


Content
Chapter Title Page
List of Figures
Figure 1.1 General
Layout Plan of the Project Site
Figure 2.1 Locations
of Air Quality Monitoring Stations
Figure 2.2 Locations
of Noise Monitoring Stations
Figure 2.3 Locations
of Water Quality Monitoring Stations
Figure 4.1 Survey
Area and Transect Walked
List of Appendices
Appendix A Project Organization Chart
Appendix B Tentative Construction Programme
Appendix C Action and Limit Levels for Construction Phase
Appendix D Event and Action Plan for Air Quality, Noise and Water
Quality
Appendix E Calibration certificates
Appendix F Graphical plots of the monitoring results
Appendix G Weather conditions during the monitoring period
Appendix H Ecological Monitoring conducted
Appendix I Summary of Bird Surveys conducted
Appendix J Summary of Herpetofauna, Mammal and
Insect Surveys conducted
Appendix K Summary of Monitoring of Water
Quality associated with Ecological Monitoring conducted
Appendix L Environmental
Mitigation Measures - Implementation Status
Executive Summary
Mott
MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by Heng Shung
Construction Co. Ltd. (The Contractor) to undertake the Environmental Team (ET)
services to carry out environmental monitoring and audit (EM&A) for both
pre-construction and construction phases of the Proposed Comprehensive
Development at Wo Shang Wai, Yuen Long.
This
is the 37th EM&A report submitted under the Condition 4.5 of Environmental
Permit No. EP-311/2008/D. This report summarises the findings on EM&A
during the period from 1 to 31 May 2013.
Exceedance of Action and Limit
Levels
There
was no breach of Action or Limit levels for Air Quality (1-hr TSP and 24-hr
TSP) and Noise level (as Leq) in the reporting month.
During May 2013, Action Level exceedances of
pH were observed at MP3, MP5 and MP6, while exceedances of DO, turbidity and/or
SS were observed at MP3 to MP6. DO exceedance was observed 13 times at MP3,
four times at MP4, four times at MP5 and eight times at MP6. SS and/or
turbidity exceedance was recorded on three monitoring dates at MP3, seven
monitoring dates at MP4, two monitoring dates at MP5 and four monitoring dates
at MP6 during the reporting month.
The summary of measured water quality is presented in Section 3.2.3.
Investigations have been carried out to
identify the causes of exceedance. From investigation, the Contractor has
implemented water quality mitigation measures as recommended in the EIA report.
With external factors affecting the adjacent
environments, such as natural variations, pond fish culture activities, rainfall
and suspected routine dredging works (unrelated to the Project), the
exceedances were considered not due to the project construction works.
Implementation of mitigation
measures
Site audits were carried out on 7, 16, 23 and 28 May 2013 to confirm the implementation measures undertaken by the Contractor in
the reporting month. The outcomes are presented in Section 6 and the status of implementation of mitigation measures
in the site is shown in Appendix L.
Record of Complaints
On 15 May 2013, a complaint was lodged with the Environmental
Protection Department (EPD) on ecological and dust impact near
Record of Notification of summons
and successful prosecution
There
was no record of Notification of summons and successful prosecution in the
reporting month.
Reporting Changes
There
was no reporting change in the reporting month.
Future Key Issues
The major site works scheduled to be commissioned in the coming three
months include site formation, foundation work, superstructure and pond drainage
management in the Wetland Restoration Area (to lower the water level and remove
unwanted species in the pond). Potential environmental impacts due to the
construction activities, including air quality, noise, water quality, ecology
and landscape and visual, will be monitored.
Environmental mitigation measures
will be implemented on site as recommended and weekly site audits will be
carried out to ensure that the environmental conditions are acceptable.
In March 2005, the Project Proponent, Profit Point Enterprises Limited, acquired the development site at Wo Shang Wai in Yuen Long. An Environmental Impact Assessment (EIA) was then carried out and approved under the EIA Ordinance (EIAO), and the Environmental Permit (EP-311/2008) for construction of the comprehensive development in Wo Shang Wai was first granted by EPD on 9 September 2008 and has been subsequently varied, with the current version (EP-311/2008/D) issued by EPD on 20 March 2013.
The Project involves the residential development and associated infrastructure and wetland restoration area and linear landscape
area. The construction works under the Environmental Permit commenced on 12 May
2010. The site formation construction works of the Wetland
Restoration Area (hereafter WRA) were completed on 15
November 2010, while the 30-month establishment period of the WRA was concluded
in August 2012 – this indicated that planting works as scheduled in the
approved Wetland Restoration and Creation Scheme (WRCS; Nov 2009) was complete,
except along the western and southern boundary where the planting is affected
by the existing site boundary and noise barrier, and for which a Variation to
Environmental Permit (EP-311/2008/C) to defer planting at the location was
approved. The current valid EP (EP-311/2008/D) includes specific mitigation
measures to minimise certain identified noise impacts during the operation
phase.
Mott MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by the Contractor, Heng Shung Construction Co. Ltd., to undertake the Environmental Team (ET) services to carry out environmental monitoring and audit (EM&A) for both pre-construction and construction phases of the Proposed Comprehensive Development at Wo Shang Wai, Yuen Long.
According to the EP Condition 4.5, the monthly EM&A Report shall be submitted to the Director within two weeks after the end of the reporting month. This report summarises the findings during the period from 1 May to 31 May 2013.
The organization chart and lines of communication with respect to the
on-site environmental management structure together with the contact
information of the key personnel are shown in Appendix A.
During the reporting period,
construction works of the Project undertaken included:
¡
Site formation
¡
Foundation Work
¡
Pond drainage management in the Wetland Restoration Area (to lower the
water level and remove unwanted species in the pond)
The Construction Works Programme
of the Project is provided in Appendix B. The general layout plan of the
Project site is shown in Figure 1.1.
The EM&A programme requires environmental monitoring of air quality, noise, water quality, ecology and landscape and visual as specified in the approved EM&A Manual.
A summary of impact EM&A requirements is presented in Table 1.1:
Table 1.1: Summary of Impact EM&A Monitoring Requirements
|
Parameters |
Descriptions |
Locations |
Frequencies |
|
Air Quality |
24-Hour TSP |
ASR1, ASR2A, ASR3, ASR4 |
Once every 6 days |
|
1-Hour TSP |
ASR1, ASR2A, ASR3, ASR4 |
3 times every 6 days |
|
|
Noise |
Leq, 30min |
NSR1, NSR3, NSR5, NSR7 |
Weekly |
|
Water Quality |
Dissolved Oxygen (DO), temperature, pH, suspended solids (SS) and Biological Oxygen Demand (BOD) |
MP1 to MP6 |
3 days per week |
|
Ecology |
Birds |
Within the Project Area and Assessment Area of 500m |
Weekly |
|
Dragonflies and Butterflies |
Within the Project Area and Assessment Area of 500m |
Once per month during Mar and Sep to Nov, and twice per month during Apr to Aug |
|
|
Herpetofauna |
Within the Project Area and Assessment Area of 500m |
Once per month during Apr to Nov |
|
|
Water quality of Wetland Restoration Area (WRA) |
Wetland Restoration Area |
After filling of WRA with water, monthly for in situ water quality and every six months (end of wet season and end of dry season) for laboratory testing |
|
|
Site Inspections |
Within the Project Area and Assessment Area of 500m |
Weekly |
|
|
Landscape
and Visual |
Auditing of protection of existing trees,
the transplanting of existing trees, the creation of new wetland, the
planting of new trees and shrubs and other landscape and visual mitigation
measures |
CM1 to CM10 and OM1 to OM7 within the
Project Area |
Site inspections once every two weeks
during construction phase; once every two months during operational phase |
The Environmental Quality Performance Limits for air quality, noise and water quality are shown in Appendix C.
The Event and Action Plan for air quality, noise and water quality are shown in Appendix D.
The monitoring schedule for the
reporting month is shown in Table 1.2
below:
Table 1.2: Environmental Monitoring and Audit Schedule for May 2013

2.
Impact Monitoring Methodology
|
For air quality, construction noise and water quality, ecology, landscape and visual monitoring
methodology, including the monitoring locations, monitoring equipments used,
monitoring parameters, and frequency and duration etc., are detailed in this Chapter.
In accordance with the EM&A Manual, 1-hour and 24-hour TSP levels monitoring are to be conducted during the construction phase. Table 2.1 summarizes the monitoring parameters, frequency and duration of air quality monitoring.
Table 2.1: Air Quality Monitoring Parameters, Frequency
and Duration
|
Parameter |
Frequency and Duration |
|
|
ASR1, ASR2A, ASR3 & ASR4 |
24-hour TSP |
At least once in every six-days |
|
1-hour TSP |
3 times every six-days |
The four air quality monitoring stations were established in the
EM&A manual and were slightly adjusted during the baseline monitoring
phase. Locations of the agreed air quality monitoring stations are listed in Table 2.2 and as shown in Figure 2.1.
Table 2.2: Air Monitoring Stations
|
Monitoring Stations |
Locations |
|
ASR1 |
Works Site Boundary |
|
ASR2A |
At the rooftop of refuse collection point,
which is located at the southwest of the project area |
|
ASR3 |
At the commercial centre at |
|
ASR4 |
Works Site Boundary |
Continuous 24-hour TSP air
quality monitoring is conducted using High Volume Sampler (HVS)
(Model: GMWS-2310 Accu-vol). The HVS meets all the requirements of the EM&A
Manual. Portable direct reading dust meters were used to carry out the 1-hour
TSP monitoring. Table 2.3 summarizes
the equipment used in the impact air quality monitoring.
Table 2.3: TSP Monitoring Equipment
|
Equipment |
Model |
|
24-hr TSP monitoring |
|
|
High
Volume Sampler |
GMWS
2310 Accu-vol |
|
Calibrator |
GMW
25 |
|
1-hr TSP monitoring |
|
|
Portable
direct reading dust meter |
AM510
SidePak Personal Aerosol Monitor Dust
Trak 8520 & 8532 |
24-hour TSP Monitoring
Installation
The HVS was installed in the vicinity of the air sensitive receiver. The following criteria were considered in the installation of the HVS.
· A horizontal platform with appropriate support to secure the sampler against gusty wind was provided.
· The distance between the HVS and any obstacles, such as buildings, was at least twice the height that the obstacle protrudes above the HVS.
· A minimum of two metres separation from walls, parapets and penthouse was required for rooftop sampler.
· A minimum of two metres separation from any supporting structure, measured horizontally was required.
· No furnace or incinerator flues or building vent were nearby.
· Airflow around the sampler was unrestricted.
· The sampler has been more than 20 metres from any drip line.
· Permission was obtained to set up the samplers and to obtain access to the monitoring stations.
· A secured supply of electricity is needed to operate the samplers.
Preparation of Filter
Papers
· Glass fibre filters, were labelled and sufficient filters that were clean and without pinholes were selected.
· All filters were equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature was around 25 °C and not variable by more than ±3 °C with relative humidity (RH) < 50 % and was not variable by more than ±5 %. A convenient working RH was 40 %.
Field Monitoring
· The power supply was checked to ensure the HVS works properly.
· The filter holder and the area surrounding the filter were cleaned.
· The filter holder was removed by loosening the four bolts and a new filter, with stamped number upward, on a supporting screen was aligned carefully.
· The filter was properly aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.
· The swing bolts were fastened to hold the filter holder down to the frame. The pressure applied should be sufficient to avoid air leakage at the edges.
· The shelter lid was closed and was secured with the aluminium strip.
· The HVS was warmed-up for about 5 minutes to establish run-temperature conditions.
· A new flow rate record sheet was set into the flow recorder.
· The flow rate of the HVS was checked and adjusted at around 1.1 m3/min. The range specified in the EM&A Manual was between 0.6-1.7 m3/min.
· The programmable timer was set for a sampling period of 24 hrs + 1 hr, and the starting time, weather condition and the filter number were recorded.
· The initial elapsed time was recorded.
· At the end of sampling, the sampled filter was removed carefully and folded in half length so that only surfaces with collected particulate matter were in contact.
· It was then placed in a clean plastic envelope and sealed.
· All monitoring information was recorded on a standard data sheet.
· Filters were sent to a HOKLAS accredited laboratory for analysis.
Maintenance and Calibration
· The HVS and its accessories are maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.
· HVSs were calibrated at two-month intervals.
· Calibration records for HVSs are shown in Appendix E.
1-hour TSP Monitoring
Field Monitoring
The measuring procedures of the 1-hour dust meter are in accordance with the Manufacturer’s Instruction Manual as follows:
·
Set POWER to “ON”, push
·
Push the knob at MEASU
· Push “O-ADJ” button. (Then meter’s indication is 0).
· Push the knob at SENSI ADJ position and set the meter’s indication to S value described on the Test Report using the trimmer for SENSI ADJ.
·
Pull out the knob and return it
to MEASU
· Push “START” button.
Maintenance and
Calibration
· The 1-hour dust meter would be checked at 3-month intervals and calibrated at 1-year intervals throughout all stages of the air quality monitoring.
