |
<4.0 or >8.0 |
<3.87 |
>84 |
>69 |
|
|
|
|
|
|
|
MP6 |
|
|
|
|
|
02/01/2013 |
7.4 |
9.2 |
14.8 |
18.5 |
|
04/01/2013 |
7.4 |
6.6 |
12.6 |
59 |
|
07/01/2013 |
7.4 |
8.7 |
15.6 |
15 |
|
09/01/2013 |
7.3 |
5.6 |
14.2 |
14.5 |
|
11/01/2013 |
7.4 |
7.6 |
11.7 |
17.5 |
|
14/01/2013 |
7.6 |
8.2 |
12.4 |
11 |
|
16/01/2013 |
7.4 |
8.4 |
16.3 |
12 |
|
18/01/2013 |
7.5 |
7.6 |
57.5 |
39 |
|
21/01/2013 |
7.5 |
7.9 |
27.3 |
20.5 |
|
23/01/2013 |
7.5 |
7.8 |
17.8 |
13.5 |
|
25/01/2013 |
7.5 |
8.6 |
10.5 |
6 |
|
28/01/2013 |
7.6 |
8.3 |
21.9 |
33 |
|
30/01/2013 |
7.5 |
11.2 |
8.5 |
3.5 |
|
Action Level |
<5.5 or >7.5 |
<4.61 |
>94 |
>75 |
|
Limit Level |
<4.0 or >8.0 |
<4.52 |
>96 |
>75 |
Notes:
(1)
Values Bold
indicate Action Level exceedance.
(2)
Values Underlined
and Bold indicate Limit Level exceedance.
On 28 January 2013, a record of complaint was
lodged with the Environmental Protection Department (EPD) on dust impact near
No notifications of summons or successful prosecution were received the reporting month.
Non-compliance
Investigations have been carried out to
identify the causes of water quality exceedance.
From investigation, construction activities
during the period of exceedance included mainly site formation. It was observed
that the Contractor has implemented water quality mitigation measures as recommended
in the EIA report, including the provision of temporary drainage facility and
associated treatment facility. Sand bags are in place in the temporary drainage
channel to enhance the desilting efficiency. The Contractor further enhanced
the water quality mitigation measures by erecting several segments of rock
bunds at the discharge outlet to avoid site runoff draining directly to the
northern ditches.
With external factors
affect the adjacent environments, such as natural variations, pond fish culture
activities and rainfall, the exceedances were considered not due to
construction works.
Complaint
From ET’s investigation of the complaint, the
major site activities conducted during December 2012 and January 2013 were backfilling
and consolidation of site formation. Potential dust sources from the site
include dust from haul road and stockpiles, backfilling, consolidation of site
formation and movement of machineries. The Contractor implemented
the air quality mitigation measures as recommended in EM&A Manual which
include:
¡
Water
spraying within the site boundary for dust suppression;
¡
Covering
of dusty stockpiles;
¡
Compaction
of fill materials by rollers; and
¡
Every
vehicle was washed to remove any dusty materials from its body and wheels
before leaving the construction site.
Other potential
dust sources that can be identified nearby include:
¡
Construction
site for Express Rail Link (major dust generating activities observed include
fugitive dust from dry haul roads).
Regular site audit
and additional ad hoc site audit were conducted on 30 and 31 January 2013.
During the site audits, regular water spraying of the haul road near the site
boundary with
Dust monitoring
was conducted since commencement of construction of the Project. No exceedance
of action and limit levels for 24-hour Total Suspended Particulates (TSP) was
recorded from December 2012 to 18 January 2013. The maximum 24-hour TSP levels
recorded at the four air quality monitoring stations AM1, AM2, AM3 and AM4
during this period were 102 mg/m3,
92 mg/m3,
95 mg/m3
and 98 mg/m3
respectively, which were well below the Action Levels of 226 mg/m3, 213mg/m3, 205 mg/m3 and 237 mg/m3 respectively.
In addition, no
exceedance of action and limit levels for 1-hour TSP was recorded from December
2012 to 24 January 2013. The maximum 1-hour TSP levels recorded at the four air
quality monitoring stations AM1, AM2, AM3 and AM4 during this period were 150 mg/m3, 162 mg/m3, 160 mg/m3 and 177 mg/m3 respectively, which were well below
the action levels of 378 mg/m3,
357 mg/m3,
358 mg/m3
and 372 mg/m3
respectively.
