|
Issue and revision record |
This document is
issued for the party which commissioned it and for specific purposes
connected with the above-captioned project only. It should not be relied
upon by any other party or used for any other purpose. |
We accept no
responsibility for the consequences of this document being relied upon by
any other party, or being used for any other purpose, or containing any error
or omission which is due to an error or omission in data supplied to us by
other parties. This document
contains confidential information and proprietary intellectual property. It
should not be shown to other parties without consent from us and from the
party which commissioned it.. |
|
Date |
Originator |
Checker |
Approver |
Description |
||
|
A |
12
December 2014 |
Edward
Leung / Brandon Wong |
Terence Kong |
Eric Ching |
Issue
to Client |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contents |
Chapter Title Page
Tables
List of Figures
Figure 1.1 General
Layout Plan of the Project Site
Figure 2.1 Locations
of Air Quality Monitoring Stations
Figure 2.2 Locations
of Noise Monitoring Stations
Figure 2.3 Locations
of Water Quality Monitoring Stations
Figure 4.1 Survey
Area and Transect Walked
List of Appendices
Appendix A Project Organization Chart
Appendix B Tentative Construction Programme
Appendix C Action and Limit Levels for
Construction Phase
Appendix D Event and Action Plan for Air
Quality, Noise and Water Quality
Appendix E Calibration Certificates
Appendix F Graphical Plots of the Monitoring
Results
Appendix G Weather Conditions during the
Monitoring Period
Appendix H Ecological Monitoring Conducted
Appendix I Summary of Bird Surveys Conducted
Appendix J Summary of Herpetofauna,
Mammal and Insect Surveys Conducted
Appendix L Environmental Mitigation Measures - Implementation Status
Appendix M Landscape
and Visual Audit Photos
Mott
MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by Heng
Shung Construction Co. Ltd. to undertake the
Environmental Team (ET) services to carry out environmental monitoring and
audit (EM&A) for both pre-construction and construction phases of the
Proposed Comprehensive Development at Wo Shang Wai,
Yuen Long.
This
is the 55th EM&A report submitted under the Condition 4.5 of
Environmental Permit No. EP-311/2008/D. This report
summarises the findings on EM&A during the period from 1 to 30 November 2014.
Exceedance of Action and Limit Levels
There
was no breach of Action or Limit levels for Air Quality (1-hr TSP and 24-hr
TSP) and Noise level (as Leq) in the
reporting month.
During November 2014, one exceedance
of DO was observed at MP3. No exceedance was observed at MP4, MP5 and MP6.
The
summary of measured water quality is presented in Section 3.2.3.
Investigations have been carried out
to identify the causes of exceedance. From
investigation, the Contractor has implemented water quality mitigation measures
as recommended in the EIA report. With external factors affecting the adjacent
environments, such as natural variations, pond fish culture activities and
rainfall, the exceedances were considered not due to
the project construction works.
Implementation of Mitigation Measures
Site
audits were carried out on 4, 11, 18 and 26 November 2014 to
confirm the implementation measures undertaken by the Contractor in the
reporting month. The outcomes are presented in Section 6 and the status of implementation of mitigation measures
in the site is shown in Appendix L.
Record of
Complaints
There was no new record of complaints received in the reporting
month.
Record of Notification of Summons and
Successful Prosecution
There was no record of Notification of
summons and successful prosecution in the reporting month.
Reporting Changes
There was no reporting change in the
reporting month.
Future Key Issues
The major site
works scheduled to be commissioned in the coming three months include site
formation, foundation work and pond drainage management in the Wetland
Restoration Area (to lower the water level and remove unwanted species in the
pond). Potential environmental impacts due to the construction activities,
including air quality, noise, water quality, ecology and landscape and visual,
will be monitored.
Environmental mitigation measures will be
implemented on site as recommended and weekly site audits will be carried out
to ensure that the environmental conditions are acceptable.
In March 2005, the Project Proponent, Profit Point Enterprises Limited, acquired the development site at Wo Shang Wai in Yuen Long. An Environmental Impact Assessment (EIA) was then carried out and approved under the EIA Ordinance (EIAO), and the Environmental Permit (EP-311/2008) for construction of the comprehensive development in Wo Shang Wai was first granted by EPD on 9 September 2008 and has been subsequently varied, with the current version (EP-311/2008/D) issued by EPD on 20 March 2013.
The
Project involves the residential development and associated
infrastructure and wetland restoration area and linear
landscape area. The construction works under the Environmental Permit commenced
on 12 May 2010. The site formation construction works of the Wetland Restoration Area (hereafter WRA) were completed on 15
November 2010, while the 30-month establishment period of the WRA was concluded
in August 2012 – this indicated that planting works as scheduled in the
approved Wetland Restoration and Creation Scheme (WRCS; Nov 2009) was complete,
except along the western and southern boundary where the planting is affected
by the existing site boundary and noise barrier, and for which a Variation to
Environmental Permit (EP-311/2008/C) to defer planting at the location was
approved. The current valid EP (EP-311/2008/D) includes specific mitigation
measures to minimise certain identified noise impacts during the operation
phase.
Mott MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by the Contractor, Heng Shung Construction Co. Ltd., to undertake the Environmental Team (ET) services to carry out environmental monitoring and audit (EM&A) for both pre-construction and construction phases of the Proposed Comprehensive Development at Wo Shang Wai, Yuen Long.
According to the EP Condition 4.5, the monthly EM&A Report shall be submitted to the Director within two weeks after the end of the reporting month. This report summarises the findings during the period from 1 to 30 November 2014.
The organisation chart
and lines of communication with respect to the on-site environmental management
structure together with the contact information of the key personnel are shown
in Appendix A.
During the
reporting month, construction works of the Project undertaken include:
¡ Site formation
¡ Foundation work
¡ Pond drainage management in the Wetland
Restoration Area (to lower the water level and remove unwanted species in the
pond)
The Construction
Works Programme of the Project is provided in Appendix B. The general layout plan
of the Project site is shown in Figure 1.1.
The EM&A programme requires environmental monitoring of air quality, noise, water quality, ecology and landscape and visual as specified in the approved EM&A Manual.