· Calibration records for direct dust meters are shown in Appendix E.
Following the requirements in the EM&A Manual for noise, noise monitoring has to be carried out during the construction phase. Continuous noise monitoring for the A-weighted levels Leq, L10 and L90 is undertaken once per every week.
Table 2.4 summarizes the monitoring parameters, frequency and duration of air quality monitoring.
Table 2.4: Noise Monitoring Parameters, Frequency and Duration
|
Monitoring Stations |
Parameter |
Frequency and Duration |
|
NSR1, NSR3,
NSR5, NSR7 |
Leq, L90 & L10 |
Once every
week |
The four noise quality monitoring stations were established
in the EM&A manual and were slightly adjusted during the baseline
monitoring phase. Locations of the agreed noise quality
monitoring stations are listed in Table
2.5 and as shown
in Figure 2.2.
Table 2.5: Noise Monitoring Stations
|
Monitoring Stations |
Locations |
Type of measurement |
|
NSR1 |
Noise monitoring equipment was set up near
the boundary wall at |
Free-field |
|
NSR3 |
The monitoring station was located next to
the guard house at |
Facade |
|
NSR5 |
The monitoring station was located within
the work site boundary. |
Free-field |
|
NSR7 |
The monitoring station was located near the
boundary wall of the house of Mai Po San Tsuen. |
Free-field |
Integrating Sound Level Meter will be used for noise monitoring. It is a Type 1 sound level meter capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx). They comply with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1). Table 2.6 summarizes the noise monitoring equipment model being used.
Table 2.6: Noise Monitoring Equipment
|
Monitoring Stations |
Equipment Model |
|
|
Integrating Sound
Level Meter |
Calibrator |
|
|
NSR1 |
Rion
NL-52 |
Rion
NC-73 |
|
NSR3 |
||
|
NSR5 |
||
|
NSR7 |
||
Field Monitoring
· The Sound Level Meter was set on a tripod at a height of at least 1.2 m above the ground.
· Façade and free-field measurements were made at the monitoring locations.
· The battery condition was checked to ensure the correct functioning of the meter.
· Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:
- frequency weighting: A
- time weighting: Fast
- time measurement: 30 minutes intervals (between 07:00 and 19:00)
· Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94 dB at 1 kHz. If the difference in the calibration level before and after measurement was more than 1 dB, the measurement would be considered invalid has to be repeated after re-calibration or repair of the equipment.
· During the monitoring period, the Leq, L10 and L90 were recorded. In addition, any site observations and noise sources were recorded on a standard record sheet.
Maintenance and
Calibration
· The microphone head of the sound level meter and calibrator is cleaned with soft cloth at quarterly intervals.
·
The meter and calibrator are
sent to the supplier or HOKLAS laboratory to check and calibrate at yearly
intervals.
·
Calibration records are shown
in Appendix E.
In accordance with the requirements in the EM&A
Manual for water quality, water quality parameters including
Dissolved Oxygen (DO), temperature, pH, turbidity, suspended solids (SS) and
Biochemical Oxygen Demand (BOD) have to be monitored at designated monitoring
stations during construction of the Project. DO, temperature and pH were
measured in-situ whereas SS and BOD were analysed in a laboratory. The measurements should be taken at
all designated monitoring stations, three days per week. The interval between
any two sets of monitoring was not less than 36 hours. Table 2.7 summarizes
the monitoring parameters, frequency and duration of water quality monitoring.
Table 2.7: Water Quality
Monitoring Parameters, Frequency and Duration
|
Monitoring Stations |
Parameter |
Frequency and Duration |
|
MP1, MP2, MP3,
MP4, MP5 & MP6 |
DO,
temperature, pH, SS, turbidity, BOD |
Three days
every week |
The six water quality
monitoring stations were established in the EM&A manual. Locations of the
agreed water quality monitoring stations are listed in Table 2.8 and as shown in Figure 2.3.
Table 2.8: Water Quality
Monitoring Stations
|
Monitoring Stations |
Easting |
Northing |
|
MP1 |
838 730.50 |
822 862.25 |
|
MP2 |
838 933.26 |
823 247.41 |
|
MP3 |
839 107.17 |
823 596.84 |
|
MP4 |
839 286.14 |
823 638.55 |
|
MP5 |
839 134.35 |
823 722.99 |
|
MP6 |
839 063.02 |
823 842.25 |
The Water Quality Monitoring Equipments and Analytical Methods applied to Water Quality Samples are given in Table 2.9 and Table 2.10 respectively. Details of which are discussed below.
Table 2.9: Water Quality Monitoring Equipments
|
Equipment |
Model |
Equipment/Serial Number |
|
Conductivity, Dissolved oxygen, pH, Salinity and
Temperature Measuring Meter |
YSI Professional Plus |
09K100735 |
|
Turbidity Meter |
Hach 2100Q |
09120C000514, 12010C015757 |
|
Global Positioning System (GPS) |
Garmin
eTrex |
ENO 007 |
Table 2.10: Analytical Methods applied to Water Quality Samples
|
Determinant, unit |
Standard Method |
|
Total Suspended Solids, mg/L |
In house method based on APHA 2540D; ALS Method
Code: EA-025 |
|
Biochemical Oxygen Demand (BOD), mg/L |
In house method based on APHA 5210B; ALS Method
Code: EP-030 |
All in-situ monitoring instruments were checked, calibrated and
certified by a laboratory accredited under HOKLAS or
any other international accreditation scheme before use.
Dissolved Oxygen (DO), temperature and pH
measuring equipment
A portable, weatherproof multiparameter instrument (YSI Professional Plus) was used in the monitoring. It can be capable for measuring dissolved oxygen (DO), pH, and temperature simultaneously with the following limits:
· a dissolved oxygen level in the range of 0-50 mg/L and 0-500 % saturation;
· a temperature of -5 to 45 degree Celsius; and
· pH value of 0-14 with 0.1 as the base unit.
Turbidity Measurement Instrument
Portable and weatherproof turbidity meter (HACH model 2100Q) was used during impact monitoring. It has a photoelectric sensor capable of measuring turbidity between 0-1000 NTU. Response of the sensor was checked with certified standard turbidity solutions before the start of measurement.
Global Positioning System
A hand-held GPS navigator (Garmin eTrex
Suspended Solids and BOD
Measurements (Sample Containers and Storage)
Water samples for SS analysis were
stored in high density polythene bottles with no preservative added, packed in
ice (cooled to 4oC without being frozen), delivered to the laboratory,
and analysed as soon as possible after collection. Analysis was carried out in a
HOKLAS accredited laboratory.
Detection
Limit
The
limits of detection for the in-situ and laboratory measurements are shown in Table
2.11.
Table 2.11: Detection Limits for Water Quality Determinants
|
Determinant |
Limit of Detection |
|
Dissolved Oxygen |
0.1 mg/L |
|
Temperature |
0.1 degree Celsius |
|
pH |
0.01 unit |
|
Turbidity |
0.1 NTU |
|
Suspended Solids |
1 mg/L |
|
BOD |
2 mg/L |
In situ measurement
All pH meters, DO/temperature
meters had been checked and calibrated prior to use. Standard buffer solution
of at least two pH levels (either pH 4 and pH 7, or pH 7 and pH 10) had been
used for calibration of the instrument before and after use.
DO meters had been calibrated by a
laboratory accredited under HOKLAS or any other international accreditation
scheme, and subsequently re-calibrated at three-monthly intervals throughout
all stages of the water quality monitoring. Responses of sensors and electrodes
had been checked with certified standard solutions before each use. Wet bulb
calibrations for all DO meters had been carried out before measurement at each
monitoring location. For the on site calibration of field equipment, BS
127:1993, "Guide to field and on-site test methods for the analysis of
waters" had been observed.
Measurements shall be at three water
depths, namely, 1m below water surface, mid-depth and 1m above stream bed/pond
bed, except where the water depth less that 6m, the mid-depth station maybe omitted. Should the water depth be less than 3m,
only the mid-depth station will be monitored.
Replicates in-situ measurements
and samples collected from each independent monitoring event are required for
all parameters to ensure a robust statistically interpretable dataset.
Water Samples Preparation and
Analysis
For collection of water sampling
within the water courses, a 500ml clean plastic beaker was used. After
collection, the water samples were stored in high-density polythene bottles.
The sample container was rinsed with a portion of the water sample. The water sample was then transferred to
the container, labelled with a unique sample ID and sealed with a screw cap. The water samples
were stored in a cool box maintained at 4oC. The water samples were then delivered to
a local HOKLAS-accredited laboratory (ALS) on the same day for analysis.
The testing methods of testing
parameters as recommended by EIA or required by EPD, with the QA/QC results are in accordance with the requirement of
HOKLAS or international accredited scheme.
The
calibration certificates for equipments used for in-situ
monitoring of water quality are attached in Appendix E.
Target species and certain other
fauna will be monitored within the Project Area and Assessment Area during the
wetland and residential construction phase. This will be important to ensure
that any unexpected events or impacts either on- or off-site are quickly
identified so that remedial action can be taken. The groups to be monitored and frequency of
monitoring are shown in Table 2.12.
Table 2.12: Summary of Construction Phase Ecological Monitoring
for the Wo Shang Wai Wetland Restoration Area (WRA)
|
Species /
Parameter |
Construction
Phase Ecological Monitoring |
|
Birds |
Weekly (including Assessment Area). |
|
Dragonflies and Butterflies |
Once per month during March and September to
November, and twice per month during April to August. |
|
Herpetofauna |
Once per month during April to November. |
|
Water Quality |
After filling of WRA with water, monthly for in situ water quality and every six
months (end of the wet season and end of the dry season) for laboratory
testing. |
|
Site Inspections |
Weekly. |
Ecological
monitoring locations during construction phase are shown in Figure 4.1 and the methodology for ecological monitoring is
detailed in Section 4.
·
The extent of the agreed works area should
be regularly checked during the construction phase. Any trespass by the
Contractor outside the limit of the works, including any damage to existing
trees and woodland shall be noted;
·
The progress of the engineering works
should be regularly reviewed on site to identify the earliest practical
opportunities for the landscape works to be undertaken;
·
All existing vegetation, streams and other
features within the study area which are not directly affected by the works are
retained and protected;
·
The methods of protecting existing
vegetation proposed by the Contractor are acceptable and enforced;
·
Preparation, lifting transport and
re-planting operations for any transplanted trees;
·
The layout, design and construction of
buildings conforms to requirements specified in the EIA report;
·
All landscaping works are carried out in
accordance with the EIA recommendations and with specifications;
·
The planting of new trees, shrubs,
groundcover, climbers, grasses and other plans, together with the replanting of
any transplanted trees are carried out properly and within the right season;
·
All necessary horticultural operations and
replacement planting are undertaken throughout the Establishment Period to
ensure the healthy establishment and growth of both transplanted trees and all
newly establishment plants.
Table 2.13: Construction and Operation
Phase Audit Checklist
|
Area of Works |
Items to be Monitored |
|
Works Area |
Check the extent of the Works to ensure
that the Works Area is not exceeded |
|
Protection
of all trees and woodland blocks to be retained |
Identification
and demarcation of trees / vegetation to be retained, erection of physical
protection (e.g. fencing), monitoring against possible incursion, physical
damage, fire, pollution, surface erosion, etc. |
|
Streams |
Ensure
no run-off into existing streams |
|
Clearance
of existing vegetation |
Identification
and demarcation of trees / vegetation to be cleared, checking of extent of
works to minimize damage, monitoring of adjacent areas against possible
incursion, physical damage, fire, pollution, surface erosion, etc. |
|
Transplanting
of trees |
Identification
and demarcation of trees / vegetation to be transplanted, monitoring of
extent of pruning / lifting works to minimize damage, timing of operations
implementation of all stages of preparatory and translocation works, and
maintenance of transplanted vegetation, etc. |
|
Topsoil
stripping |
Ensuring
existing topsoil is stripped and stored under recognized good practice and is
hydroseeded and regularly turned to prevent anaerobic conditions |
|
New
buildings |
Ensure
that building finishes accord with mitigation proposals with regard to colour
and albedo. |
|
Boundaries |
Ensuring
hoarding are erected as required |
|
Noise
Barrier |
Ensure
noise barrier design accords with the mitigation proposals with regard to
location, materials and finishes. |
|
Night-time
lighting |
Ensuring
night-time lighting is directional, hooded and shielded away from VSRs |
|
Plant
supply |
Monitoring
of operations relating to the supply of specialist plant material (including
the collecting, germination and growth of plants from seed) to ensure that
plants will be available in time to be used within the construction works. |
|
Landscape
and wetland treatments generally |
Check
that wetland, and hard / soft landscape designs conform to intent of
mitigation measures and agreed designs |
|
Soiling,
planting, etc. |
Monitoring
of implementation and maintenance of soiling and planting works against
possible incursion, physical damage, fire, pollution, surface erosion, etc. |
|
Establishment
Works |
Monitoring
of implementation of maintenance operation during Establishment Period |
The monitoring locations should
check against the mitigation measures proposed under the approved Environmental
Impact Assessment, which are summarised as follows:
Table 2.14: Proposed Construction Phase
Mitigation Measures
|
ID No. |
Landscape and Visual
Mitigation Measure |
|
CM1 |
The construction area and contractor’s
temporary works areas should be minimised to avoid impacts on adjacent
landscape. |
|
CM2 |
Screening of construction works by
hoardings/noise barriers around Works area in visually unobtrusive colours,
to screen Works. |
|
CM3 |
Reduction of construction period to
practical minimum. |
|
CM4 |
Topsoil, where identified, should be
stripped and stored for re-use in the construction of the soft landscape
works, where the soil material meets acceptable criteria and where
practical. The Contract Specification
shall include storage and reuse of topsoil as appropriate. |
|
CM5 |
Hydroseeding or sheeting of soil
stockpiles with visually unobtrusive material (in earth tone). |
|
CM6 |
Advance screen planting to noise
barriers. |
|
CM7 |
Control night-time lighting and glare by
hooding all lights. |
|
CM8 |
Ensure no run-off into streams adjacent
to Project Area. |
|
CM9 |
Protection of existing trees on boundary
of project area shall be carefully protected during construction. Detailed Tree Protection Specification
shall be provided in the Contract Specification. Under this specification,
the Contractor shall be required to submit, for approval, a detailed working
method statement for the protection of trees prior to undertaking any works
adjacent to all retained trees, including trees in contractor’s works
areas. (Tree protection measures will
be detailed at S16 and Tree Removal Application stage). |
|
CM10 |
Trees unavoidably affected by the works
shall be transplanted where practical.