On the other hand,
the prevailing wind direction in December 2012 was northeast from the
information obtained from the Hong Kong Observatory.
There was no
deterioration of air quality observed during regular site audits carried out by
the Environmental Team and during the additional ad hoc site walk carried out
on 31 January 2013.
Non-compliance
As non-compliances have been recorded, the
Event and Action Plan has been followed. Although it is considered that the
exceedances were not related to the Project, the Contractor was reminded to
implement the water quality mitigation measures in accordance with the
recommendation stated in Section 5.6.1 – 5.6.4 of the EIA Report as far as
practicable and regular spot check would be conducted on the nearby discharge
by Contractor and inform ET for investigation.
To cater for the site runoff in wet season, the
Contractor has further enhanced the water quality mitigation measures by
erecting several segments of rock bunds at the discharge outlet to avoid site
runoff draining directly to the northern ditches.
Complaint
Air quality mitigation measures as recommended
in the Implementation Schedule of the EM&A Manual have been implemented by
Contractor to minimise the air quality nuisance arising from the site
activities. Nevertheless, such measures can be enhanced. The Contractor was
recommended to fully cover any idled excavated dusty materials or stockpile of
dusty materials entirely by impervious sheeting. The Contractor was also
recommended to provide water spraying to mitigate against dust emissions during
ongoing backfilling works and also to haul roads, unpaved areas and dusty
operations especially during dry weather condition. Site briefing on a weekly
basis on environmental mitigation measures to site staff should be conducted to
increase site staff environmental awareness.
Cumulative statistics for complaints, notifications of summons and
successful prosecutions for the Project account for period starting from the
date of commencement of construction (i.e. 12 May 2010) to the end of the
reporting month and are summarized in the Table
7.2 below.
Table 7.2: Statistics for Complaints, Notifications of Summons and Successful Prosecutions
|
Reporting Period |
Cumulative Statistics |
||
|
|
Complaints |
Notifications
of summons |
Successful
prosecutions |
|
This reporting month (Jan 2013) |
1 |
0 |
0 |
|
From 12 May 2010 to end
of the reporting month (Jan 2013) |
4 |
0 |
0 |
The major site works scheduled to be commissioned in the coming month include:
¡
Site
Formation
¡
Foundation
Work
Key issues to be considered in the coming month include:
¡
Generation
of dust from activities on-site during dry weather condition;
¡
Noise
impact from operating equipment and machinery on-site;
¡
Generation
of site surface runoffs and wastewater from activities on-site;
¡
Sorting,
recycling, storage and disposal of general refuse and construction waste from
activities on-site; and
¡
Management
of chemicals and avoidance of oil spillage on-site and to the drainage.
The environmental site inspection and environmental monitoring will be continued in the coming month. Impact monitoring for air, noise, water quality, ecology and landscape and visual in accordance with the approved EM&A Manual has commenced since 12 May 2010. The tentative monitoring schedule for February 2013 is shown in the Table 8.1.
Table 8.1: Tentative Environmental Monitoring and
Audit Schedule for February 2013

The EM&A programme as recommended in the EM&A manual has been undertaken in the reporting month since 12 May 2010.
Monitoring of Air Quality, Noise, Water Quality, Ecology and Landscape and Visual impacts due to the Project was under way. In particular, the 1-hr TSP, 24-hr TSP, noise level (as Leq) and water quality parameters (such as pH, DO and SS) under monitoring have been checked against established Action and Limit levels.
There was no breach of Action and Limit Levels for 1-hr TSP,
24-hr TSP and noise in the
reporting month.
Exceedances of pH, DO, turbidity and SS were
observed at MP3 to MP6 in January 2013. Investigations have been carried out to identify
the causes of exceedance. From investigation, the Contractor has implemented
water quality mitigation measures as recommended in the EIA report. With
external factors affecting the adjacent environments, such as natural
variations and pond fish culture activities, the exceedances were considered
not due to construction works.