A summary of impact EM&A requirements is presented in Table 1.1 below:
Table 1.1: Summary of Impact EM&A Requirements
|
Parameters |
Descriptions |
Locations |
Frequencies |
|
Air
Quality |
24-Hour TSP |
ASR1, ASR2A, ASR3, ASR4 |
Once every 6 days |
|
1-Hour TSP |
ASR1, ASR2A, ASR3, ASR4 |
3 times every 6 days |
|
|
Noise |
Leq,
30min |
NSR1, NSR3, NSR5, NSR7 |
Weekly |
|
Water Quality |
Dissolved Oxygen (DO), temperature, pH, suspended solids (SS) and Biological Oxygen Demand (BOD) |
MP1 to MP6 |
3 days per week |
|
Ecology |
Birds |
Within the Project Area and Assessment Area of 500m |
Weekly |
|
Dragonflies and Butterflies |
Within the Project Area and Assessment Area of 500m |
Once per month during Mar and Sep to November, and twice per month during Apr to Aug |
|
|
Herpetofauna |
Within the Project Area and Assessment Area of 500m |
Once per month during Apr to Nov |
|
|
Water quality of Wetland Restoration Area (WRA) |
WRA |
After filling of WRA with water, monthly for in situ water quality and every size months (end of wet season and end of dry season) for laboratory testing |
|
|
Site Inspections |
Within the Project Area and Assessment Area of 500m |
Weekly |
|
|
Landscape and Visual |
Auditing of
protection of existing trees, the transplanting of existing trees, the
creation of new wetland, the planting of new trees and shrubs and other
landscape and visual mitigation measures |
CM1 to CM10 and OM1 to OM7 within the
Project Area |
Site
inspections once every two weeks during construction phase; once every two
months during operational phase |
The Environmental Quality Performance Limits for air quality, noise and water quality are shown in Appendix C.
The Event and Action Plan for air quality, noise and water quality are shown in Appendix D.
The monitoring schedule
for the reporting month is shown in Table
1.2 below
Table 1.2: Environmental
Monitoring and Audit Schedule for November 2014
For air quality,
construction noise and water quality, ecology,
landscape and visual monitoring methodology, including the monitoring
locations, monitoring equipment used, monitoring parameters, and frequency and
duration, etc, are detailed in this Chapter.
In accordance with the EM&A Manual, 1-hour and 24-hour TSP levels monitoring are to be conducted during the construction phase. Table 2.1 summarizes the monitoring parameters, frequency and duration of air quality monitoring.
Table 2.1: Air Quality Monitoring Parameters, Frequency and Duration
|
Parameter |
Frequency and Duration |
|
|
ASR1, ASR2A, ASR3 & ASR4 |
24-hour TSP |
At least once in every six-days |
|
1-hour TSP |
3 times every six-days |
The
four air quality monitoring stations were established in the EM&A manual
and were slightly adjusted during the baseline monitoring phase. Locations of the
agreed air quality monitoring stations are listed in Table 2.2 and as shown in Figure 2.1.
Table 2.2: Air Monitoring Stations
|
Monitoring Stations |
Locations |
|
ASR1 |
Works Site Boundary |
|
ASR2A |
At the rooftop of refuse collection point,
which is located at the southwest of the project area |
|
ASR3 |
At the commercial centre at Palm Springs, which
is located at the south of the project area |
|
ASR4 |
Works Site Boundary |
Continuous
24-hour TSP air quality monitoring is conducted using High Volume Sampler (HVS) (Model: GMWS-2310 Accu-vol). The HVS meets all the requirements of the
EM&A Manual. Portable direct reading dust meters were used to carry out the
1-hour TSP monitoring. Table 2.3
summarizes the equipment used in the impact air quality monitoring.
Table 2.3: TSP Monitoring Equipment
|
Equipment |
Model |
|
24-hr TSP monitoring |
|
|
High Volume Sampler |
GMWS 2310 Accu-vol |
|
Calibrator |
GMW 25 |
|
1-hr TSP monitoring |
|
|
Portable direct reading dust meter |
AM510 SidePak
Personal Aerosol Monitor Dust Trak 8520 |
Installation
The HVS was installed in the vicinity of the air sensitive receiver. The following criteria were considered in the installation of the HVS.
Preparation of Filter Papers
· Glass fibre filters, were labelled and sufficient filters that were clean and without pinholes were selected.
· All filters were equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature was around 25 °C and not variable by more than ±3 °C with relative humidity (RH) < 50 % and was not variable by more than ±5 %. A convenient working RH was 40 %.
Field Monitoring
· The power supply was checked to ensure the HVS works properly.
· The filter holder and the area surrounding the filter were cleaned.
· The filter holder was removed by loosening the four bolts and a new filter, with stamped number upward, on a supporting screen was aligned carefully.
· The filter was properly aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.
· The swing bolts were fastened to hold the filter holder down to the frame. The pressure applied should be sufficient to avoid air leakage at the edges.
· The shelter lid was closed and was secured with the aluminium strip.
· The HVS was warmed-up for about 5 minutes to establish run-temperature conditions.
· A new flow rate record sheet was set into the flow recorder.
· The flow rate of the HVS was checked and adjusted at around 1.1 m3/min. The range specified in the EM&A Manual was between 0.6-1.7 m3/min.
· The programmable timer was set for a sampling period of 24 hrs + 1 hr, and the starting time, weather condition and the filter number were recorded.
· The initial elapsed time was recorded.
· At the end of sampling, the sampled filter was removed carefully and folded in half length so that only surfaces with collected particulate matter were in contact.
· It was then placed in a clean plastic envelope and sealed.
· All monitoring information was recorded on a standard data sheet.
· Filters were sent to a HOKLAS accredited laboratory for analysis.
Maintenance and Calibration
· The HVS and its accessories are maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.
· HVSs were calibrated at two-month intervals.
· Calibration records for HVSs are shown in Appendix E.
Field Monitoring
The measuring procedures of the 1-hour dust meter are in accordance with the Manufacturer’s Instruction Manual as follows:
· Set POWER to “ON”, push BATTERY button, make sure that the meter’s indicator is in the range with a red line and allow the instrument to stand for about 3 minutes (Then, the air sampling inlet has been capped).
· Push the knob at MEASURE position.
· Push “O-ADJ” button. (Then meter’s indication is 0).
· Push the knob at SENSI ADJ position and set the meter’s indication to S value described on the Test Report using the trimmer for SENSI ADJ.
· Pull out the knob and return it to MEASURE position.
· Push “START” button.
Maintenance and Calibration
· The 1-hour dust meter would be checked at 3-month intervals and calibrated at 1-year intervals throughout all stages of the air quality monitoring.
· Calibration records for direct dust meters are shown in Appendix E.