Trees should be transplanted straight to their destinations and not
held in a nursery. A detailed Tree
Transplanting Specification shall be provided in the Contract Specification,
if applicable. Sufficient time for necessary tree root and crown preparation
periods shall be allowed in the project programme. |
Table 2.15: Proposed Operation Phase
Mitigation Measures
|
ID No. |
Landscape Mitigation Measure |
|
OM1 |
Compensatory Tree Planting for all felled
trees shall be provided to the satisfaction of relevant Government
departments. Required numbers and
locations of compensatory trees shall be determined and agreed separately
with Government during the Tree Felling Application process under ETWBTC
3/2006. |
|
OM2 |
A continuous belt of screen planting
along southern perimeter of project area with fast growing tree species. At least 450 trees capable of reaching a
height > 10m within 10 years should be planted. Planting of the belt of trees shall be
carried out as advance works ahead of other site formation and building
works. |
|
OM3 |
Maximise soft landscape and amenity water
bodies in residential areas of the development. Approximately 750 trees (of Heavy Standard
size) should be planted. Where space
permits, roadside berms should be created. Street trees should be of species
that reach a mature height of no less than 15m. |
|
OM4 |
Maximise freshwater habitat wetland
creation consistent with achieving other parameters. Minimum 4.74 ha to be provided. Wetlands must have natural edge profiles
with >1m wide emergent zone. No
access to the wetland by residents and all wetlands must be screened from
residential development by a continuous tree screen at interface with
residential development or earth mounding such that disturbance is minimised.
Implementation of the wetland shall be carried out as advance works. |
|
OM5 |
Use appropriate (visually unobtrusive and
non-reflective) building materials and colours in built structures. |
|
OM6 |
During detailed design, refine building
layout to create a min. 10m wide gap between buildings north of Wo Shang Wai
pond and also two min. 10m wide gaps in the row of buildings adjacent to
Royal Palms. |
|
OM7 |
Streetscape elements (e.g. paving,
signage, street furniture, lighting etc.) shall be sensitively designed in a
manner that responds to the local context, and minimises potential negative
landscape and visual impacts. Lighting
units should be directional and minimise unnecessary light spill. |
Impact monitoring for air quality (dust), noise and water quality
due to the construction work were undertaken during the reporting month in
compliance with the EM&A manual in the reporting period. Regular site
inspections were carried out on 2, 9, 16, 23 and 29 May 2013 in the reporting month to assess the compliance
with environmental requirements.
Results of 1-hour TSP at the four monitoring locations are summarised in Table 3.1. Graphical plots of the monitoring results are shown in Appendix F. The weather conditions in the reporting period are provided in Appendix G.
Table 3.1: Summary of 1-hour TSP Monitoring Results
|
Monitoring Date |
Start Time |
1-hr TSP (μg/m3) |
Range (μg/m3) |
Action Level
(μg/m3) |
Limit Level
(μg/m3) |
|||
|
1st
Result |
2nd
Result |
3rd
Result |
||||||
|
ASR1 |
||||||||
|
06-May-13 |
13:15 |
85 |
74 |
68 |
68-110 |
378 |
500 |
|
|
10-May-13 |
13:26 |
110 |
84 |
94 |
||||
|
16-May-13 |
13:23 |
84 |
90 |
72 |
||||
|
22-May-13 |
14:08 |
94 |
86 |
74 |
||||
|
28-May-13 |
13:10 |
74 |
91 |
83 |
||||
|
ASR2A |
||||||||
|
06-May-13 |
12:46 |
74 |
65 |
83 |
65-102
|
357 |
500 |
|
|
10-May-13 |
12:53 |
84 |
96 |
102 |
||||
|
16-May-13 |
12:50 |
86 |
94 |
76 |
||||
|
22-May-13 |
13:39 |
74 |
80 |
91 |
||||
|
28-May-13 |
12:47 |
83 |
74 |
90 |
||||
|
ASR3 |
||||||||
|
06-May-13 |
12:32 |
89 |
92 |
74 |
65-104 |
358 |
500 |
|
|
10-May-13 |
12:33 |
94 |
100 |
88 |
||||
|
16-May-13 |
12:37 |
92 |
104 |
88 |
||||
|
22-May-13 |
13:18 |
84 |
93 |
74 |
||||
|
28-May-13 |
12:34 |
72 |
65 |
80 |
||||
|
ASR4 |
||||||||
|
06-May-13 |
13:11 |
104 |
96 |
83 |
83-113 |
372 |
500 |
|
|
10-May-13 |
13:16 |
113 |
105 |
96 |
||||
|
16-May-13 |
13:18 |
106 |
93 |
84 |
||||
|
22-May-13 |
13:59 |
102 |
96 |
88 |
||||
|
28-May-13 |
13:03 |
105 |
93 |
112 |
||||
Results of 24-hour TSP at the four monitoring locations are summarised in Table 3.2. Graphical plots of the monitoring results are shown in Appendix F. The weather conditions in the reporting period are provided in Appendix G.
Table 3.2: Summary of 24-hour TSP Monitoring Results
|
Monitoring Date |
Monitoring
Results (μg/m3) |
Range
(μg/m3) |
Action Level
(μg/m3) |
Limit Level
(μg/m3) |
|
ASR1 |
|
|
|
|
|
06-May-13 |
88 |
82-98 |
226 |
260 |
|
10-May-13 |
98 |
|||
|
16-May-13 |
86 |
|||
|
22-May-13 |
82 |
|||
|
28-May-13 |
91 |
|||
|
ASR2A |
|
|
|
|
|
06-May-13 |
83 |
75-90 |
213 |
260 |
|
10-May-13 |
90 |
|||
|
16-May-13 |
75 |
|||
|
22-May-13 |
82 |
|||
|
28-May-13 |
82 |
|||
|
ASR3 |
|
|
|
|
|
06-May-13 |
87 |
74-96 |
205 |
260 |
|
10-May-13 |
96 |
|||
|
16-May-13 |
80 |
|||
|
22-May-13 |
74 |
|||
|
28-May-13 |
93 |
|||
|
ASR4 |
|
|
|
|
|
06-May-13 |
96 |
76-98
|
237 |
260 |
|
10-May-13 |
98 |
|||
|
16-May-13 |
82 |
|||
|
22-May-13 |
76 |
|||
|
28-May-13 |
90 |
No exceedance of 1-hour and 24-hour TSP (Action or Limit Level) was recorded in the reporting period.
The construction noise monitoring results are summarized in Table 3.3. Graphical plots of the monitoring data are shown in Appendix F. The weather conditions in the reporting period are provided in Appendix G.
Table 3.3: Summary of Construction
Noise Monitoring Results
|
Monitoring Date |
Start Time |
Mean &
Range of Noise Levels, dB(A) |
Limit Level
for Leq (dB) |
||
|
Leq |
L10 |
L90 |
|||
|
NSR1 |
|
|
|
|
>
75 |
|
06-May-13 |
15:59 |
57 |
58 |
46 |
|
|
16-May-13 |
15:06 |
56 |
58 |
53 |
|
|
22-May-13 |
15:59 |
56 |
59 |
51 |
|
|
28-May-13 |
15:27 |
54 |
60 |
43 |
|
|
NSR3 |
|
|
|
|
|
|
06-May-13 |
15:19 |
57 |
58 |
44 |
|
|
16-May-13 |
15:50 |
58 |
61 |
49 |
|
|
22-May-13 |
16:39 |
56 |
57 |
49 |
|
|
28-May-13 |
14:47 |
55 |
57 |
53 |
|
|
NSR5 |
|
|
|
|
|
|
06-May-13 |
13:22 |
59 |
61 |
56 |
|
|
16-May-13 |
13:29 |
58 |
60 |
54 |
|
|
22-May-13 |
14:15 |
57 |
58 |
54 |
|
|
28-May-13 |
13:19 |
57 |
61 |
51 |
|
|
NSR7 |
|
|
|
|
|
|
06-May-13 |
14:34 |
64 |
67 |
60 |
|
|
16-May-13 |
14:18 |
65 |
68 |
60 |
|
|
22-May-13 |
15:10 |
61 |
64 |
58 |
|
|
28-May-13 |
14:02 |
67 |
70 |
64 |
|
No exceedance (Action/Limit Level) of construction noise was recorded in the reporting period.
The water quality monitoring results are summarized in Table 3.4. Graphical plots of the monitoring data are shown in Appendix F. The weather conditions in the reporting period are provided in Appendix G.