On 28
January 2013, a complaint was lodged with the Environmental Protection
Department (EPD) on dust impact near
With considerations
on the construction activities and environment, the following recommendations
were provided:
Air Quality
·
All stockpiles should be covered by tarpaulin or kept
wet by water spraying;
·
All
vehicles should be washed to remove any dusty materials before leaving the
construction sites;
·
The portion
of road leading the construction site that is within
·
Sufficient water spraying should be provided at haul
road to reduce dust emission, especially during dry weather conditions; and
·
Ensure proper functioning of the wheel wash facility.
Noise
·
Mobile plant should be sited as far away from NSRs as
possible;
·
Plant
known to emit noise strongly in one direction should be orientated to direct
noise away from the NSRs; and
·
The
construction activities should be better scheduled to reduce noise nuisance.
Water Quality
·
Water accumulated in the site (including water inside
drip trays) should be cleared frequently;
·
Ensure
proper functioning of the wastewater treatment facility; and
·
Silt and debris should be removed from the temporary
drainage channel regularly.
Waste Management
·
Reuse the excavated materials as far as practical to
reduce the amount of waste disposal;
·
Ensure drip trays are provided for chemical containers
to prevent leakage or soil contamination;
·
All
plants and vehicles should be properly maintained to prevent oil leakage; and
·
Oil
stains on soil should be cleared by disposal of contaminated soil.


Contact
information:
|
Company |
Position |
Name |
Telephone |
|
Heng Shung Construction Co. Ltd. (The Contractor) |
Assistant Construction
Manager |
Ms. Lynne HUNG |
2908 2391 |
|
|
Site Agent |
Mr. POON Man Ho |
9426 3533 |
|
|
Environmental Officer |
Mr. Ricky WONG |
9866 7625 |
|
ENVIRON Hong
Kong Ltd. (Independent
Environmental Checker (IEC)) |
Independent Environmental
Checker |
Mr. David YEUNG |
3743 0788 |
|
Mott MacDonald Hong Kong Ltd. (Environmental Team
(ET)) |
Environmental Team Leader (until 18 Jan 2013) |
Ms. Florence YUEN |
2828 5768 |
|
|
Environmental Team Leader (from 19 Jan 2013) |
Mr. Terence KONG |
2828 5919 |
Appendix C.
Action and Limit Levels for Construction Phase
|
Air
Quality
Action
and Limit Levels for 24-hour TSP
|
Monitoring Station |
Action Level (mg/m3) |
Limit Level (mg/m3) |
|
ASR1 |
226 |
260 |
|
ASR2A |
213 |
260 |
|
ASR3 |
205 |
260 |
|
ASR4 |
237 |
260 |
Action and Limit Levels for 1-hour TSP
|
Monitoring Station |
Action Level (mg/m3) |
Limit Level (mg/m3) |
|
ASR1 |
378 |
500 |
|
ASR2A |
357 |
500 |
|
ASR3 |
358 |
500 |
|
ASR4 |
372 |
500 |
Noise
Action and Limit Levels for
Construction Noise
|
Time Period |
Action Level |
Limit Level |
|
NSR1, NSR3, NSR5, NSR7 |
||
|
0700 – 1900 hours on
normal weekdays |
When one documented
complaint is received from any one of the sensitive receivers |
75 dB(A) |
Water Quality
Action and Limit
Levels for Water Quality
|
Parameters |
DO in mg/L |
Turbidity in NTU |
SS in mg/L |
pH |
||||
|
|
Action
Level |
Limit
Level |
Action
Level |
Limit Level |
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
|
MP1 |
1.23 |
1.17 |
173 |
177 |
231 |
299 |
< 5.5 or > 7.5 |
< 4.0 or > 8.0 |
|
MP2 |
1.04 |
0.89 |
132 |
163 |
170 |
209 |
||
|
MP3 |
6.85 |
6.65 |
64 |
67 |
65 |
66 |
||
|
MP4 |
3.91 |
3.82 |
60 |
64 |
50 |
53 |
||
|
MP5 |
4.13 |
3.87 |
81 |
84 |
66 |
69 |
||
|
MP6 |
4.61 |
4.52 |
94 |
96 |
75 |
75 |
||
Appendix D.