Following the requirements in the EM&A Manual for noise, noise monitoring has to be carried out during the construction phase. Continuous noise monitoring for the A-weighted levels Leq, L10 and L90 is undertaken once per every week.
Table 2.4 summarizes the monitoring parameters, frequency and duration of air quality monitoring.
Table 2.4: Noise Monitoring Parameters, Frequency and Duration
|
Monitoring Stations |
Parameter |
Frequency and Duration |
|
NSR1, NSR3, NSR5,
NSR7 |
Leq, L90 & L10 |
Once every week |
The
four noise
quality monitoring stations were established in the EM&A manual and were
slightly adjusted during the baseline monitoring phase. Locations of the agreed
noise
quality monitoring stations are listed in Table
2.5 and as shown in Figure 2.2.
Table 2.5: Noise Monitoring Stations
|
Monitoring Stations |
Locations |
Type of measurement |
|
NSR1 |
Noise monitoring equipment was set up near
the boundary wall at Palm Springs. |
Free-field |
|
NSR3 |
The monitoring station was located next to
the guard house at Palm Springs. |
Facade |
|
NSR5 |
The monitoring station was located within the
work site boundary. |
Free-field |
|
NSR7 |
The monitoring station was located near the
boundary wall of the house of Mai Po San Tsuen. |
Free-field |
Integrating Sound Level Meter will be used for noise monitoring. It is a Type 1 sound level meter capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx). They comply with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1). Table 2.6 summarizes the noise monitoring equipment model being used.
Table 2.6: Noise Monitoring Equipment
|
Monitoring Stations |
Equipment Model |
|
|
Integrating Sound Level Meter |
Calibrator |
|
|
NSR1 |
Rion NL-52 |
Rion NC-73 |
|
NSR3 |
||
|
NSR5 |
||
|
NSR7 |
||
Field Monitoring
- frequency weighting: A
- time weighting: Fast
- time measurement: 30 minutes intervals (between 07:00 and 19:00)
Maintenance and Calibration
In accordance
with the requirements in the EM&A Manual for water quality, water quality parameters including Dissolved Oxygen
(DO), temperature, pH, turbidity, suspended solids (SS) and Biochemical Oxygen Demand
(BOD) have to be monitored at designated monitoring stations during
construction of the Project. DO, temperature and
pH were measured in-situ whereas SS and BOD were analysed
in a laboratory. The measurements should be taken at all designated monitoring stations, three days
per week. The interval between any two sets of monitoring was not less than 36
hours. Table 2.7 summarizes
the monitoring parameters, frequency and duration of water quality monitoring.
Table 2.7: Water Quality Monitoring Parameters, Frequency and Duration
|
Monitoring Stations |
Parameter |
Frequency and Duration |
|
MP1, MP2, MP3, MP4,
MP5 & MP6 |
DO, temperature, pH,
SS, turbidity, BOD |
Three days every
week |
The
six water quality monitoring stations were
established in the EM&A manual. Locations of the agreed water quality monitoring stations are listed in
Table 2.8 and as shown in Figure 2.3..
Table 2.8: Water Quality Monitoring Stations
|
Monitoring Stations |
Easting |
Northing |
|
MP1 |
838 730.50 |
822 862.25 |
|
MP2 |
838 933.26 |
823 247.41 |
|
MP3 |
839 107.17 |
823 596.84 |
|
MP4 |
839 286.14 |
823 638.55 |
|
MP5 |
839 134.35 |
823 722.99 |
|
MP6 |
839 063.02 |
823 842.25 |
The Water Quality Monitoring Equipment and Analytical Methods applied to Water Quality Samples are given in Table 2.9 and Table 2.10 respectively. Details of which are discussed below.
Table 2.9: Water Quality Monitoring Equipment
|
Equipment |
Model |
Equipment/Serial Number |
|
Conductivity,
Dissolved oxygen, pH, Salinity and Temperature Measuring Meter |
YSI
Professional Plus |
09K100735 |
|
Turbidity
Meter |
Hach 2100Q
IS/Hach 2100Q |
09120C000514 |
|
Global
Positioning System (GPS) |
Garmin eTrex
Vista |
ENO 007 |
Table 2.10: Analytical Methods applied to Water Quality Samples
|
Determinant, unit |
Standard Method |
|
Total
Suspended Solids, mg/L |
In house
method based on APHA 2540D; ALS Method Code: EA-025 |
|
Biochemical
Oxygen Demand (BOD), mg/L |
In house
method based on APHA 5210B; ALS Method Code: EP-030 |
All
in-situ monitoring instruments were checked, calibrated and certified by a
laboratory accredited
under HOKLAS or any other international accreditation scheme before use.
Dissolved Oxygen (DO), temperature and pH measuring equipment
A portable, weatherproof multiparameter instrument (YSI Professional Plus) was used in the monitoring. It can be capable for measuring dissolved oxygen (DO), pH, and temperature simultaneously with the following limits:
· a dissolved oxygen level in the range of 0-50 mg/L and 0-500 % saturation;
· a temperature of -5 to 45 degree Celsius; and
· pH value of 0-14 with 0.1 as the base unit.
Turbidity Measurement Instrument
Portable and weatherproof turbidity meter (HACH model 2100Q) was used during impact monitoring. It has a photoelectric sensor capable of measuring turbidity between 0-1000 NTU. Response of the sensor was checked with certified standard turbidity solutions before the start of measurement.
Global Positioning System
A
hand-held GPS navigator (Garmin eTrex Vista)
was used to identify the designated monitoring stations prior to water sampling.
Suspended Solids and BOD Measurements (Sample Containers and Storage)
Water samples for SS analysis were stored in
high density polythene bottles with no preservative added, packed in ice
(cooled to 4oC without being frozen), delivered to the laboratory,
and analysed as soon as possible after collection. Analysis was carried out in
a HOKLAS accredited laboratory.
The limits of detection for the in-situ and
laboratory measurements are shown in Table 2.11.
Table 2.11: Detection Limits for Water Quality Determinants
|
Determinant |
Limit of Detection |
|
Dissolved Oxygen |
0.1 mg/L |
|
Temperature |
0.1 degree Celsius |
|
pH |
0.01 unit |
|
Turbidity |
0.1 NTU |
|
Suspended Solids |
1 mg/L |
|
BOD |
2 mg/L |
In situ measurement
All pH meters, DO/temperature meters had been checked and calibrated prior to use. Standard buffer solution of at least two pH levels (either pH 4 and pH 7, or pH 7 and pH 10) had been used for calibration of the instrument before and after use.