Table 3.4: Summary of Water Quality Monitoring Results
|
Monitoring Date |
Temp (oC) |
pH |
Dissolved Oxygen (DO) (mg/L) |
DO (%) |
Turbidity
(NT) |
BOD (mg/L) (1) |
Suspended
Solids (mg/L) |
|
MP3 |
|
|
|
|
|
|
|
|
02/05/2013 |
22.6 |
7.3 |
3.6 |
41.2 |
66.2 |
5 |
62 |
|
04/05/2013 |
22.9 |
7.3 |
7.6 |
88.2 |
17.9 |
6 |
17.5 |
|
06/05/2013 |
24.4 |
7.3 |
6.4 |
75.9 |
30.0 |
83.5 |
30 |
|
08/05/2013 |
24.5 |
7.4 |
3.4 |
41.1 |
50.7 |
6.5 |
48 |
|
10/05/2013 |
26.8 |
7.3 |
3.8 |
48.1 |
41.3 |
6.5 |
35.5 |
|
13/05/2013 |
28.3 |
7.3 |
4.3 |
54.2 |
30.9 |
9 |
30 |
|
15/05/2013 |
28.7 |
7.3 |
4.0 |
51.2 |
32.7 |
8 |
29 |
|
18/05/2013 |
28.4 |
7.3 |
4.8 |
61.9 |
54.6 |
21 |
54 |
|
20/05/2013 |
28.1 |
7.3 |
4.7 |
59.6 |
49.4 |
11.5 |
52 |
|
22/05/2013 |
24.8 |
7.3 |
5.8 |
66.9 |
48.9 |
7 |
41.5 |
|
24/05/2013 |
30.1 |
7.3 |
4.4 |
55.9 |
79.5 |
8 |
81.5 |
|
27/05/2013 |
28.5 |
7.3 |
5.0 |
65.2 |
60.2 |
9 |
57.5 |
|
29/05/2013 |
29.5 |
7.8 |
6.1 |
70.8 |
53.6 |
8 |
42 |
|
31/05/2013 |
29.8 |
7.5 |
6.0 |
79.5 |
65.0 |
6 |
101 |
|
Action Level |
- |
<5.5 or >7.5 |
<6.85 |
- |
>64 |
- |
>65 |
|
Limit
Level |
- |
<4.0 or >8.0 |
<6.65 |
- |
>67 |
- |
>66 |
|
|
|
|
|
|
|
|
|
|
MP4 |
|
|
|
|
|
|
|
|
02/05/2013 |
20.7 |
7.5 |
3.7 |
40.8 |
14.9 |
5 |
15.5 |
|
04/05/2013 |
22.0 |
7.5 |
6.2 |
69.8 |
34.9 |
4.5 |
37.5 |
|
06/05/2013 |
23.8 |
7.4 |
3.4 |
39.8 |
17.0 |
3 |
15.5 |
|
08/05/2013 |
23.8 |
7.4 |
3.5 |
40.9 |
15.4 |
7.5 |
31 |
|
10/05/2013 |
26.7 |
7.5 |
4.1 |
51.3 |
27.3 |
7 |
23 |
|
13/05/2013 |
26.9 |
7.4 |
3.7 |
46.8 |
33.0 |
5.5 |
29.5 |
|
15/05/2013 |
28.1 |
7.4 |
4.5 |
56.3 |
19.8 |
5 |
22 |
|
18/05/2013 |
28.0 |
7.4 |
5.0 |
66.0 |
62.0 |
34 |
81.5 |
|
20/05/2013 |
28.4 |
7.4 |
6.2 |
72.0 |
75.4 |
4 |
78.5 |
|
22/05/2013 |
23.7 |
7.5 |
4.8 |
61.0 |
105.0 |
2 |
70.5 |
|
24/05/2013 |
29.9 |
7.5 |
6.2 |
71.8 |
225.0 |
5 |
135 |
|
27/05/2013 |
28.2 |
7.4 |
6.2 |
72.1 |
344.5 |
5 |
224 |
|
29/05/2013 |
29.1 |
7.4 |
6.0 |
69.0 |
59.3 |
3.5 |
61 |
|
31/05/2013 |
26.7 |
7.3 |
4.6 |
52.2 |
47.6 |
2.5 |
62.5 |
|
Action Level |
- |
<5.5 or >7.5 |
<3.91 |
- |
>60 |
- |
>50 |
|
Limit
Level |
- |
<4.0 or >8.0 |
<3.82 |
- |
>64 |
- |
>53 |
|
|
|
|
|
|
|
|
|
|
MP5 |
|
|
|
|
|
|
|
|
02/05/2013 |
20.8 |
7.5 |
5.2 |
58.2 |
37.5 |
4 |
36.5 |
|
04/05/2013 |
22.6 |
7.6 |
6.1 |
69.9 |
45.9 |
5 |
39.5 |
|
06/05/2013 |
24.8 |
7.5 |
4.2 |
50.0 |
27.8 |
3 |
26.5 |
|
08/05/2013 |
24.1 |
7.4 |
3.2 |
36.6 |
28.8 |
16 |
16.5 |
|
10/05/2013 |
27.3 |
7.5 |
4.5 |
56.0 |
30.2 |
5.5 |
20.5 |
|
13/05/2013 |
27.5 |
7.4 |
3.7 |
46.4 |
34.0 |
7 |
26.5 |
|
15/05/2013 |
27.4 |
7.4 |
3.1 |
39.2 |
35.4 |
5 |
36 |
|
18/05/2013 |
28.1 |
7.4 |
4.5 |
57.9 |
57.9 |
14.5 |
42.5 |
|
20/05/2013 |
27.6 |
7.5 |
4.4 |
55.8 |
37.2 |
4 |
41 |
|
22/05/2013 |
24.1 |
7.6 |
3.7 |
45.3 |
94.5 |
3 |
86.5 |
|
24/05/2013 |
29.4 |
7.5 |
4.8 |
61.3 |
41.0 |
6 |
32.5 |
|
27/05/2013 |
28.1 |
7.5 |
6.4 |
75.1 |
156.5 |
4 |
125 |
|
29/05/2013 |
29.4 |
7.5 |
5.8 |
65.8 |
73.4 |
3 |
63.5 |
|
31/05/2013 |
26.7 |
7.5 |
4.5 |
53.4 |
46.6 |
3 |
49 |
|
Action Level |
- |
<5.5 or >7.5 |
<4.13 |
- |
>81 |
- |
>66 |
|
Limit
Level |
- |
<4.0 or >8.0 |
<3.87 |
- |
>84 |
- |
>69 |
|
|
|
|
|
|
|
|
|
|
MP6 |
|
|
|
|
|
|
|
|
02/05/2013 |
21.1 |
7.5 |
5.8 |
64.1 |
65.5 |
7 |
49 |
|
04/05/2013 |
22.8 |
7.6 |
5.7 |
62.0 |
63.9 |
6 |
70 |
|
06/05/2013 |
24.7 |
7.5 |
4.8 |
56.8 |
30.8 |
9 |
36 |
|
08/05/2013 |
23.8 |
7.4 |
3.9 |
45.4 |
34.8 |
7 |
32 |
|
10/05/2013 |
26.8 |
7.5 |
3.9 |
48.6 |
43.2 |
6 |
43 |
|
13/05/2013 |
26.8 |
7.5 |
4.3 |
53.2 |
53.2 |
7 |
56.5 |
|
15/05/2013 |
27.2 |
7.5 |
3.8 |
47.4 |
95.7 |
5 |
132 |
|
18/05/2013 |
27.8 |
7.5 |
4.7 |
60.2 |
82.7 |
11 |
102 |
|
20/05/2013 |
27.5 |
7.5 |
3.7 |
47.6 |
29.0 |
12 |
35.5 |
|
22/05/2013 |
23.8 |
7.6 |
4.1 |
52.0 |
82.2 |
2.5 |
59 |
|
24/05/2013 |
29.2 |
7.6 |
4.1 |
52.6 |
39.2 |
5 |
21.5 |
|
27/05/2013 |
27.9 |
7.5 |
4.8 |
60.7 |
39.1 |
3 |
33 |
|
29/05/2013 |
29.2 |
7.5 |
6.4 |
75.0 |
138.2 |
4 |
126.5 |
|
31/05/2013 |
26.8 |
7.2 |
4.3 |
49.8 |
63.4 |
6 |
100.5 |
|
Action Level |
- |
<5.5 or >7.5 |
<4.61 |
- |
>94 |
- |
>75 |
|
Limit
Level |
- |
<4.0 or >8.0 |
<4.52 |
- |
>96 |
- |
>75 |
Notes:
(1) “<2 “ : BOD
value is too low to indicate (<2mg/L).
(2) Values Bold indicate Action Level exceedance.
(3) Values Underlined and Bold indicate Limit Level exceedance.
Exceedance Investigation and Findings
During May 2013, Action Level
exceedances of pH were observed at MP3, MP5 and MP6, while exceedances of DO,
turbidity and/or SS were observed at MP3 to MP6. DO exceedance was observed 13
times at MP3, four times at MP4, four times at MP5 and eight times at MP6. SS
and/or turbidity exceedance was recorded on three monitoring dates at MP3,
seven monitoring dates at MP4, two monitoring dates at MP5 and four monitoring
dates at MP6 during the reporting month.
The Event and Action Plan in Appendix
D was followed under these cases of exceedances.
From investigation, construction
activities during the period of exceedance included mainly site formation and
foundation work, as well as pond drainage management in the Wetland Restoration
Area (to lower the water level and remove unwanted species in the pond). It was
observed that the Contractor has implemented water quality mitigation measures
as recommended in the EIA report, including the provision of temporary drainage
facility and associated treatment facility. Sand bags are in place in the
temporary drainage channel to enhance the desilting efficiency. The Contractor
further enhanced the water quality mitigation measures by erecting several
segments of rock bunds at the discharge outlet to avoid site runoff draining
directly to the northern ditches.
Exceedances of pH, DO and
turbidity and SS at MP3
Exceedance of the action and/or limit level of
pH observed on one monitoring date at MP3, while Action/Limit Level exceedance
of DO was recorded on 13 monitoring dates at MP3. Also, Action/Limit Level
exceedance of turbidity and/or SS were observed on three monitoring dates, As
understood, the fish pond near the site (represented by MP3) was being
separated from the construction site by the WRA since November 2010, so the
exceedances were not considered to be related to the construction activities.
The exceedances of pH, DO, turbidity and SS may be due to external factors such
as pond fish culture activities which were out of the control of the project.
The turbidity exceedance may have been caused by fish movements.
Exceedances of pH, DO, turbidity
and SS at MP4 to MP6
During the reporting month, exceedance of the
Action/Limit Level of pH was observed at MP5 and MP6 but not observed at MP4.
Meanwhile, Action/Limit Level of DO was exceeded four times at MP4, four times
at MP5 and eight times at MP6. Action/Limit Level exceedance of turbidity was
observed on at MP4 on 18, 20, 22, 24 and 27 May 2013, at MP5 on 22 and 27 May
2013 and at MP6 on 15 and 29 May 2013. Action/Limit Level exceedance of SS was
observed at MP4 on 18, 20, 22, 24, 27, 29 and 31 May 2013, at MP5 on 22 and 27
May 2013 and at MP6 on 15, 18, 29 and 31 May 2013.
From
Hong Kong Observatory (HKO) records, total rainfall recorded at HKO during the
reporting month was 509.3 mm, which was well above the 1981-2010 climatological
normal for the same month of 304.7 mm. The heaviest rain fell on 22 and 25 May
2013 when 230.8 and 52.0 mm of rain were recorded respectively at HKO. Black
and Red Rainstorm Warning signals as well as Special Announcement on Flooding
in the northern
The
heavy and/or persistent rainfall may have caused a large amount of surface
runoff from all sources in the vicinity of the open ditch. It is believed that
the runoff significantly increased the turbulence and thus resulted in higher
turbidity and/or SS inside the ditch water on the days of turbidity and/or SS
exceedance. This may have caused the colour of water body in the ditch to be
brown at MP4 on 24 May 2013 (please refer to Photo 4). The higher SS induced by
the heavy and/or persistent rain may also have resulted in a decrease in DO on
some of the monitoring days.
From
photo record at MP4 and MP5 on 27 May 2013, suspected routine dredging works
(unrelated to the Project) to remove floating plants in the open ditch were observed
during monitoring and the colour of water body in the ditch was brown at MP4
and slightly brown at MP5. These works may have significantly increased the
turbulence and therefore may have caused the particularly higher turbidity and
SS inside the ditch water at MP4 and MP5 on this particular day. Furthermore,
the colour of the water body in the ditch was brown at MP6 on 29 May 2013. This
may have been a consequential flow-on effect from the nearby abovementioned
dredging works which may have increased the turbulence at MP6, causing the
particularly higher turbidity and/or SS inside the ditch water at that location
on 29 and 31 May 2013.
Also, the
site effluent was effectively treated by the AquaSed system and discharged from
the site at a low, controlled rate during the reporting month.
Conclusion
As a result, the abovementioned exceedances are
unlikely to be due to the construction works and therefore not considered to be
related to the project.
This report documents surveys conducted in the
Survey Area between 1 and 31 May 2013.
The Wetland Restoration Area (WRA) is also surveyed as the area is accessible
and site formation works for WRA has been completed. The updated survey transect is provided in Figure 4.1.
Dates and ecological surveys conducted during this period are summarised in Appendix H.
Monitoring was undertaken following the survey
methodology in the EM&A Manual. A transect was followed in the bird surveys
(see Figure 4.1). All
bird species were identified to species and all bird species of conservation
importance and/or wetland dependent were enumerated and recorded to the
habitats in which they were observed. Flying birds were not recorded unless
they were foraging and/or associated with the habitat (such as swifts). Further,
notable bird observations during other surveys were also recorded.
Bird surveys were conducted on a weekly basis. A total of 33 bird species were recorded in the
Survey Area (excluding the WRA), 16 of which were species of conservation
importance and/or wetland-dependence. Within the WRA, 18 bird species were
recorded, 9 of which were species of conservation importance and/or
wetland-dependent species, including one of the target species (i.e. Little
Egret) was recorded. A
summary of survey data is provided in Appendix I.
One night time herpetofauna survey was
conducted in the reporting month. One Gunther's Frog was recorded in the Survey
Area (excluding the WRA) and one Checkered Keelback was recorded in the WRA
Monitoring of dragonflies and butterflies were conducted on a
bi-weekly basis according to the EM&A Manual. A total of six odonata species were recorded in the Survey Area
(excluding the WRA) while six butterfly species were recorded. Within the WRA, a total of 14 odonata species were recorded, while four butterfly species were recorded. A summary
of the survey findings is provided in Appendix J.
Monitoring
of mammals was conducted concurrently with other surveys. No mammals were
recorded in the Survey Area (excluding the WRA) nor the WRA during regular
survey. No mammals species were recorded in other surveys. A summary of the
survey findings is provided in Appendix J.
During the reporting period, pH of Cells 2 and 4 reached the Action Level. No measures
are proposed at the moment, but the condition will be monitored. Monitoring data are
presented in Appendix K.
Pedology samples
were collected on 31 May 2013 for laboratory analysis of soil quality. Results
will be presented in a future Monthly EM&A Report when the data are received.
Removal of exotic vegetation in all cells was undertaken; these
included but not limited to Ipomoes sp.,
Mikania sp., Mimosa sp., Pennisetum sp.
and Typha sp.
Vegetation management activities undertaken at the
site primarily involved watering of plants, weeding and grass cutting.
Removal of Golden
Apple Snail was undertaken on an “as-seen” basis.
All
sighted red fire ant nests were treated with approved pesticide.
Ecological monitoring during May 2013 was carried out according to the
survey methodology and frequency outlined in the EM&A Manual.