Event and Action Plan for Air
Quality, Noise, Water Quality, Ecology and Landscape & Visual
|
Air Quality
|
Event |
Action |
|||
|
ET Leader |
IEC |
ER |
Contractor |
|
|
Action Level |
|
|
|
|
|
1.
Exceedance for one
sample |
1.
Identify source, investigate the causes of exceedance and
propose remedial measures. 2.
Inform IEC and ER. 3.
Repeat measurement to confirm finding. 4.
Increase monitoring frequency to daily. |
1.
Check monitoring data submitted by ET. 2.
Check Contractor’s working method. |
1.
Notify Contractor. |
1.
Rectify any unacceptable practice. 2.
Amend working methods if appropriate. |
|
2.
Exceedance for two or
more consecutive samples |
1.
Identify the source. 2.
Inform IEC and ER. 3.
Advise ER on the
effectiveness of the proposed remedial measures 4.
Repeat measurements to confirm findings. 5.
Increase monitoring frequency to daily. 6.
Discuss with IEC and the Contractor on remedial actions
required. 7.
If exceedance continues, arrange meeting with IEC and ER. 8.
If exceedance stops, cease additional monitoring. |
1.
Check monitoring data submitted by ET. 2.
Check the Contractor’s working method. 3.
Discuss with ET Leader and the Contractor on possible remedial
measures. 4.
Advise ER on the effectiveness of the proposed remedial
measures. 5.
Supervise implementation of remedial measures. |
1.
Confirm receipt of notification of exceedance in writing. 2.
Notify the Contractor. 3.
Ensure remedial measures properly implemented. |
1.
Submit proposals for remedial actions to IEC within 3 working
days of notification. 2.
Implement the agreed proposals. 3.
Amend proposal if appropriate. |
|
Limit Level |
|
|
|
|
|
1.
Exceedance for one
sample |
1.
Identify source, investigate the causes of exceedance and
propose remedial measures. 2.
Inform ER and EPD. 3.
Repeat measurement to confirm finding. 4.
Increase monitoring frequency to daily. 5.
Assess effectiveness of Contractor’s remedial actions and keep
IEC, EPD and ER informed of the results. |
1.
Check monitoring data submitted by ET. 2.
Check the Contractor’s working method. 3.
Discuss with ET Leader and the Contractor on possible remedial
measures. 4.
Advise ER on the effectiveness of the proposed remedial
measures. 5.
Supervise implementation of remedial measures. |
1.
Confirm receipt of notification of exceedance in writing. 2.
Notify the Contractor. 3.
Ensure remedial measures properly implemented. |
1.
Take immediate action to avoid further exceedance. 2.
Submit proposals for remedial actions to IEC within 3 working
days of notification. 3.
Implement the agreed proposals. 4.
Amend proposal if appropriate. |
|
2.
Exceedance for two or
more consecutive samples |
1.
Notify IEC, ER, EPD and the Contractor. 2.
Identify the source. 3.
Repeat measurements to confirm findings. 4.
Increase monitoring frequency to daily. 5.
Carry out analysis of the Contractor’s working procedures to
determine possible mitigation to be implemented. 6.
Arrange meeting IEC and ER to discuss the remedial actions to be
taken. 7.
Assess effectiveness of the Contractor’s remedial actions and
keep IEC, EPD and ER informed of the results. 8.
If exceedance stops, cease additional monitoring. |
1.
Discuss amongst ER, ET Leader and the Contractor on the
potential remedial actions. 2.
Review the Contractor’s remedial actions whenever necessary and
advise ER accordingly. 3.
Supervise the implementation of remedial measures. |
1.
Confirm receipt of notification of exceedance in writing. 2.
Notify the Contractor. 3.
In consultation with IEC, agree with the remedial measures to be
implemented. 4.
Ensure remedial measures are properly implemented. 5.
If exceedance continues, consider what activity of the work is
responsible and instruct the Contractor to stop that activity of work until
the exceedance is abated. |
1.
Take immediate action to avoid further exceedance. 2.
Submit proposals for remedial actions to IEC within 3 working
days of notification. 3.
Implement the agreed proposals. 4.
Resubmit proposals if problem still not under control. 5.