DO meters had been calibrated by a laboratory accredited under HOKLAS or any other international accreditation scheme, and subsequently re-calibrated at three-monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes had been checked with certified standard solutions before each use. Wet bulb calibrations for all DO meters had been carried out before measurement at each monitoring location. For the on-site calibration of field equipment, BS 127:1993, "Guide to field and on-site test methods for the analysis of waters" had been observed.
Measurements shall be at three water depths, namely, 1m below water surface, mid-depth and 1m above stream bed/pond bed, except where the water depth less that 6m, the mid-depth station maybe omitted. Should the water depth be less than 3m, only the mid-depth station will be monitored.
Replicates in-situ measurements and samples collected from each independent monitoring event are required for all parameters to ensure a robust statistically interpretable dataset.
Water Samples Preparation and Analysis
For collection of water sampling within the water courses, a 500ml clean plastic beaker was used. After collection, the water samples were stored in high-density polythene bottles. The sample container was rinsed with a portion of the water sample. The water sample was then transferred to the container, labelled with a unique sample ID and sealed with a screw cap. The water samples were stored in a cool box maintained at 4oC. The water samples were then delivered to a local HOKLAS-accredited laboratory (ALS) on the same day for analysis.
The testing methods of testing parameters as recommended by EIA or required by EPD, with the QA/QC results are in accordance with the requirement of HOKLAS or international accredited scheme.
The calibration certificates
for equipment used for in-situ monitoring of water quality are attached in Appendix E.
Target species and certain other fauna will be monitored within the Project Area and Assessment Area during the wetland and residential construction phase. This will be important to ensure that any unexpected events or impacts either on- or off-site are quickly identified so that remedial action can be taken. The groups to be monitored and frequency of monitoring are shown in Table 2.12.
Table 2.12: Summary of Construction Phase Ecological Monitoring for the Wo Shang Wai Wetland Restoration Area (WRA)
|
Species / Parameter |
Construction Phase Ecological Monitoring |
|
Birds |
Weekly (including Assessment Area). |
|
Dragonflies and Butterflies |
Once per month during March and September
to November, and twice per month during April to August. |
|
Herpetofauna |
Once per month during April to November. |
|
Water Quality |
After filling of WRA with water, monthly
for in situ water quality and every
six months (end of the wet season and end of the dry season) for laboratory
testing. |
|
Site Inspections |
Weekly. |
Ecological
monitoring locations during
construction phase are shown in Figure 4.1 and the methodology for ecological monitoring
is detailed in Section 4.
All measures undertaken by both the Contractor and the specialist Landscape Sub-Contractor during the construction phase and first year of the operational phase shall be audited by a Registered Landscape Architect, as a member of the ET, on a regular basis to ensure compliance with the intended aims of the measures. Site inspections should be undertaken at least once every two weeks throughout the construction period and once every two months during the operational phase.
The broad scope
of audit is detailed below but should also be undertaken with reference to the
more specific checklist provided in Table
2.13 below. Operational phase auditing will be restricted to the last 12
months of the establishment works of the landscaping proposals and thus only
the items below concerning this period are relevant to the operational phase.
·
The extent of the agreed works area should be regularly
checked during the construction phase. Any trespass by the Contractor outside
the limit of the works, including any damage to existing trees and woodland
shall be noted;
·
The progress of the engineering works should be regularly
reviewed on site to identify the earliest practical opportunities for the
landscape works to be undertaken;
·
All existing vegetation, streams and other features within
the study area which are not directly affected by the works are retained and
protected;
·
The methods of protecting existing vegetation proposed by the
Contractor are acceptable and enforced;
·
Preparation, lifting transport and re-planting operations for
any transplanted trees;
·
The layout, design and construction of buildings conforms to
requirements specified in the EIA report;
·
All landscaping works are carried out in accordance with the
EIA recommendations and with specifications;
·
The planting of new trees, shrubs, groundcover, climbers,
grasses and other plans, together with the replanting of any transplanted trees
are carried out properly and within the right season;
·
All necessary horticultural operations and replacement
planting are undertaken throughout the Establishment Period to ensure the
healthy establishment and growth of both transplanted trees and all newly
establishment plants.
Table 2.13: Construction and Operation Phase Audit Checklist
|
Area of Works |
Items to be Monitored |
|
Works Area |
Check the extent of the
Works to ensure that the Works Area is not exceeded |
|
Protection of all trees and woodland blocks to be retained |
Identification and demarcation of trees / vegetation to be retained, erection
of physical protection (e.g. fencing), monitoring against possible incursion,
physical damage, fire, pollution, surface erosion, etc. |
|
Streams |
Ensure no run-off into existing streams |
|
Clearance of existing vegetation |
Identification and demarcation of trees / vegetation to be cleared,
checking of extent of works to minimize damage, monitoring of adjacent areas
against possible incursion, physical damage, fire, pollution, surface
erosion, etc. |
|
Transplanting of trees |
Identification and demarcation of trees / vegetation to be transplanted,
monitoring of extent of pruning / lifting works to minimize damage, timing of
operations implementation of all stages of preparatory and translocation
works, and maintenance of transplanted vegetation, etc. |
|
Topsoil stripping |
Ensuring existing topsoil is stripped and stored under recognized good
practice and is hydroseeded and regularly turned to prevent anaerobic
conditions |
|
New buildings |
Ensure that building finishes accord with mitigation proposals with
regard to colour and albedo. |
|
Boundaries |
Ensuring hoarding are erected as required |
|
Noise Barrier |
Ensure noise barrier design accords with the mitigation proposals with
regard to location, materials and finishes. |
|
Night-time lighting |
Ensuring night-time lighting is directional, hooded and shielded away
from VSRs |
|
Plant supply |
Monitoring of operations relating to the supply of specialist plant material
(including the collecting, germination and growth of plants from seed) to
ensure that plants will be available in time to be used within the
construction works. |
|
Landscape and wetland treatments generally |
Check that wetland, and hard / soft landscape designs conform to intent
of mitigation measures and agreed designs |
|
Soiling, planting, etc. |
Monitoring of implementation and maintenance of soiling and planting
works against possible incursion, physical damage, fire, pollution, surface
erosion, etc. |
|
Establishment Works |
Monitoring of implementation of maintenance operation during
Establishment Period |
The monitoring locations should check
against the mitigation measures proposed under the approved Environmental Impact
Assessment, which are summarised as follows in Table
2.14
and Table
2.15:
Table 2.14: Proposed Construction Phase Mitigation Measures
|
ID No. |
Landscape and Visual Mitigation Measure |
|
CM1 |
The construction
area and contractor’s temporary works areas should be minimised to avoid
impacts on adjacent landscape. |
|
CM2 |
Screening
of construction works by hoardings/noise barriers around Works area in
visually unobtrusive colours, to screen Works. |
|
CM3 |
Reduction
of construction period to practical minimum. |
|
CM4 |
Topsoil,
where identified, should be stripped and stored for re-use in the
construction of the soft landscape works, where the soil material meets
acceptable criteria and where practical.