Summary of survey findings is listed as follows:
Table 4.1: Summary of Ecological Monitoring in WRA and Survey Area
|
Species |
Survey Area (excluding WRA) |
WRA |
|
Birds (total) |
33 |
18 |
|
Birds (of conservation importance and/or
wetland-dependence) |
16 |
9 |
|
Amphibians |
1 |
0 |
|
Reptiles |
0 |
1 |
|
Mammals |
0 |
0 |
|
Odonates |
6 |
14 |
|
Butterflies |
6 |
4 |
Survey findings indicate that the ponds within the Survey Area
supported numbers and diversity of wetland-dependent birds typical of fish pond
areas. The WRA continues to attract
wetland dependent fauna and serves as a buffer between the residential portion
and the fishponds in the north.
The EM&A programme for
Landscape and Visual impact due to the construction commenced in May 2010 and
continued during the reporting period. Site inspections on Landscape and Visual
impact were carried out on 15 and 28 May 2013 to confirm the implementation of
mitigation measures at construction stage.
The audit was
undertaken with references to the specific checklists provided in Tables 2.13 – 2.15 and audit results
are summarized as below:
Table 5.1: Construction and Operation Phase Audit Summary
|
Area of Works |
Items to be Monitored |
|
Works Area |
The boundaries of the works area have been
established on site in accordance with the contract documents and approved
plans (EP), and the limit of current heavy construction activity is now
confined to within the site hoardings (North side of the site / access road)
and the noise barriers (other sides of the site). Minor works such as horticultural
maintenance of the planting and transplanted trees, and boundary fence
repair was proceeding along the Royal Palms - No construction works were observed to have
exceeded the site boundaries. No construction was carried out at the wetland restoration area after 15 November 2010. |
|
Protection of all trees and woodland blocks
to be retained |
Trees retained within the site along the
northeast boundary, beside wetland restoration area, have been identified
and protected by temporary protective fencing. |
|
Streams |
The works site is partly encircled by a berm
/ perimeter channel to intercept surface water and prevent it from washing
off into any of the neighboring sites.
Surface water is collected within the site in a temporary drainage
channel. Gravels beds and barriers
have been installed to filter site runoff, sedimentation ponds have been
provided to enable primary treatment before discharge to mains drains. |
|
Clearance of existing vegetation |
Site clearance was completed prior to the
commencement of construction. |
|
Transplanting of trees |
Tree transplanting has been completed, with
the trees relocated to various points within the planting strip along the
southern boundary of the site, outside the noise barrier. The trees continue to re-establish well. |
|
Topsoil stripping |
Suitable pond bund and soil material which
had been excavated and stockpiled from the original site, has now been
re-used within the landscape works Dust suppression measures are active along
all internal site access tracks. |
|
New buildings |
No new permanent buildings have yet been
constructed on site |
|
Boundaries |
Hoardings have been erected along most of the
boundaries of the site. Installation
of new screen fence between the future residential sites and the constructed
wetland restoration areas is complete. Fence has been painted green to match
with the surrounding vegetated environment. |
|
Noise Barrier |
Noise barriers have been installed along the
southern and western boundaries of the site in accordance with the contract
requirements. Their design complies
with the mitigation requirements, with upper 6 to 7m portion of the barrier
being made from a translucent material with green tinted (to match with the
environment). Supporting GMS structure, likewise, has been painted green. |
|
Night-time lighting |
No night-time works were reported to have
been carried out during the monitoring period |
|
Landscape and wetland treatments generally |
Continuous belt of screen planting along the
southern and western boundaries of the site has been completed. The formation, soiling and water control
structures of the wetland restoration area have been completed. The wetland areas are being established, with
the ponds are being seasonally filled with rain water. Planting of areas around the WRA cells is
complete. No construction was carried
out at the wetland restoration area after 15 November 2010. |
|
Soiling, etc. |
The soiling for the advance planting strip
has been completed. The soil
placement and grading for each of the wetland restoration areas has been
completed. |
|
Plant supply |
The plant material used in the Advance
Planting Strip and in the WRA are all commonly available species and came
from commercial sources. Transplanted reeds (Phragmites australis)
at the wetland habitat came from the temporary holding nursery onsite. |
|
Planting |
The total number of trees that will reach a
minimum of 10m in the advance planting strip meets the contract
requirements. The tree species are
all from the approved list. This planting
should achieve the required screening effect within the required time
period. Some of the trees that were identified as
dead in previous month or having defects (i.e. extensive bark damage,
cavities, fungal growths etc) still need to be replaced with new specimens.
Some of the recently planted trees are still in poor condition, but are
showing small signs of graduate improvement Seedling trees and shrubs, have been
established at the margins of the wetland cells. Some additional fill-in
planting has been undertaken. |
|
Establishment
Works |
Maintenance operations for the advance
planting, compensatory planting and transplanted trees are generally being
undertaken in accordance with the specification, although some of the long
outstanding items have not yet been addressed / fully addressed Some of the taller trees that were partially
blown over, or growing into the noise barrier structure, have been set
upright and supported with cables and bamboo stakes, but the technique used
is unsatisfactory and many trees still need to be rectified. Precautions should be taken to prevent
tree damage by the structure. Trees from outside the site which fell on top
of trees in the advance planting strip, have partly been removed but no
rectification of affected trees has been undertaken. Some of the trees previously noted as having
severe trunk damage (e.g. lower trunk of T333), and fungal growths on the
bark, still need to be replaced with new specimens. Trees T21 and T364 have lost their leader
and are no longer viable, so should be removed and replaced. Branches broken on trees have been pruned
away. Workmanship of some pruning works did not comply with proper
arboricultural practice resulting in bark tearing. Large hanging branches on
T20, T266 and T419 should be removed immediately. Broken branch noted on
tree behind the newly planted shrubs near WRA cell 4 Profuse fungal growth was noted on trunk of
T292. Tree is irreparably damaged / rotten and should be removed
immediately. Some of the tree tags are embedding into the
trunk. Tree ties and tags should be re-set to avoid strangling the trees.
Excessive sap flow due to a tight wire on the trunk of T142. Some shrub areas are covered with fallen
leaves, branches and debris which needs to be cleared away. In some areas
shrub growth is still thin and needs to be replanted. Many fungi are growing on the dead vegetable
matter throughout the advance planting strip. These should be cleared and
fungicide applied. Soil exposed in the bare areas is beginning
to erode, and surface protection / replanting is urgently required. Soil
runoff from the area near the noise barrier needs to be cleared away and
barriers erected to prevent its re-occurrence. Invasive climbers and weeds have been cleared
in some areas behind the noise barrier and along the planting strip but many
areas still need clearance. Weeding should be carried out thoroughly, on a
monthly basis, as weeds will inhibit growth of the advance planting. Pruning of all overgrown shrubs needs to be
undertaken regularly. Regular horticultural maintenance (grass
cutting, weeding, watering etc.) in the shrubs and tree seedling areas
around the WRA cells is being undertaken. The stands of Phragmites australis reeds in the WRA cells are still growing
profusely and becoming invasive.
Although some have been partially cleared, active management of these
reeds is urgently needed to stop them from affecting other plant species
(repeat). The growth of seedling trees / shrubs planted
on the north side of WRA1 is unsatisfactory and needs improvement. |
The ET had carried out construction
phase weekly site inspections on 7, 16, 23 and 28 May 2013. All observations
have been recorded in the site inspection checklist and passed to the
Contractor together with the appropriate recommended mitigation measures where
necessary. The key observations from site inspections and associated
recommendations are summarized in Table 6.1.
Table 6.1: Summary of Site Inspections and Recommendations
|
Key
Observations |
ET Recommendation |
Contractor’s Responses / Action(s) Undertaken |
Close-out (Date) |
|
Some
parts of the haul road were dry |
To
provide water spray to minimize fugitive dust nuisance |
Agreed and followed up |
21 May
2013 |
|
Some
oil stains on the ground were observed |
To
remove the oil stains and treat affected soil as chemical waste |
Agreed and followed up |
21 May 2013 |
The Contractor has been registered as a
chemical waste producer for the Project. Construction and demolition (C&D)
material sorting was carried out on site. A sufficient number of receptacles were
available for general refuse collection.
As advised by the Contractor, no C&D material was generated on
site during the period. 4[w1] kg of metals was generated and collected by registered recycling
collector. 3 kg of paper/cardboard packing and 15 kg of plastic were generated
on site and collected by registered recycling collector. No chemical waste was
generated and collected by licensed chemical waste collector. 90 kg of other types of wastes (e.g.
general refuse) was generated on site and disposed of at public landfill
facility.
The Contractor is advised to maintain on
site waste sorting and recording system and maximize reuse/recycling of C&D
wastes.
The environmental permits, licenses, and/or
notifications on environmental protection for this Project which were valid during
the reporting period is summarised in Table
6.2.
Table 6.2: Status of Environmental Submissions, Licenses and Permits
|
Statutory Reference |
Description |
Permit/Reference No. |
Status |
|
EIAO |
Environmental Permit |
EP-311/2008/D |
Valid |
|
APCO |
Notification of
Construction Work under APCO |
316688
(27 Apr 2010) |
Valid |
|
WPCO |
Discharge
License |
WT00007442-2010
(2 Nov 2010) |
Valid |
|
WDO |
Registration as Chemical
Waste Producer |
WPN0000-542-H3083-04 |
Valid |
|
WDO |
Bill Account for
disposal |
700945423 |
Valid |
Legend: EIAO
– Environmental
Impact Assessment Ordinance
APCO – Air Pollution Control Ordinance
WPCO – Water Pollution Control Ordinance
WDO – Waste Disposal Ordinance
The EM&A programme followed the
recommended mitigation measures in the EM&A Manual. The EM&A
requirements as well as the summary of implementation status of the
environmental mitigation measures are provided in Appendix L. In particular, the following
mitigation measures were brought to attention during the site audits:
Air Quality
·
Access roads should be sprayed with water or dust
suppression chemical to maintain the entire road surface wet or paved; and
·
All
vehicles should be washed to remove any dusty materials before leaving the
construction sites.
Water Quality
·
Soil contaminated with chemicals/oils should be
removed from site, and the voids created should be filled with suitable
materials.
·
Ensure
proper functioning of the wastewater treatment
facility; and
·
Silt and debris should be removed from the temporary
drainage channel regularly.
Waste Management
·
Reuse the excavated materials as far as practical to
reduce the amount of waste disposal; and
·
Oil
stains on soil should be cleared by disposal of contaminated soil.
There is no breach of Action or Limit Levels
for Air Quality and Noise monitoring in the reporting month.
During May 2013,
Action Level exceedances of pH were observed at MP3, MP5 and MP6, while
exceedances of DO, turbidity and/or SS were observed at MP3 to MP6. DO
exceedance was observed 13 times at MP3, four times at MP4, four times at MP5
and eight times at MP6. SS and/or turbidity exceedance was recorded on three
monitoring dates at MP3, seven monitoring dates at MP4, two monitoring dates at
MP5 and four monitoring dates at MP6 during the reporting month.