Stop the relevant activity of works as determined by ER until
the exceedance is abated. |
Construction Noise
|
Event |
Action |
|||
|
ET Leader |
IEC |
ER |
Contractor |
|
|
Action Level |
1. Notify IEC and the Contractor. 2. Carry out investigation. 3. Report the results of investigation to IEC and the Contractor. 4. Discuss with the Contractor and formulate remedial measures. 5. Increase monitoring frequency to check mitigation measures. |
1. Review with analysed results submitted by ET. 2. Review the proposed remedial measures by the Contractor and advise ER
accordingly. 3. Supervise the implement of remedial measures. |
1. Confirm receipt of notification of exceedance in writing. 2. Notify the Contractor. 3. Require the Contractor to propose remedial measures for the analysed
noise problem. 4. Ensure remedial measures are properly implemented. |
1. Submit noise mitigation proposals to IEC. 2. Implement noise mitigation proposals. |
|
Limit Level |
1. Identify the source. 2. Notify IEC, ER, EPD and the Contractor. 3. Repeat measurement to confirm findings. 4. Increase monitoring frequency. 5. Carry out analysis of Contractor’s working procedures to determine
possible mitigation to be implemented. 6. Inform IEC, ER, and EPD the causes & actions taken for the
exceedances. 7. Assess effectiveness of the Contractor’s remedial actions and keep
IEC, EPD and ER informed of the results. 8. If exceedance stops, cease additional monitoring. |
1. Discuss amongst ER, ET Leader and the Contractor on the potential
remedial actions. 2. Review the Contractor’s remedial actions whenever necessary to assure
their effectiveness and advise ER accordingly. 3. Supervise the implementation of remedial measures. |
1. Confirm receipt of notification of exceedance in writing. 2. Notify the Contractor. 3. Require the Contractor to propose remedial measures for the analysed
noise problem. 4. Ensure remedial measures are properly implemented. 5. If exceedance continues, consider what activity of the work is
responsible and instruct the Contractor to stop that activity of work until
the exceedance is abated. |
1. Take immediate action to avoid further exceedance. 2. Submit proposals for remedial actions to IEC within 3 working days of
notification. 3. Implement the agreed proposals. 4. Resubmit proposals if problem still not under control. 5. Stop the relevant activity of works as determined by the ER until the
exceedance is abated. |
Water Quality
|
Event |
Action |
|||
|
ET Leader |
IEC |
ER |
Contractor |
|
|
Action Level |
|
|
|
|
|
1. Exceedance for one sample |
1. Repeat
in-situ measurement to confirm finding; 2. Identify
source(s) of impact; 3. Inform
IEC and Contractor; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with IEC and Contractor; and 6. Repeat
measurement on next day of exceedance. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC on the proposed mitigation measures; and 2. Make
agreement on the mitigation measures to be implemented. |
1. Inform
the ER and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and propose mitigation measures to IEC and ER; and 6. Implement
the agreed mitigation measures. |
|
2.
Exceedance for two or
more consecutive samples |
1. Repeat
in-situ measurement to confirm finding; 2. Identify
source(s) of impact; 3. Inform
IEC and Contractor; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with IEC and Contractor; 6. Ensure
mitigation measures are implemented; 7. Prepare
to increase the monitoring frequency to daily; and 8. Repeat
measurement on next day of exceedance. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC on the proposed mitigation measures; 2. Make
agreement on the mitigation measures to be implemented; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Inform
the Engineer and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and propose mitigation measures to IEC and ER within 3
working days; and 6. Implement
the agreed mitigation measures. |
|
Limit Level |
|
|
|
|
|
1.
Exceedance for one
sample |
1. Repeat
in-situ measurement to confirm finding; 2. Identify
source(s) of impact; 3. Inform
IEC, Contractor and EPD; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with IEC, ER and Contractor; 6. Ensure
mitigation measures are implemented; and 7. Increase
the monitoring frequency to daily until no exceedance of Limit level. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC, ET and Contractor on the proposed mitigation measures; and 2. Request
Contractor to critically review the working methods; 3. Make
agreement on the mitigation measures to be implemented; and 4. Assess
the effectiveness of the implemented mitigation measures. |
1. Inform
the Engineer and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and ER and propose mitigation measures to IEC and ER within 3
working days; and 6. Implement
the agreed mitigation measures. |
|
2.