The Contract Specification shall include storage and reuse of topsoil
as appropriate. |
|
CM5 |
Hydroseeding
or sheeting of soil stockpiles with visually unobtrusive material (in earth
tone). |
|
CM6 |
Advance
screen planting to noise barriers. |
|
CM7 |
Control
night-time lighting and glare by hooding all lights. |
|
CM8 |
Ensure
no run-off into streams adjacent to Project Area. |
|
CM9 |
Protection
of existing trees on boundary of project area shall be carefully protected during
construction. Detailed Tree Protection
Specification shall be provided in the Contract Specification. Under this
specification, the Contractor shall be required to submit, for approval, a
detailed working method statement for the protection of trees prior to
undertaking any works adjacent to all retained trees, including trees in
contractor’s works areas. (Tree
protection measures will be detailed at S16 and Tree Removal Application
stage). |
|
CM10 |
Trees
unavoidably affected by the works shall be transplanted where practical. Trees should be transplanted straight to
their destinations and not held in a nursery.
A detailed Tree Transplanting Specification shall be provided in the
Contract Specification, if applicable. Sufficient time for necessary tree
root and crown preparation periods shall be allowed in the project programme. |
Table 2.15: Proposed Operation Phase Mitigation Measures
|
ID No. |
Landscape Mitigation Measure |
|
OM1 |
Compensatory
Tree Planting for all felled trees shall be provided to the satisfaction of
relevant Government departments.
Required numbers and locations of compensatory trees shall be determined
and agreed separately with Government during the Tree Felling Application
process under ETWBTC 3/2006. |
|
OM2 |
A
continuous belt of screen planting along southern perimeter of project area
with fast growing tree species. At
least 450 trees capable of reaching a height > 10m within 10 years should
be planted. Planting of the belt of
trees shall be carried out as advance works ahead of other site formation and
building works. |
|
OM3 |
Maximise
soft landscape and amenity water bodies in residential areas of the
development. Approximately 750 trees
(of Heavy Standard size) should be planted.
Where space permits, roadside berms should be created. Street trees
should be of species that reach a mature height of no less than 15m. |
|
OM4 |
Maximise
freshwater habitat wetland creation consistent with achieving other
parameters. Minimum 4.74 ha to be
provided. Wetlands must have natural
edge profiles with >1m wide emergent zone.
No access to the wetland by residents and all wetlands must be
screened from residential development by a continuous tree screen at
interface with residential development or earth mounding such that
disturbance is minimised. Implementation of the wetland shall be carried out
as advance works. |
|
OM5 |
Use
appropriate (visually unobtrusive and non-reflective) building materials and
colours in built structures. |
|
OM6 |
During
detailed design, refine building layout to create a min. 10m wide gap between
buildings north of Wo Shang Wai pond and also two min. 10m wide gaps in the
row of buildings adjacent to Royal Palms. |
|
OM7 |
Streetscape
elements (e.g. paving, signage, street furniture, lighting etc.) shall be
sensitively designed in a manner that responds to the local context, and
minimises potential negative landscape and visual impacts. Lighting units should be directional and
minimise unnecessary light spill. |
Impact monitoring for air quality (dust), noise
and water quality due to the construction work were undertaken during the
reporting month in compliance with the EM&A manual in the reporting period.
Regular site inspections were carried out on 4, 11, 18 and 26 November 2014 in
the reporting month to assess the compliance with environmental requirements.
Results of 1-hour TSP at the four monitoring locations are summarised in Table 3.1. Graphical plots of the monitoring results are shown in Appendix F. The weather conditions in the reporting period are provided in Appendix G.
Table 3.1: Summary of 1-hour TSP Monitoring Results
|
Monitoring
Date |
Start
Time |
1-hr TSP (μg/m3) |
Range (μg/m3) |
Action Level (μg/m3) |
Limit Level (μg/m3) |
|||
|
1st Result |
2nd Result |
3rd Result |
||||||
|
ASR1 |
||||||||
|
04-Nov-14 |
12:42 |
128 |
130 |
125 |
72 – 130 |
378 |
500 |
|
|
10-Nov-14 |
12:41 |
82 |
79 |
89 |
||||
|
14-Nov-14 |
12:44 |
91 |
86 |
82 |
||||
|
20-Nov-14 |
12:48 |
72 |
77 |
76 |
||||
|
26-Nov-14 |
12:52 |
108 |
104 |
99 |
||||
|
ASR2A |
||||||||
|
04-Nov-14 |
08:43 |
106 |
111 |
113 |
62– 113 |
357 |
500 |
|
|
10-Nov-14 |
08:43 |
86 |
74 |
80 |
||||
|
14-Nov-14 |
08:40 |
62 |
69 |
74 |
||||
|
20-Nov-14 |
08:45 |
70 |
68 |
62 |
||||
|
26-Nov-14 |
08:39 |
86 |
89 |
79 |
||||
|
ASR3 |
||||||||
|
04-Nov-14 |
08:23 |
112 |
115 |
119 |
62 – 119 |
358 |
500 |
|
|
10-Nov-14 |
08:25 |
76 |
77 |
84 |
||||
|
14-Nov-14 |
08:20 |
73 |
65 |
62 |
||||
|
20-Nov-14 |
08:23 |
67 |
70 |
64 |
||||
|
26-Nov-14 |
08:19 |
89 |
75 |
73 |
||||
|
ASR4 |
||||||||
|
04-Nov-14 |
12:30 |
123 |
127 |
129 |
70 – 129 |
372 |
500 |
|
|
10-Nov-14 |
12:33 |
86 |
90 |
92 |
||||
|
14-Nov-14 |
12:30 |
85 |
87 |
89 |
||||
|
20-Nov-14 |
12:31 |
70 |
74 |
79 |
||||
|
26-Nov-14 |
12:38 |
97 |
105 |
100 |
||||
Results of 24-hour TSP at the four monitoring locations are summarised in Table 3.2. Graphical plots of the monitoring results are shown in Appendix F. The weather conditions in the reporting period are provided in Appendix G.