Table 7.1: Summary of Exceedances in Water Quality
|
Monitoring
Date |
pH |
Dissolved
Oxygen (mg/L) |
Turbidity
(NT) |
Suspended
Solids (mg/L) |
|
MP3 |
|
|
|
|
|
02/05/2013 |
7.3 |
3.6 |
66.2 |
62 |
|
04/05/2013 |
7.3 |
7.6 |
17.9 |
17.5 |
|
06/05/2013 |
7.3 |
6.4 |
30.0 |
30 |
|
08/05/2013 |
7.4 |
3.4 |
50.7 |
48 |
|
10/05/2013 |
7.3 |
3.8 |
41.3 |
35.5 |
|
13/05/2013 |
7.3 |
4.3 |
30.9 |
30 |
|
15/05/2013 |
7.3 |
4.0 |
32.7 |
29 |
|
18/05/2013 |
7.3 |
4.8 |
54.6 |
54 |
|
20/05/2013 |
7.3 |
4.7 |
49.4 |
52 |
|
22/05/2013 |
7.3 |
5.8 |
48.9 |
41.5 |
|
24/05/2013 |
7.3 |
4.4 |
79.5 |
81.5 |
|
27/05/2013 |
7.3 |
5.0 |
60.2 |
57.5 |
|
29/05/2013 |
7.8 |
6.1 |
53.6 |
42 |
|
31/05/2013 |
7.5 |
6.0 |
65.0 |
101 |
|
Action Level |
<5.5 or >7.5 |
<6.85 |
>64 |
>65 |
|
Limit
Level |
<4.0 or >8.0 |
<6.65 |
>67 |
>66 |
|
|
|
|
|
|
|
MP4 |
|
|
|
|
|
02/05/2013 |
7.5 |
3.7 |
14.9 |
15.5 |
|
04/05/2013 |
7.5 |
6.2 |
34.9 |
37.5 |
|
06/05/2013 |
7.4 |
3.4 |
17.0 |
15.5 |
|
08/05/2013 |
7.4 |
3.5 |
15.4 |
31 |
|
10/05/2013 |
7.5 |
4.1 |
27.3 |
23 |
|
13/05/2013 |
7.4 |
3.7 |
33.0 |
29.5 |
|
15/05/2013 |
7.4 |
4.5 |
19.8 |
22 |
|
18/05/2013 |
7.4 |
5.0 |
62.0 |
81.5 |
|
20/05/2013 |
7.4 |
6.2 |
75.4 |
78.5 |
|
22/05/2013 |
7.5 |
4.8 |
105.0 |
70.5 |
|
24/05/2013 |
7.5 |
6.2 |
225.0 |
135 |
|
27/05/2013 |
7.4 |
6.2 |
344.5 |
224 |
|
29/05/2013 |
7.4 |
6.0 |
59.3 |
61 |
|
31/05/2013 |
7.3 |
4.6 |
47.6 |
62.5 |
|
Action
Level |
<5.5 or >7.5 |
<3.91 |
>60 |
>50 |
|
Limit
Level |
<4.0 or >8.0 |
<3.82 |
>64 |
>53 |
|
|
|
|
|
|
|
MP5 |
|
|
|
|
|
02/05/2013 |
7.5 |
5.2 |
37.5 |
36.5 |
|
04/05/2013 |
7.6 |
6.1 |
45.9 |
39.5 |
|
06/05/2013 |
7.5 |
4.2 |
27.8 |
26.5 |
|
08/05/2013 |
7.4 |
3.2 |
28.8 |
16.5 |
|
10/05/2013 |
7.5 |
4.5 |
30.2 |
20.5 |
|
13/05/2013 |
7.4 |
3.7 |
34.0 |
26.5 |
|
15/05/2013 |
7.4 |
3.1 |
35.4 |
36 |
|
18/05/2013 |
7.4 |
4.5 |
57.9 |
42.5 |
|
20/05/2013 |
7.5 |
4.4 |
37.2 |
41 |
|
22/05/2013 |
7.6 |
3.7 |
94.5 |
86.5 |
|
24/05/2013 |
7.5 |
4.8 |
41.0 |
32.5 |
|
27/05/2013 |
7.5 |
6.4 |
156.5 |
125 |
|
29/05/2013 |
7.5 |
5.8 |
73.4 |
63.5 |
|
31/05/2013 |
7.5 |
4.5 |
46.6 |
49 |
|
Action Level |
<5.5 or >7.5 |
<4.13 |
>81 |
>66 |
|
Limit
Level |
<4.0 or >8.0 |
<3.87 |
>84 |
>69 |
|
|
|
|
|
|
|
MP6 |
|
|
|
|
|
02/05/2013 |
7.5 |
5.8 |
65.5 |
49 |
|
04/05/2013 |
7.6 |
5.7 |
63.9 |
70 |
|
06/05/2013 |
7.5 |
4.8 |
30.8 |
36 |
|
08/05/2013 |
7.4 |
3.9 |
34.8 |
32 |
|
10/05/2013 |
7.5 |
3.9 |
43.2 |
43 |
|
13/05/2013 |
7.5 |
4.3 |
53.2 |
56.5 |
|
15/05/2013 |
7.5 |
3.8 |
95.7 |
132 |
|
18/05/2013 |
7.5 |
4.7 |
82.7 |
102 |
|
20/05/2013 |
7.5 |
3.7 |
29.0 |
35.5 |
|
22/05/2013 |
7.6 |
4.1 |
82.2 |
59 |
|
24/05/2013 |
7.6 |
4.1 |
39.2 |
21.5 |
|
27/05/2013 |
7.5 |
4.8 |
39.1 |
33 |
|
29/05/2013 |
7.5 |
6.4 |
138.2 |
126.5 |
|
31/05/2013 |
7.2 |
4.3 |
63.4 |
100.5 |
|
Action Level |
<5.5 or >7.5 |
<4.61 |
>94 |
>75 |
|
Limit
Level |
<4.0 or >8.0 |
<4.52 |
>96 |
>75 |
Notes:
(1) Values Bold indicate Action Level exceedance.
(2) Values Underlined and Bold indicate Limit Level exceedance.
On 15
May 2013, a complaint was lodged with the Environmental Protection Department
(EPD) on ecological and dust impact near
No notifications of summons or successful prosecution were received the reporting month.
Non-compliance
Investigations have been carried out to
identify the causes of water quality exceedance.
From investigation, construction activities
during the period of exceedance included mainly site formation and foundation
work, as well as pond
drainage management in the Wetland Restoration Area (to lower the water level
and remove unwanted species in the pond). It was observed that the Contractor
has implemented water quality mitigation measures as recommended in the EIA
report, including the provision of temporary drainage facility and associated
treatment facility. Sand bags are in place in the temporary drainage channel to
enhance the desilting efficiency. The Contractor further enhanced the water
quality mitigation measures by erecting several segments of rock bunds at the
discharge outlet to avoid site runoff draining directly to the northern
ditches.
With external factors
affecting the adjacent environments, such as natural variations, pond fish
culture activities, rainfall and suspected routine dredging works (unrelated to
the Project), the exceedances were considered not due to Project construction
works.
Complaint
From ET’s
investigation of the complaint, the major site activity conducted during April
and May 2013 were consolidation of site formation. Potential dust sources from
the site include dust from haul road and stockpiles, backfilling, consolidation
of site formation and movement of machineries. Potential ecological impact
sources from the site include consolidation of site formation and movement of
machineries.
Based on the site
daily record provided by Contractor, the Contractor implemented the following
air quality and ecological mitigation measures as recommended in EM&A
Manual which include:
¡
Maintain
and operate the automatic sprinkler system to ensure water spraying within the
site boundary for dust suppression;
¡
Water
spraying within the site boundary for dust suppression where the automatic
sprinkler system cannot cover;
¡
Covering
of dusty stockpiles;
¡
Compaction
of fill materials by rollers;
¡
Every
vehicle was washed to remove any dusty materials from its body and wheels
before leaving the construction site;
¡
Clear
Definition of Project Area Limit with a well-established fence;
¡
Maintenance
of wastewater treatment facilities to avoid water quality impact to nearby
sensitive receivers.
Other potential dust
sources that can be identified nearby include:
¡
Construction
site for Express Rail Link
¡
Construction
of village houses
¡
Traffic
from
Weekly site audits
were conducted since the start of the EM&A programme. During the 28 May
2013 site audit, regular water spraying of the haul road near the site boundary
with
Dust monitoring
was conducted since commencement of construction of the Project. No exceedance
of action and limit levels for 24-hour Total Suspended Particulates (TSP) was
recorded from April to 16 May 2013. The maximum 24-hour TSP levels recorded at
the four air quality monitoring stations AM1, AM2, AM3 and AM4 during this period
were 98 mg/m3, 96 mg/m3, 96 mg/m3 and 102 mg/m3 respectively, which were well below the action levels of
226 mg/m3,
213mg/m3,
205 mg/m3
and 237 mg/m3 respectively.
In addition, no
exceedance of action and limit levels for 1-hour TSP was recorded from April to
24 May 2013. The maximum 1-hour TSP levels recorded at the four air quality
monitoring stations AM1, AM2, AM3 and AM4 during this period were 122 mg/m3, 122 mg/m3, 126 mg/m3 and 134 mg/m3 respectively, which were
well below the action levels of 378 mg/m3, 357 mg/m3, 358 mg/m3 and 372 mg/m3 respectively.
On the other hand,
the prevailing wind direction in April and May 2013 was mostly northeast and
easterly from the information obtained from the Hong Kong Observatory.
Also, it is observed that the photos provided
by the complainant are not the most up-to-date, as the Contractor has
implemented additional dust control measures since January 2013, such as
automatic sprinkler system and additional paving of haul roads, to enhance the
dust control measures and reduce the dust source.
In accordance to the
proposed ecological mitigation measures in the EIA report (AEIAR-120/2008), a
Wetland Restoration Area (WRA) was established to the North of the Project Area
and the established period concluded in October 2012.
Regular surveys for
the Ecological Monitoring are conducted in accordance to the approved EM&A
manual. During the surveys, an increase
in diversity and numbers of different types of fauna has been observed within
the survey area and WRA. Based on the
survey results, no apparent adverse impact to the ecological surroundings has
been observed.
There was no
deterioration of air quality and adverse impact to the ecological environment
observed during regular site audit carried out by the Environmental Team on 28
May 2013.
Non-compliance
As non-compliances have been recorded, the
Event and Action Plan has been followed. Although it is considered that the
exceedances were not related to the Project, the Contractor was reminded to implement
the water quality mitigation measures in accordance with the recommendation
stated in Section 5.6.1 – 5.6.4 of the EIA Report as far as practicable and
regular spot check would be conducted on the nearby discharge by Contractor and
inform ET for investigation.
To cater for the site runoff in wet season, the
Contractor has further enhanced the water quality mitigation measures by
erecting several segments of rock bunds at the discharge outlet to avoid site
runoff draining directly to the northern ditches.
Complaint
Air quality and ecological mitigation measures
as recommended in the Implementation Schedule of the EM&A Manual have been
implemented by Contractor to minimise the air quality nuisance arising from the
site activities. No immediate actions
are required, but the Contractor is reminded to ensure all proposed mitigation
measures recommended in the Implementation Schedule of the EM&A Manual are
implemented to reduce any possible environmental impacts.
Cumulative statistics for complaints, notifications of summons and
successful prosecutions for the Project account for period starting from the
date of commencement of construction (i.e. 12 May 2010) to the end of the
reporting month and are summarized in the Table
7.2 below.
Table 7.2: Statistics for Complaints, Notifications of Summons and Successful Prosecutions
|
Reporting Period |
Cumulative Statistics |
||
|
|
Complaints |
Notifications of summons |
Successful prosecutions |
|
This reporting month (May 2013) |
1 |
0 |
0 |
|
From 12 May 2010 to end of the reporting
month (May 2013) |
5 |
0 |
0 |
The major site works scheduled to be commissioned in the coming month include:
¡
Site Formation
¡
Foundation Work
¡
Superstructure
¡
Pond drainage management in the Wetland Restoration Area (to
lower the water level and remove unwanted species in the pond)
Key issues to be considered in the coming month include:
¡
Generation of dust from activities on-site during dry weather
conditions;
¡
Noise impact from operating equipment and machinery on-site;
¡
Generation and treatment of site surface runoffs and wastewater from
activities on-site and during wet weather conditions;
¡
Sorting, recycling, storage and disposal of general refuse and
construction waste from activities on-site; and
¡
Management of chemicals and avoidance of oil spillage on-site and to the
drainage.
The environmental site inspection and environmental monitoring will be continued in the coming month. Impact monitoring for air, noise, water quality, ecology and landscape and visual in accordance with the approved EM&A Manual has commenced since 12 May 2010. The tentative monitoring schedule for June 2013 is shown in the Table 8.1.
Table 8.1: Tentative
Environmental Monitoring and Audit Schedule for June 2013

The EM&A programme as recommended in the EM&A manual has been undertaken in the reporting month since 12 May 2010.
Monitoring of Air Quality, Noise, Water Quality, Ecology and Landscape and Visual impacts due to the Project was under way. In particular, the 1-hr TSP, 24-hr TSP, noise level (as Leq) and water quality parameters (such as pH, DO and SS) under monitoring have been checked against established Action and Limit levels.
There was no breach of Action and Limit
Levels for 1-hr TSP, 24-hr TSP and
noise in the reporting month.
During May 2013, Action/Limit Level
exceedances of pH, DO, turbidity and/or SS were observed at MP3 to MP6. Investigations have been carried out to
identify the causes of exceedance. From investigation, the Contractor has
implemented water quality mitigation measures as recommended in the EIA report.
With
external factors affecting the adjacent environments, such as natural
variations, pond fish culture activities, rainfall and suspected routine
dredging works (unrelated to the Project), the exceedances were considered not
due to construction works.
On 15 May 2013, a
complaint was lodged with the Environmental Protection Department (EPD) on ecological and dust impact near
With
considerations on the construction activities and environment, the following
recommendations were provided:
Air
Quality
·
Access roads should be sprayed with water or dust
suppression chemical to maintain the entire road surface wet or paved; and
·
All
vehicles should be washed to remove any dusty materials before leaving the
construction sites.
Water Quality
·
Soil contaminated with chemicals/oils should be
removed from site, and the voids created should be filled with suitable
materials.
·
Ensure
proper functioning of the wastewater treatment facility; and
·
Silt and debris should be removed from the temporary
drainage channel regularly.
Waste Management
·
Reuse the excavated materials as far as practical to
reduce the amount of waste disposal; and
·
Oil
stains on soil should be cleared by disposal of contaminated soil.


Contact
information:
|
Company |
Position |
Name |
Telephone |
|
Heng Shung Construction Co. Ltd. |
Assistant Construction
Manager |
Ms. Lynne HUNG |
2908 2391 |
|
(The Contractor) |
Site Agent |
Mr. POON Man Ho |
9426 3533 |
|
|
Environmental
Officer |
Mr. Ricky WONG |
9866 7625 |
|
ENVIRON Hong
Kong Ltd. (Independent
Environmental Checker (IEC)) |
Independent
Environmental Checker |
Mr. David YEUNG |
3465 2888 |
|
Mott MacDonald Hong Kong Ltd. (Environmental Team
(ET)) |
Environmental
Team Leader |
Mr. Terence
KONG |
2828 5919 |
Appendix C.