Exceedance for two or
more consecutive samples |
1. Repeat
in-situ measurement to confirm finding; 2. Identify
source(s) of impact; 3. Inform
IEC, Contractor and EPD; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with IEC, ER and Contractor; 6. Ensure
mitigation measures are implemented; and 7. Increase
the monitoring frequency to daily until no exceedance of Limit level for two
consecutive days. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC, ET and Contractor on the proposed mitigation measures; and 2. Request
Contractor to critically review the working methods; 3. Make
agreement on the mitigation measures to be implemented; 4. Assess
the effectiveness of the implemented mitigation measures; and 5. Consider
and instruct, if necessary, the Contractor to slow down or to stop all or
part of the marine work until no exceedance of Limit Level. |
1. Inform
the ER and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and ER and propose mitigation measures to IEC and ER within 3
working days; 6. Implement
the agreed mitigation measures; and 7. As
directed by the Engineer, to slow down or to stop all or part of the marine
work or construction activities. |
Appendix E.
Calibration
certificates
|
Appendix F.
Graphical plots of the
monitoring results
|
Appendix G.
Weather conditions during
the monitoring period
|
Appendix H.
Ecological Monitoring conducted
|
|
January 2013 |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
|
Mammals |
|
|
|
ü |
|
|
|
ü |
|
|
|
|
|
|
ü |
|
Birds |
|
|
|
ü |
|
|
|
ü |
|
|
|
|
|
|
ü |
|
Herpetofauna # |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Dragonflies & butterflies # |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Water
Quality |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Inspection Visits |
|
|
|
ü |
|
|
|
|
|
|
ü |
|
|
|
|
|
January 2013 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
|
Mammals |
|
|
|
|
|
|
ü |
|
|
|
|
|
|
ü |
|
|
|
Birds |
|
|
|
|
|
|
ü |
|
|
|
|
|
|
ü |
|
|
|
Herpetofauna # |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Dragonflies & butterflies # |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Water
Quality |
|
|
|
|
ü |
|
|
|
|
|
|
|
|
|
|
|
|
Inspection Visits |
|
|
ü |
|
|
|
|
|
|
ü |
|
|
|
ü |
|
|
Note:
* Light grey cells indicate
public holidays, Saturdays or Sundays.
# Survey
was not required for this item during the reporting month.
Appendix I.
Summary of Bird Surveys conducted
|
Table
I1. Summary of bird species of
conservation importance and/or wetland-dependence recorded in the Survey Area
(excluding the WRA)
|
Species Name(5) |
Scientific Name(5) |
Conservation Status (2) |
Jan 2013 |
|
|
Occurrence(3) |
Mean(4) |
|||
|
Little
Grebe |
Tachybaptus ruficollis |
LC, (1) |
5 |
17.8 |
|
Great
Cormorant |
Phalacrocorax carbo |
PRC, (1) |
5 |
5.6 |
|
Grey
Heron |
Ardea cinerea |
PRC, (1) |
5 |
4.2 |
|
Great
Egret |
Egretta alba |
PRC, (RC), (1) |
5 |
4.6 |
|
Little
Egret |
Egretta garzetta |
PRC, (RC), (1) |
5 |
18.2 |
|
Chinese
Pond Heron |
Ardeola bacchus |
PRC, (RC), (1) |
5 |
3.6 |
|
Northern
Shoveler |
Anas clypeata |
RC, (1) |
1 |
0.2 |
|
Tufted
Duck |
Aythya fuligula |
LC, (1) |
5 |
35.0 |
|
White-breasted
Waterhen |
Amaurornis phoenicurus |
(1) |
4 |
1.8 |
|
Pied
Avocet |
Recurvirostra avosetta |
RC, (1) |
2 |
1.2 |
|
Little
Ringed Plover |
Charadrius dubius |
LC, (1) |
2 |
2.8 |
|
Green
Sandpiper |
Tringa ochropus |
(1) |
4 |
4.6 |
|
Common
Sandpiper |
Actitis hypoleucos |
(1) |
5 |
6.2 |
|
Common
Kingfisher |
Alcedo atthis |
(1) |
3 |
1.4 |
|
White
Wagtail |
Motacilla alba |
(1) |
5 |
6.8 |
|
Grey
Wagtail |
Motacilla cinerea |
(1) |
1 |
0.2 |
|
Eastern
Yellow Wagtail |
Motacilla tschutschensis |
(1) |
3 |
2.6 |
|
No. of
Species Recorded |
17 |
|||
(1) Indicates wetland-dependant or wetland-associated species.