Table 3.2: Summary of 24-hour TSP Monitoring Results
|
Monitoring
Date |
Monitoring Results (μg/m3) |
Range (μg/m3) |
Action Level (μg/m3) |
Limit Level (μg/m3) |
|
ASR1 |
|
|
|
|
|
04-Nov-14 |
79 |
56-127 |
226 |
260 |
|
10-Nov-14 |
69 |
|||
|
14-Nov-14 |
127 |
|||
|
20-Nov-14 |
61 |
|||
|
26-Nov-14 |
56 |
|||
|
ASR2A |
|
|
|
|
|
04-Nov-14 |
64 |
64-80 |
213 |
260 |
|
10-Nov-14 |
78 |
|||
|
14-Nov-14 |
80 |
|||
|
20-Nov-14 |
71 |
|||
|
26-Nov-14 |
66 |
|||
|
ASR3 |
|
|
|
|
|
04-Nov-14 |
88 |
70-113 |
205 |
260 |
|
10-Nov-14 |
70 |
|||
|
14-Nov-14 |
113 |
|||
|
20-Nov-14 |
73 |
|||
|
26-Nov-14 |
88 |
|||
|
ASR4 |
|
|
|
|
|
04-Nov-14 |
90 |
80-93 |
237 |
260 |
|
10-Nov-14 |
81 |
|||
|
14-Nov-14 |
93 |
|||
|
20-Nov-14 |
90 |
|||
|
26-Nov-14 |
80 |
No exceedance of 1-hour and 24-hour TSP (Action or Limit Level) was recorded in the reporting period.
The construction noise monitoring results are summarized in Table 3.3. Graphical plots of the monitoring data are shown in Appendix F. The weather conditions in the reporting period are provided in Appendix G.
Table 3.3: Summary of Construction Noise Monitoring Results
|
Monitoring
Date |
Start Time |
Mean & Range of Noise Levels, dB(A) |
Limit Level for Leq
(dB) |
||
|
Leq |
L10 |
L90 |
|||
|
NSR1 |
|
|
|
|
> 75 |
|
04-Nov-14 |
09:00 |
54 |
56 |
44 |
|
|
10-Nov-14 |
09:01 |
52 |
55 |
48 |
|
|
20-Nov-14 |
09:02 |
54 |
58 |
45 |
|
|
26-Nov-14 |
08:47 |
54 |
58 |
45 |
|
|
NSR3 |
|
|
|
|
|
|
04-Nov-14 |
09:48 |
50 |
51 |
43 |
|
|
10-Nov-14 |
09:49 |
51 |
53 |
45 |
|
|
20-Nov-14 |
09:50 |
53 |
57 |
45 |
|
|
26-Nov-14 |
09:35 |
54 |
57 |
46 |
|
|
NSR5 |
|
|
|
|
|
|
04-Nov-14 |
13:09 |
50 |
53 |
44 |
|
|
10-Nov-14 |
13:08 |
49 |
53 |
45 |
|
|
20-Nov-14 |
13:14 |
50 |
53 |
43 |
|
|
26-Nov-14 |
13:19 |
49 |
53 |
44 |
|
|
NSR7 |
|
|
|
|
|
|
04-Nov-14 |
13:57 |
64 |
67 |
63 |
|
|
10-Nov-14 |
13:58 |
64 |
67 |
62 |
|
|
20-Nov-14 |
14:04 |
65 |
67 |
61 |
|
|
26-Nov-14 |
14:09 |
65 |
67 |
59 |
|
No exceedance (Action/Limit Level) of construction noise was recorded in the reporting period.
The water quality monitoring results are summarized in Table 3.4. Graphical plots of the monitoring data are shown in Appendix F. The weather conditions in the reporting period are provided in Appendix G.
Table 3.4: Summary of Water Quality Monitoring Results
|
Monitoring Date |
Temp (oC) |
pH |
Dissolved Oxygen (DO) (mg/L) |
DO (%) |
Turbidity
(NT) |
BOD
(mg/L) (1) |
Suspended
Solids (mg/L) |
|
MP3 |
|
|
|
|
|
|
|
|
03/11/2014 |
25.1 |
7.5 |
7.3 |
88.6 |
14.2 |
2 |
14.5 |
|
05/11/2014 |
25.0 |
7.5 |
7.3 |
88.4 |
12.5 |
2 |
15.5 |
|
07/11/2014 |
24.0 |
7.5 |
7.3 |
87.0 |
16.8 |
3 |
19.5 |
|
10/11/2014 |
24.5 |
7.5 |
7.2 |
85.8 |
25.0 |
2 |
19.5 |
|
12/11/2014 |
23.9 |
7.5 |
7.1 |
84.6 |
29.9 |
3 |
27.5 |
|
14/11/2014 |
22.9 |
7.5 |
7.4 |
85.7 |
8.6 |
<2 |
11 |
|
17/11/2014 |
23.3 |
7.5 |
7.3 |
85.6 |
30.0 |
10 |
22.5 |
|
19/11/2014 |
22.1 |
7.5 |
7.0 |
85.9 |
42.8 |
5 |
35 |
|
21/11/2014 |
21.9 |
7.5 |
6.5 |
79.1 |
25.7 |
8.5 |
27 |
|
24/11/2014 |
21.6 |
7.5 |
7.9 |
90.1 |
33.9 |
6.5 |
32.5 |
|
26/11/2014 |
21.8 |
7.5 |
7.6 |
86.6 |
58.0 |
4 |
56 |
|
28/11/2014 |
23.1 |
7.5 |
7.5 |
87.7 |
29.3 |
3.5 |
24 |
|
Action Level |
- |
<5.5 or >7.5 |
<6.85 |
- |
>64 |
- |
>65 |
|
Limit Level |
- |
<4.0 or >8.0 |
<6.65 |
- |
>67 |
- |
>66 |
|
|
|
|
|
|
|
|
|
|
MP4 |
|
|
|
|
|
|
|
|
03/11/2014 |
24.9 |
7.4 |
6.8 |
82.4 |
8.3 |
<2 |
11.5 |
|
05/11/2014 |
24.7 |
7.4 |
7.1 |
85.8 |
5.5 |
<2 |
<2 |
|
07/11/2014 |
24.4 |
7.4 |
7.4 |
90.3 |
9.7 |
<2 |
11.5 |
|
10/11/2014 |
24.1 |
7.4 |
7.0 |
83.3 |
22.2 |
3 |
16 |
|
12/11/2014 |
24.2 |
7.4 |
7.1 |