Action and Limit Levels for
Construction Phase
|
Air Quality
Action and Limit Levels for 24-hour TSP
|
Monitoring Station |
Action Level (mg/m3) |
Limit Level (mg/m3) |
|
ASR1 |
226 |
260 |
|
ASR2A |
213 |
260 |
|
ASR3 |
205 |
260 |
|
ASR4 |
237 |
260 |
Action and Limit Levels for 1-hour TSP
|
Monitoring Station |
Action Level (mg/m3) |
Limit Level (mg/m3) |
|
ASR1 |
378 |
500 |
|
ASR2A |
357 |
500 |
|
ASR3 |
358 |
500 |
|
ASR4 |
372 |
500 |
Noise
Action and Limit Levels for
Construction Noise
|
Time Period |
Action Level |
Limit Level |
|
NSR1, NSR3, NSR5, NSR7 |
||
|
0700 – 1900 hours
on normal weekdays |
When one
documented complaint is received from any one of the sensitive receivers |
75 dB(A) |
Water Quality
Action and Limit
Levels for Water Quality
|
Parameters |
DO in mg/L |
Turbidity in NTU |
SS in mg/L |
pH |
||||
|
|
Action Level |
Limit Level |
Action Level |
Limit Level |
Action Level |
Limit Level |
Action Level |
Limit Level |
|
MP1 |
1.23 |
1.17 |
173 |
177 |
231 |
299 |
< 5.5 or > 7.5 |
< 4.0 or > 8.0 |
|
MP2 |
1.04 |
0.89 |
132 |
163 |
170 |
209 |
||
|
MP3 |
6.85 |
6.65 |
64 |
67 |
65 |
66 |
||
|
MP4 |
3.91 |
3.82 |
60 |
64 |
50 |
53 |
||
|
MP5 |
4.13 |
3.87 |
81 |
84 |
66 |
69 |
||
|
MP6 |
4.61 |
4.52 |
94 |
96 |
75 |
75 |
||
Appendix D.
Event and
Action Plan for Air Quality, Noise, Water Quality, Ecology and Landscape
& Visual
|
Air Quality
|
Event |
Action |
|||
|
ET Leader |
IEC |
ER |
Contractor |
|
|
Action Level |
|
|
|
|
|
1.
Exceedance
for one sample |
1.
Identify source, investigate the causes
of exceedance and propose remedial measures. 2.
Inform IEC and ER. 3.
Repeat measurement to confirm finding. 4.
Increase monitoring frequency to daily. |
1.
Check monitoring data submitted by ET. 2.
Check Contractor’s working method. |
1.
Notify Contractor. |
1.
Rectify any unacceptable practice. 2.
Amend working methods if appropriate. |
|
2.
Exceedance
for two or more consecutive samples |
1.
Identify the source. 2.
Inform
IEC and ER. 3.
Advise
ER on the effectiveness of the proposed remedial measures 4.
Repeat measurements to confirm findings. 5.
Increase monitoring frequency to daily. 6.
Discuss with IEC and the Contractor on
remedial actions required. 7.
If exceedance continues, arrange meeting with
IEC and ER. 8.
If exceedance stops, cease additional
monitoring. |
1.
Check monitoring data submitted by ET. 2.
Check the Contractor’s working method. 3.
Discuss with ET Leader and the Contractor on
possible remedial measures. 4.
Advise ER on the effectiveness of the proposed
remedial measures. 5.
Supervise implementation of remedial measures. |
1.
Confirm receipt of notification of exceedance
in writing. 2.
Notify the Contractor. 3.
Ensure remedial measures properly implemented. |
1.
Submit proposals for remedial actions to IEC
within 3 working days of notification. 2.
Implement the agreed proposals. 3.
Amend proposal if appropriate. |
|
Limit Level |
|
|
|
|
|
1.
Exceedance
for one sample |
1.
Identify source, investigate the causes of
exceedance and propose remedial measures. 2.
Inform ER and EPD. 3.
Repeat measurement to confirm finding. 4.
Increase monitoring frequency to daily. 5.
Assess effectiveness of Contractor’s remedial
actions and keep IEC, EPD and ER informed of the results. |
1.
Check monitoring data submitted by ET. 2.
Check the Contractor’s working method. 3.
Discuss with ET Leader and the Contractor on
possible remedial measures. 4.
Advise ER on the effectiveness of the proposed
remedial measures. 5.
Supervise implementation of remedial measures. |
1.
Confirm receipt of notification of exceedance
in writing. 2.
Notify the Contractor. 3.
Ensure remedial measures properly implemented. |
1.
Take immediate action to avoid further
exceedance. 2.
Submit proposals for remedial actions to IEC
within 3 working days of notification. 3.
Implement the agreed proposals. 4.
Amend proposal if appropriate. |
|
2.
Exceedance
for two or more consecutive samples |
1.
Notify IEC, ER, EPD and the Contractor. 2.
Identify the source. 3.
Repeat measurements to confirm findings. 4.
Increase monitoring frequency to daily. 5.
Carry out analysis of the Contractor’s working
procedures to determine possible mitigation to be implemented. 6.
Arrange meeting IEC and ER to discuss the
remedial actions to be taken. 7.
Assess effectiveness of the Contractor’s
remedial actions and keep IEC, EPD and ER informed of the results. 8.
If exceedance stops, cease additional
monitoring. |
1.
Discuss amongst ER, ET Leader and the
Contractor on the potential remedial actions. 2.
Review the Contractor’s remedial actions
whenever necessary and advise ER accordingly. 3.
Supervise the implementation of remedial
measures. |
1.
Confirm receipt of notification of exceedance
in writing. 2.
Notify the Contractor. 3.
In consultation with IEC, agree with the
remedial measures to be implemented. 4.
Ensure remedial measures are properly
implemented. 5.
If exceedance continues, consider what
activity of the work is responsible and instruct the Contractor to stop that
activity of work until the exceedance is abated. |
1.
Take immediate action to avoid further
exceedance. 2.
Submit proposals for remedial actions to IEC
within 3 working days of notification. 3.
Implement the agreed proposals. 4.
Resubmit proposals if problem still not under
control. 5.
Stop the relevant activity of works as
determined by ER until the exceedance is abated. |
Construction Noise
|
Event |
Action |
|||
|
ET
Leader |
IEC |
ER |
Contractor |
|
|
Action
Level |
1. Notify
IEC and the Contractor. 2. Carry
out investigation. 3. Report
the results of investigation to IEC and the Contractor. 4. Discuss
with the Contractor and formulate remedial measures. 5. Increase
monitoring frequency to check mitigation measures. |
1. Review
with analysed results submitted by ET. 2. Review
the proposed remedial measures by the Contractor and advise ER accordingly. 3. Supervise
the implement of remedial measures. |
1. Confirm
receipt of notification of exceedance in writing. 2. Notify
the Contractor. 3. Require
the Contractor to propose remedial measures for the analysed noise problem. 4. Ensure
remedial measures are properly implemented. |
1. Submit
noise mitigation proposals to IEC. 2. Implement
noise mitigation proposals. |
|
Limit
Level |
1. Identify
the source. 2. Notify
IEC, ER, EPD and the Contractor. 3. Repeat
measurement to confirm findings. 4. Increase
monitoring frequency. 5. Carry
out analysis of Contractor’s working procedures to determine possible
mitigation to be implemented. 6. Inform
IEC, ER, and EPD the causes & actions taken for the exceedances. 7. Assess
effectiveness of the Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results. 8. If
exceedance stops, cease additional monitoring. |
1. Discuss
amongst ER, ET Leader and the Contractor on the potential remedial actions. 2. Review
the Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise ER accordingly. 3. Supervise
the implementation of remedial measures. |
1. Confirm
receipt of notification of exceedance in writing. 2. Notify
the Contractor. 3. Require
the Contractor to propose remedial measures for the analysed noise problem. 4. Ensure
remedial measures are properly implemented. 5. If
exceedance continues, consider what activity of the work is responsible and
instruct the Contractor to stop that activity of work until the exceedance is
abated. |
1. Take
immediate action to avoid further exceedance. 2. Submit
proposals for remedial actions to IEC within 3 working days of notification. 3. Implement
the agreed proposals. 4. Resubmit
proposals if problem still not under control. 5. Stop
the relevant activity of works as determined by the ER until the exceedance
is abated. |
Water Quality
|
Event |
Action |
|||
|
ET Leader |
IEC |
ER |
Contractor |
|
|
Action Level |
|
|
|
|
|
1. Exceedance for one sample |
1. Repeat in-situ measurement to confirm
finding; 2. Identify source(s) of impact; 3. Inform IEC and Contractor; 4. Check monitoring data, all plant, equipment
and Contractor’s working methods; 5. Discuss mitigation measures with IEC and
Contractor; and 6. Repeat measurement on next day of
exceedance. |
1. Discuss with ET and Contractor on the mitigation
measures; 2. Review proposals on mitigation measures
submitted by Contractor and advise the ER accordingly; and 3. Assess the effectiveness of the implemented
mitigation measures. |
1. Discuss with IEC on the proposed mitigation
measures; and 2. Make agreement on the mitigation measures
to be implemented. |
1. Inform the ER and confirm notification of
the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Consider changes of working methods; 5. Discuss with ET and IEC and propose
mitigation measures to IEC and ER; and 6. Implement the agreed mitigation measures. |
|
2.
Exceedance
for two or more consecutive samples |
1. Repeat in-situ measurement to confirm
finding; 2. Identify source(s) of impact; 3. Inform IEC and Contractor; 4. Check monitoring data, all plant, equipment
and Contractor’s working methods; 5. Discuss mitigation measures with IEC and
Contractor; 6. Ensure mitigation measures are implemented; 7. Prepare to increase the monitoring
frequency to daily; and 8. Repeat measurement on next day of
exceedance. |
1. Discuss with ET and Contractor on the
mitigation measures; 2. Review proposals on mitigation measures
submitted by Contractor and advise the ER accordingly; and 3. Assess the effectiveness of the implemented
mitigation measures. |
1. Discuss with IEC on the proposed mitigation
measures; 2. Make agreement on the mitigation measures
to be implemented; and 3. Assess the effectiveness of the implemented
mitigation measures. |
1. Inform the Engineer and confirm
notification of the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Consider changes of working methods; 5. Discuss with ET and IEC and propose
mitigation measures to IEC and ER within 3 working days; and 6. Implement the agreed mitigation measures. |
|
Limit Level |
|
|
|
|
|
1.
Exceedance
for one sample |
1. Repeat in-situ measurement to confirm
finding; 2. Identify source(s) of impact; 3. Inform IEC, Contractor and EPD; 4. Check monitoring data, all plant, equipment
and Contractor’s working methods; 5. Discuss mitigation measures with IEC, ER
and Contractor; 6. Ensure mitigation measures are implemented;
and 7. Increase the monitoring frequency to daily
until no exceedance of Limit level. |
1. Discuss with ET and Contractor on the
mitigation measures; 2. Review proposals on mitigation measures
submitted by Contractor and advise the ER accordingly; and 3. Assess the effectiveness of the implemented
mitigation measures. |
1. Discuss with IEC, ET and Contractor on the
proposed mitigation measures; and 2. Request Contractor to critically review the
working methods; 3. Make agreement on the mitigation measures
to be implemented; and 4. Assess the effectiveness of the implemented
mitigation measures. |
1. Inform the Engineer and confirm
notification of the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Consider changes of working methods; 5. Discuss with ET and IEC and ER and propose
mitigation measures to IEC and ER within 3 working days; and 6. Implement the agreed mitigation measures. |
|
2.
Exceedance
for two or more consecutive samples |
1. Repeat in-situ measurement to confirm
finding; 2. Identify source(s) of impact; 3. Inform IEC, Contractor and EPD; 4. Check monitoring data, all plant, equipment
and Contractor’s working methods; 5. Discuss mitigation measures with IEC, ER
and Contractor; 6. Ensure mitigation measures are implemented;
and 7. Increase the monitoring frequency to daily
until no exceedance of Limit level for two consecutive days. |
1. Discuss with ET and Contractor on the
mitigation measures; 2. Review proposals on mitigation measures
submitted by Contractor and advise the ER accordingly; and 3. Assess the effectiveness of the implemented
mitigation measures. |
1. Discuss with IEC, ET and Contractor on the
proposed mitigation measures; and 2. Request Contractor to critically review the
working methods; 3. Make agreement on the mitigation measures
to be implemented; 4. Assess the effectiveness of the implemented
mitigation measures; and 5. Consider and instruct, if necessary, the
Contractor to slow down or to stop all or part of the marine work until no
exceedance of Limit Level. |
1. Inform the ER and confirm notification of
the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Consider changes of working methods; 5. Discuss with ET and IEC and ER and propose
mitigation measures to IEC and ER within 3 working days; 6. Implement the agreed mitigation measures;
and 7. As directed by the Engineer, to slow down
or to stop all or part of the marine work or construction activities. |
Appendix E.