(2) Conservation status follows that of Fellowes et al. (2002) and BirdLife International listing (2011).
(3) Indicates number of surveys recorded within the reporting period.
(4) Refers to the mean number of individuals recorded in the reporting period (excluding the WRA)
(5) Follows HK bird list (dated 2012-11-22).
Table I2. Summary of bird species of conservation importance and/or
wetland-dependence recorded in the WRA
|
Species Name(5) |
Scientific
Name(5) |
Conservation Status (2) |
Jan 2013 |
Records Outside Surveys |
|
|
Occurrence(3) |
Mean(4) |
||||
|
Little Grebe |
Tachybaptus ruficollis |
LC, (1) |
3 |
1.2 |
ü |
|
Great Cormorant |
Phalacrocorax carbo |
PRC, (1) |
3 |
0.8 |
- |
|
Grey Heron |
Ardea cinerea |
PRC, (1) |
3 |
0.8 |
ü |
|
Great Egret |
Egretta alba |
PRC, (RC), (1) |
4 |
1.0 |
ü |
|
Little Egret |
Egretta garzetta |
PRC, (RC), (1) |
4 |
2.2 |
ü |
|
Chinese Pond Heron |
Ardeola bacchus |
PRC, (RC), (1) |
4 |
2.4 |
- |
|
Northern Shoveler |
Anas clypeata |
RC, (1) |
- |
- |
ü |
|
Tufted Duck |
Aythya fuligula |
LC, (1) |
- |
- |
ü |
|
White-breasted Waterhen |
Amaurornis phoenicurus |
(1) |
1 |
0.2 |
- |
|
Little Ringed Plover |
Charadrius dubius |
LC, (1) |
1 |
0.4 |
- |
|
Common Greenshank |
Tringa nebularia |
LC, (1) |
- |
- |
ü |
|
Common Sandpiper |
Actitis hypoleucos |
(1) |
- |
- |
ü |
|
Common Kingfisher |
Alcedo atthis |
(1) |
2 |
0.5 |
- |
|
Eastern Yellow Wagtail |
Motacilla tschutschensis |
(1) |
3 |
1.4 |
- |
|
White Wagtail |
Motacilla alba |
(1) |
3 |
0.8 |
ü |
|
No. of
Species Recorded |
15 |
||||
(1) Indicates wetland-dependant or
wetland-associated species.
(2) Conservation status follows that of Fellowes et al. (2002) and BirdLife International
listing (2011).
(3) Indicates number of surveys recorded within
the reporting period.
(4) Refers to the mean number of individuals
recorded in the reporting period at WRA.
(5) Follows HK bird list (dated 2012-11-22).
Table J1. Summary of herpetofauna
monitoring in the Survey Area (excluding the WRA)
|
Species Name |
Scientific Name |
Conservation Status(1) |
Jan 2013 |
|
|
Occurrence(2) |
Mean(3) |
|||
|
Amphibian |
No. of |
Species Recorded |
0 |
|
|
(No survey scheduled in January 2013) |
|
|
|
|
|
|
|
|
Occurrence(2) |
Mean(3) |
|
Reptile |
No. of |
Species Recorded |
0 |
|
|
(No survey scheduled in January 2013) |
|
|
|
|
(1) Conservation status follows that of Fellowes et al. (2002), Chan et al. (2005) and Karsen et al. (1998).
(2) Indicates number of surveys recorded within the reporting period.
(3) Refers to the mean number of individuals recorded in the
reporting period (excluding the WRA).