85.4 |
8.5 |
<2 |
7.5 |
|
14/11/2014 |
23.3 |
7.4 |
7.1 |
83.7 |
10.9 |
<2 |
7.5 |
|
17/11/2014 |
23.5 |
7.4 |
7.3 |
85.7 |
11.1 |
3.5 |
12.5 |
|
19/11/2014 |
22.5 |
7.4 |
6.7 |
84.5 |
16.5 |
3 |
17.5 |
|
21/11/2014 |
21.6 |
7.4 |
6.2 |
75.5 |
13.1 |
<2 |
13 |
|
24/11/2014 |
21.9 |
7.4 |
8.1 |
92.8 |
11.1 |
8 |
10.5 |
|
26/11/2014 |
22.1 |
7.4 |
8.0 |
91.5 |
4.8 |
4 |
<2 |
|
28/11/2014 |
22.9 |
7.4 |
7.3 |
84.7 |
7.8 |
<2 |
5 |
|
Action Level |
- |
<5.5 or >7.5 |
<3.91 |
- |
>60 |
- |
>50 |
|
Limit Level |
- |
<4.0 or >8.0 |
<3.82 |
- |
>64 |
- |
>53 |
|
|
|
|
|
|
|
|
|
|
MP5 |
|
|
|
|
|
|
|
|
03/11/2014 |
24.4 |
7.4 |
7.5 |
89.9 |
12.6 |
2.5 |
14.5 |
|
05/11/2014 |
24.4 |
7.4 |
7.3 |
88.2 |
9.6 |
<2 |
7.5 |
|
07/11/2014 |
24.2 |
7.4 |
7.0 |
83.7 |
14.5 |
2 |
19 |
|
10/11/2014 |
24.3 |
7.4 |
7.3 |
88.1 |
27.0 |
2 |
21.5 |
|
12/11/2014 |
24.4 |
7.4 |
7.5 |
90.5 |
23.5 |
2 |
22.5 |
|
14/11/2014 |
23.6 |
7.4 |
7.5 |
89.1 |
18.6 |
2.5 |
18 |
|
17/11/2014 |
22.9 |
7.4 |
7.5 |
87.7 |
22.8 |
6 |
17 |
|
19/11/2014 |
21.9 |
7.4 |
6.7 |
83.0 |
26.3 |
4 |
33 |
|
21/11/2014 |
22.5 |
7.4 |
6.3 |
78.5 |
19.6 |
6 |
22 |
|
24/11/2014 |
22.0 |
7.4 |
7.5 |
86.0 |
24.5 |
5.5 |
27 |
|
26/11/2014 |
22.2 |
7.4 |
7.4 |
85.5 |
40.6 |
4 |
50 |
|
28/11/2014 |
23.3 |
7.4 |
7.1 |
83.9 |
20.6 |
3 |
19 |
|
Action Level |
- |
<5.5 or >7.5 |
<4.13 |
- |
>81 |
- |
>66 |
|
Limit Level |
- |
<4.0 or >8.0 |
<3.87 |
- |
>84 |
- |
>69 |
|
|
|
|
|
|
|
|
|
|
MP6 |
|
|
|
|
|
|
|
|
03/11/2014 |
25.0 |
7.4 |
7.2 |
87.3 |
11.6 |
<2 |
14 |
|
05/11/2014 |
24.6 |
7.4 |
6.9 |
83.7 |
8.9 |
<2 |
9.5 |
|
07/11/2014 |
24.5 |
7.4 |
6.8 |
82.6 |
13.7 |
2 |
17.5 |
|
10/11/2014 |
24.4 |
7.4 |
6.8 |
82.7 |
26.0 |
2 |
20 |
|
12/11/2014 |
24.3 |
7.4 |
7.3 |
87.5 |
16.4 |
<2 |
17.5 |
|
14/11/2014 |
23.5 |
7.4 |
7.0 |
83.7 |
20.1 |
2 |
14.5 |
|
17/11/2014 |
23.1 |
7.4 |
7.1 |
83.3 |
24.8 |
6 |
18 |
|
19/11/2014 |
22.3 |
7.4 |
5.4 |
69.6 |
32.1 |
4 |
30.5 |
|
21/11/2014 |
22.3 |
7.4 |
6.8 |
84.2 |
21.7 |
6 |
22.5 |
|
24/11/2014 |
22.1 |
7.4 |
7.1 |
82.5 |
29.7 |
4 |
24 |
|
26/11/2014 |
21.0 |
7.4 |
7.3 |
82.2 |
22.5 |
2 |
23 |
|
28/11/2014 |
23.4 |
7.4 |
6.8 |
80.6 |
21.5 |
3 |
20 |
|
Action Level |
- |
<5.5 or >7.5 |
<4.61 |
- |
>94 |
- |
>75 |
|
Limit Level |
- |
<4.0 or >8.0 |
<4.52 |
- |
>96 |
- |
>75 |
Notes:
(1) “<2 “
: BOD value is too low to indicate (<2mg/L).
(2) Values Bold indicate Action Level exceedance.
(3) Values Underlined and Bold indicate
Limit Level exceedance.
During November 2014, one exceedance of DO was
observed at MP3. No exceedance
was observed at MP4, MP5 and MP6.
The Event and Action Plan in Appendix D was followed under these cases of exceedances.
From investigation, construction
activities during the period of exceedance included
mainly site formation and foundation work, as well as pond drainage management
in the Wetland Restoration Area (to lower the water level and remove unwanted
species in the pond). It was observed that the Contractor has implemented water
quality mitigation measures as recommended in the EIA report, including the
provision of temporary drainage facility and associated treatment facility.
Sand bags are in place in the temporary drainage channel to enhance the desilting efficiency. The Contractor further enhanced the
water quality mitigation measures by erecting several segments of rock bunds
and installing a barrier at the discharge outlet to desilt
and divert site runoff to sedimentation tanks and wastewater treatment
facilities (Aquased), which will ensure all site runoff is treated to satisfactory quality before discharging
into the northern ditches.