Calibration certificates
|
Appendix F.
Graphical plots of the
monitoring results
|
Appendix G.
Weather conditions
during the monitoring period
|
Appendix H.
Ecological Monitoring conducted
|
|
May 2013 |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
|
Mammals |
|
|
ü |
|
|
|
ü |
|
|
|
|
|
|
ü |
|
|
Birds |
|
|
ü |
|
|
|
ü |
|
|
|
|
|
|
ü |
|
|
Herpetofauna |
|
|
|
|
|
|
|
|
|
|
|
|
|
ü |
|
|
Dragonflies &
butterflies |
|
|
ü |
|
|
|
|
|
|
|
|
|
|
ü |
|
|
Water Quality |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Inspection Visits |
|
|
ü |
|
|
|
|
|
|
ü |
|
|
|
ü |
|
|
May 2013 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
|
Mammals |
|
|
|
|
|
ü |
|
|
|
|
|
|
ü |
|
|
|
|
Birds |
|
|
|
|
|
ü |
|
|
|
|
|
|
ü |
|
|
|
|
Herpetofauna |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Dragonflies &
butterflies |
|
|
|
|
|
|
|
|
|
|
|
|
ü |
|
|
|
|
Water Quality |
|
|
|
|
|
|
|
|
ü |
|
|
|
|
|
|
|
|
Inspection Visits |
|
|
|
|
|
|
|
|
ü |
|
|
|
|
|
|
ü |
Note: Light grey cells
indicate public holidays, Saturdays or Sundays.
.
Appendix I.
Summary of Bird
Surveys conducted
|
Table I1. Summary of bird species
of conservation importance and/or wetland-dependence recorded in the Survey
Area (excluding the WRA)
|
Species Name(5) |
Scientific Name(5) |
Conservation Status (2) |
May 2013 |
|
|
Occurrence(3) |
Mean(4) |
|||
|
Little Grebe |
Tachybaptus ruficollis |
LC, (1) |
5 |
5.8 |
|
Black-crowned Night Heron |
Nycticorax nycticorax |
(LC), (1) |
2 |
1.2 |
|
Chinese Pond Heron |
Ardeola bacchus |
PRC, (RC), (1) |
5 |
4.2 |
|
Little Egret |
Egretta garzetta |
PRC, (RC), (1) |
5 |
9.0 |
|
Intermediate Egret |
Egretta intermedia |
RC, (1) |
2 |
0.6 |
|
Great Egret |
Egretta alba |
PRC, (RC), (1) |
5 |
4.0 |
|
Tufted Duck |
Aythya fuligula |
LC, (1) |
2 |
0.4 |
|
Black Kite |
Milvus migrans |
RC |
1 |
0.2 |
|
Common Moorhen |
Gallinula chloropus |
(1) |
1 |
0.2 |
|
Green Sandpiper |
Tringa ochropus |
(1) |
2 |
0.6 |
|
Common Sandpiper |
Actitis hypoleucos |
(1) |
1 |
0.2 |
|
Whiskered Tern |
Chlidonias hybrida |
LC, (1) |
2 |
1.2 |
|
Common Kingfisher |
Alcedo atthis |
(1) |
3 |
0.8 |
|
Eastern Yellow Wagtail |
Motacilla tschutschensis |
(1) |
2 |
0.8 |
|
White Wagtail |
Motacilla alba |
(1) |
5 |
3.2 |
|
White-shouldered Starling |
Sturnus sinensis |
(LC), (1) |
1 |
0.6 |
|
No.
of Species Recorded |
16 |
|||
(1) Indicates wetland-dependant or wetland-associated species.
(2) Conservation status follows that of Fellowes et al. (2002) and BirdLife International listing (2011).
(3) Indicates number of surveys recorded within the reporting period.
(4) Refers to the mean number of individuals recorded in the reporting period (excluding the WRA)
(5) Follows HK bird list (dated 2013-2-25).
Table I2. Summary of bird species of conservation importance
and/or wetland-dependence recorded in the WRA
|
Species Name(5) |
Scientific Name(5) |
Conservation Status (2) |
May 2013 |
Records Outside Surveys |
|
|
Occurrence(3) |
Mean(4) |
||||
|
Little Grebe |
Tachybaptus ruficollis |
LC, (1) |
1 |
1.5 |
ü |
|
Yellow Bittern |
Ixobrychus sinensis |
LC, (1) |
2 |
1.0 |
ü |
|
Little Egret |
Egretta garzetta |
PRC, (RC), (1) |
2 |
0.6 |
|
|
Black Kite |
Milvus migrans |
RC |
1 |
0.2 |
|
|
White-breasted Waterhen |
Amaurornis phoenicurus |
(1) |
- |
- |
ü |
|
Common Sandpiper |
Actitis hypoleucos |
(1) |
1 |
0.2 |
|
|
Common Kingfisher |
Alcedo atthis |
(1) |
3 |
0.6 |
|
|
Eastern Yellow Wagtail |
Motacilla tschutschensis |
(1) |
1 |
0.2 |
|
|
White Wagtail |
Motacilla alba |
(1) |
2 |
1.0 |
|
|
No.
of Species Recorded |
9 |
||||
(1) Indicates wetland-dependant or
wetland-associated species.
(2) Conservation status follows that of Fellowes et al. (2002) and BirdLife International
listing (2011).
(3) Indicates number of surveys recorded within
the reporting period.
(4) Refers to the mean number of individuals
recorded in the reporting period at WRA.
(5) Follows HK bird list (dated 2013-02-25).
Table J1. Summary of herpetofauna monitoring in the Survey Area (excluding the
WRA)
|
Species Name |
Scientific Name |
Conservation Status(1) |
May 2013 |
|
|
Occurrence(2) |
Mean(3) |
|||
|
Amphibian |
No. of |
Species Recorded |
0 |
|
|
Gunther's Frog |
Rana guentheri |
- |
1 |
1 |
|
|
|
|
Occurrence(2) |
Mean(3) |
|
Reptile |
No. of |
Species Recorded |
0 |
|
|
(No recordsin May 2013) |
|
|
|
|
(1) Conservation status follows that of Fellowes et al. (2002), Chan et al. (2005) and Karsen et al. (1998).
(2) Indicates number of surveys recorded within the reporting period.
(3) Refers to the mean number of individuals
recorded in the reporting period (excluding the WRA).
Table J2. Summary of herpetofauna monitoring
in the WRA
|
Species Name |
Scientific Name |
Conservation Status(1) |
May 2013 |
||||
|
Occurrence(2) |
Mean(3) |
||||||
|
Amphibian |
No. of |
Species Recorded |
0 |
||||
|
(No records in May 2013) |
|
|
|
|
|||
|
|
|
|
Occurrence(2) |
Mean(3) |
|||
|
Reptiles |
No. of |
Species Recorded |
0 |
||||
|
(No records in May 2013) |
|
|
|
|
|||
(1) Conservation status follows that of Fellowes et al. (2002), Chan et al. (2005) and Karsen et al. (1998).
(2) Indicates number of surveys recorded within the reporting period.
(3) Refers to the mean number of individuals
recorded in the reporting period in the WRA.
Table J3. Summary of mammal monitoring in the Survey Area (excluding the WRA)
|
Species Name |
Scientific Name |
Conservation Status(1) |
May 2013 |
|
|
|
|
|
Occurrence(2) |
Mean(3) |
|
Mammal |
No. of |
Species
Recorded |
0 |
|
|
(No records in May 2013) |
|
|
|
|
(1) Conservation status follows that of Fellowes et al. (2002) and Shek (2006).
(2) Indicates number of surveys recorded within the reporting period.
(3) Refers to the mean number of individuals
recorded in the reporting period (excluding the WRA).
Table J4.
Summary of mammal monitoring in the WRA
|
Species
Name |
Scientific Name |
Conservation Status(1) |
May 2013 |
Records Outside Surveys |
|
|
|
|
|
Occurrence(2) |
Mean(3) |
|
|
Mammal |
No. of |
Species
Recorded |
0 |
|
|
|
(No records in May 2013) |
|
|
|
|
|
(1) Conservation status follows that of Fellowes et al. (2002) and Shek (2006).
(2) Indicates number of surveys recorded within the reporting period.
(3) Refers to the mean number of individuals
recorded in the reporting period in the WRA.
Table J5. Summary of odonate and butterfly
monitoring in the Survey Area (excluding WRA)
|
Common
Name |
Scientific Name |
Conservation Status(1) |
May 2013 |
|
|
Occurrence(2) |
Mean(3) |
|||
|
Odonate |
No.
of Species Recorded |
6 |
||
|
Common Bluetail |
Ischnura senegalensis |
- |
2 |
27.3 |
|
Common Flangetail |
Ictionogomphus pertinax |
- |
2 |
1.7 |
|
Variegated Flutterer |
Rhyothemis variegata arria |
- |
1 |
1.0 |
|
Saddlebag Glider |
Tramea virginia |
- |
2 |
1.0 |
|
Green Skimmer |
Orthetrum sabina sabina |
- |
1 |
0.3 |
|
Asian Amberwing |
Brachythemis contaminata |
- |
1 |
1.3 |
|
Butterfly |
No.
of Species Recorded |
6 |
||
|
Long-tailed Blue |
Lampides boeticus |
- |
1 |
0.3 |
|
Pale Grass Blue |
Pseudozizeeria maha serica |
- |
2 |
1.0 |
|
Indian Cabbage White |
Pieris canidia |
- |
2 |
1.0 |
|
Common Grass Yellow |
Eurema hecabe |
- |
2 |
1.3 |
|
Paris Peacock |
Papilio paris |
- |
0 |
0.0 |
|
Mottled Emigrant |
Catopsilia pyranthe |
- |
1 |
0.3 |
(1) Conservation status follows that of Fellowes et al. (2002), Lo & Hui (2004), Tam et al. (2011) and Young & Yiu (2002).
(2) Indicates number of surveys recorded within the reporting period.
(3) Refers to the mean number of individuals recorded in the survey (excluding the WRA).
Table J6. Summary of dragonfly and butterfly
monitoring in the WRA
|
Common Name |
Scientific Name |
Conservation Status(1) |
May 2013 |
|
|
Occurrence(2) |
Mean(3) |
|||
|
Odonate |
No. of Species Recorded |
14 |
||
|
Common Bluetail |
Ischnura senegalensis |
- |
3 |
201.3 |
|
Organge-tailed Sprite |
Ceriagrion auranticum ryukyuanum |
- |
1 |
0.3 |
|
Asian Pintail |
Acisoma panorpoides |
- |
1 |
0.3 |
|
Blue Percher |
Diplacodes trivialis |
- |
1 |
0.3 |
|
Evening Skimmer |
Tholymis tillarga |
- |
1 |
0.3 |
|
Lessor Emperor |
Anax parthenope julius |
- |
1 |
0.3 |
|
Common Flangetail |
Ictionogomphus pertinax |
- |
2 |
2.0 |
|
Variegated
Flutterer |
Rhyothemis variegata arria |
- |
2 |
32.0 |
|
Saddlebag Glider |
Tramea virginia |
- |
2 |
1.7 |
|
Wandering Glider |
Pantala flavescens |
- |
1 |
0.7 |
|
Blue Dasher |
Brachydiplax chalybea flavovittata |
- |
1 |
0.3 |
|
Pied
Percher |
Neurothemis tullia tullia |
- |
1 |
0.3 |
|
Green
Skimmer |
Orthetrum sabina sabina |
- |
1 |
1.7 |
|
Asian Amberwing |
Brachythemis contaminata |
- |
1 |
1.7 |
|
Butterfly |
No. of Species Recorded |
4 |
||
|
Pale Grass Blue |
Pseudozizeeria maha serica |
- |
1 |
0.7 |
|
Indian Cabbage White |
Pieris canidia |
- |
2 |
1.0 |
|
Common Grass Yellow |
Eurema hecabe |
- |
2 |
1.3 |
|
Paris Peacock |
Papilio paris |
- |
1 |
0.3 |
(1) Conservation status follows that of Fellowes et al. (2002), Lo & Hui (2004), Tam et al. (2011) and Young & Yiu (2002).
(2) Indicates number of surveys recorded within the reporting period.
(3) Refers to the mean number
of individuals recorded in the reporting period in the WRA.
Table K1. Water quality at WRA in May 2013
|
Cell No. |
Temp. (°C) |
pH |
Salinity (ppt) |
Turb (mg/L) |
DO (mg/L) |
Water Level (cm) |
|
1 |
29.1 |
8.00 |
0.85 |
11.2 |
6.2 |
220 |
|
2 |
29.0 |
8.11 |
1.04 |
9.7 |
5.5 |
180 |
|
3 |
29.0 |
7.99 |
0.87 |
6.2 |
4.9 |
220 |
|
4 |
28.7 |
8.21 |
0.89 |
18.7 |
5.5 |
220 |
Note: Values highlighted in bold indicate that
action level is reached; whereas values in bold and underline indicate that
limit level is reached.