Table J2. Summary of herpetofauna monitoring in the
WRA
|
Species Name |
Scientific Name |
Conservation Status(1) |
Jan 2013 |
||||
|
Occurrence(2) |
Mean(3) |
||||||
|
Amphibian |
No. of |
Species Recorded |
0 |
||||
|
(No survey scheduled in January 2013) |
|
|
|
|
|||
|
|
|
|
Occurrence(2) |
Mean(3) |
|||
|
Reptiles |
No. of |
Species Recorded |
0 |
||||
|
(No survey
scheduled in January 2013) |
|
|
|
|
|||
(1) Conservation status follows that of Fellowes et al. (2002), Chan et al. (2005) and Karsen et al. (1998).
(2) Indicates number of surveys recorded within the reporting period.
(3) Refers to the mean number of individuals recorded in the
reporting period in the WRA.
Table
J3. Summary of mammal monitoring in the
Survey Area (excluding the WRA)
|
Species Name |
Scientific Name |
Conservation Status(1) |
Jan 2013 |
|
|
Occurrence(2) |
Mean(3) |
|||
|
Mammal |
No. of |
Species Recorded |
0 |
|
|
(No Records in January 2013) |
|
|
|
|
(1) Conservation status follows that of Fellowes et al. (2002) and Shek (2006).
(2) Indicates number of surveys recorded within the reporting period.
(3) Refers to the mean number of individuals recorded in the
reporting period (excluding the WRA).
Table J4. Summary of mammal monitoring in
the WRA
|
Species Name |
Scientific Name |
Conservation Status(1) |
Jan 2013 |
Records Outside Surveys |
|
|
Occurrence(2) |
Mean(3) |
||||
|
Mammal |
No. of |
Species Recorded |
2 |
||
|
Small Asian
Mongoose |
Herpestes javanicus |
- |
- |
- |
ü |
|
Japanese Pipistrelle |
Pipistrellus abramus |
LC |
- |
- |
ü |
(1) Conservation status follows that of Fellowes et al. (2002) and Shek (2006).
(2) Indicates number of surveys recorded within the reporting period.
(3) Refers to the mean number of individuals recorded in the
reporting period in the WRA.
Table J5. Summary
of odonate and butterfly monitoring in the Survey Area (excluding WRA)
|
Common Name |
Scientific Name |
Conservation Status(1) |
Jan 2013 |
|
|
Occurrence(2) |
Mean(3) |
|||
|
Odonate |
No. of Species Recorded |
0 |
||
|
(No Records in January 2013) |
|
|
|
|
|
Butterfly |
No. of Species
Recorded |
0 |
||
|
(No Records in January 2013) |
|
|
|
|
(1) Conservation status follows that of Fellowes et al. (2002), Lo & Hui (2004), Tam et al. (2011) and Young & Yiu (2002).
(2) indicates number of surveys recorded within the reporting period.
(3) refers to the mean number of individuals recorded in the survey (excluding the WRA).
Table J6. Summary of dragonfly and butterfly
monitoring in the WRA
|
Common Name |
Scientific Name |
Conservation Status(1) |
Jan 2013 |
|
|
Occurrence(2) |
Mean(3) |
|||
|
Odonate |
No. of Species Recorded |
0 |
||
|
(No Records in January 2013) |
|
|
|
|
|
Butterfly |
No. of Species Recorded |
0 |
||
|
(No Records in January 2013) |
|
|
|
|
(1) Conservation status follows that of Fellowes et al. (2002), Lo & Hui (2004), Tam et al. (2011) and Young & Yiu (2002).
(2) indicates number of surveys recorded within the reporting period.
(3) refers to the mean number of individuals
recorded in the reporting period in the WRA.
Table K1. Water quality at WRA in Jan 2013
|
Cell No. |
Temp. (°C) |
pH |
Salinity (ppt) |
Turb (mg/L) |
DO (mg/L) |
Water Level (cm) |
|
1 |
18.2 |
8.44 |
0.76 |
22.4 |
8.62 |
170 |
|
2 |
18.5 |
8.37 |
0.93 |
14.8 |
9.28 |
140 |
|
3 |
18.2 |
7.98 |
0.81 |
7.5 |
8.37 |
180 |
|
4 |
18.8 |
8.32 |
0.90 |
11.9 |
8.78 |
180 |
Note: Values highlighted in bold indicate that
action level is reached; whereas values in bold and underline indicate that
limit level is reached.