Exceedance of DO at MP3
During the reporting month at MP3, exceedance of the Action/Limit Level of DO was observed on
one monitoring dates. As understood, the fish pond near the site (represented
by MP3) was being separated from the construction site by the WRA since
November 2010, so the exceedances were not considered
to be related to the construction activities. The exceedances
of DO may be due to external factors such as pond fish culture activities which
were out of the control of the project.
Conclusion
As a result, the abovementioned exceedances are unlikely to be due to the construction
works and therefore not considered to be related to the project.
This report
documents surveys conducted in the Survey Area between 1 and 30 November 2014.
The Wetland Restoration Area (WRA) is also surveyed as the area is accessible
and site formation works for WRA has been completed. The updated survey transect is provided in Figure 4.1. Dates and ecological surveys
conducted during this period are summarised in Appendix H.
Monitoring
was undertaken following the survey methodology in the EM&A Manual. A
transect was followed in the bird surveys (see Figure 4.1). All bird species were identified
to species and all bird species of conservation importance and/or wetland
dependent were enumerated and recorded to the habitats in which they were
observed. Flying birds were not recorded unless they were foraging and/or
associated with the habitat (such as swifts). Further, notable bird
observations during other surveys were also recorded.
Bird surveys were conducted on a weekly basis. A total of 47 bird species
were recorded in the Survey Area (excluding the WRA), 28 of which were species
of conservation importance and/or wetland-dependence. Within the WRA, 35 bird
species were recorded, 17 of which were species of conservation importance
and/or wetland-dependent species, including two of the target species (i.e.
Little Egret, Chinese Pond Heron) were recorded in regular survey. The WRA
continues to attract a number of species of conservation importance, including
Yellow Bittern, Ixobrychus sinensis and
Common Greenshank, Tringa nebularia in
regular survey and additional night search. Yellow Bittern, Ixobrychus sinensis and Common Greenshank, Tringa nebularia are
listed by Fellowes et al. as of “Local Concern” in 2002.
One day time herpetofauna survey were conducted in the period. No amphibian species and reptile species were recorded in the Survey Area (excluding the WRA) nor within the WRA in regular survey and additional search.
A summary of the survey findings is provided in Appendix J.
Odonatas and butterflies surveys were conducted on a monthly
basis according to the EM&A Manual. No odonata
species and butterfly species were recorded in the Survey Area (excluding the
WRA) during regular survey and additional search. Within the WRA, five odonata species were recorded, while two butterfly species
were recorded
A summary of the survey findings is provided in Appendix J.
Monitoring of mammals was
conducted concurrently with other surveys. No mammals were
recorded in the Survey Area nor within the WRA during
regular survey.
A summary of the survey findings is provided
in Appendix J.
Water level of Cell 2 and Cell 4 reached the action
level within the reporting period.
Monitoring data are presented in Appendix K.
Removal of exotic vegetation in all cells was
undertaken; these included but not limited to Ipomoes sp., Mikania sp., Mimosa sp., Pennisetum
sp. and Typha sp..
All
sighted Red Fire Ant nests were treated with approved pesticide.
Ecological monitoring during November 2014 was carried out according to
the survey methodology and frequency outlined in the EM&A Manual.
Summary of
survey findings is listed in Table 4.1 below:
Table 4.1: Summary of Ecological Monitoring in WRA and Survey Area
|
Species |
Survey Area (excluding WRA) |
WRA |
|
|
Birds (total) |
47 |
35 |
|
|
Birds (of
conservation importance and/or wetland-dependence) |
28 |
17 |
|
|
Amphibians |
0 |
0 |
|
|
Reptiles |
0 |
0 |
|
|
Mammals |
0 |
1 |
|
|
Odonates |
0 |
5 |
|
|
Butterflies |
0 |
0 |
|
Survey findings indicate that the ponds within the Survey
Area supported numbers and diversity of wetland-dependent birds typical of fish
pond areas. The WRA continues to attract
wetland dependent fauna and serves as a buffer between the residential portion
and the fishponds in the north.
The EM&A
programme for Landscape and Visual impact due to the construction commenced in June
2010 and continued during the reporting period. Site inspections on Landscape
and Visual impact were carried out on 14 and 26 November 2014 to confirm the
implementation of mitigation measures at construction stage.
The audit was undertaken with references to the specific checklists
provided in Tables 2.13 – 2.15 and audit results are summarized below in Table 5.1.
Representative photos showing the implementation of mitigation measures are presented in Appendix M.
Table 5.1: Construction and Operation Phase Audit Summary
|
Area of Works |
Items to be
Monitored |
|
|
Works Area |
The boundaries of the works area have been established on site in
accordance with the contract documents and approved plans (EP), and the
limit of current heavy construction activity is now confined to within the
site hoardings (North side of the site / access road) and the noise barriers
(other sides of the site). Minor works such as horticultural maintenance of
the planting and transplanted trees, and boundary fence repair was
proceeding along the Royal Palms – Palm Springs boundary. (Appendix M Photo 1 – Table 2.14 CM2 refers) No construction
works were observed to have exceeded the site boundaries. No construction was carried out at the wetland
restoration area after 15 November 2010. |
|
|
Protection of all
trees and woodland blocks to be retained |
Trees retained
within the site along the northeast boundary, beside wetland restoration
area, have been identified and protected by temporary protective fencing. |
|
|
Streams |
The works site is
partly encircled by a berm / perimeter channel to intercept surface water
and prevent it from washing off into any of the neighboring sites. Surface water is collected within the site
in a temporary drainage channel.
Gravels beds and barriers have been installed to filter site runoff,
sedimentation ponds have been provided to enable primary treatment before
discharge to mains drains. |
|
|
Clearance of
existing vegetation |
Site clearance was
completed prior to the commencement of construction. |
|
|
Transplanting of
trees |
Tree transplanting
has been completed, with the trees relocated to various points within the
planting strip along the southern boundary of the site, outside the noise barrier. The trees continue to re-establish well. |
|
|
Topsoil stripping |
Suitable pond bund and soil material which had been excavated and
stockpiled from the original site, has now been
re-used within the landscape works. Dust suppression measures
are active along all internal site access tracks. |
|
|
New buildings |
No new permanent
buildings have yet been constructed on site. |
|
|
Boundaries |
Hoardings have
been erected along most of the boundaries of the site. Installation of new screen fence between
the future residential sites and the constructed wetland restoration areas
is complete. Fence has been painted green to match with the surrounding
vegetated environment. (Appendix M
Photo 1 – Table 2.14 CM2 refers) |
|
|
Noise Barrier |
Noise barriers
have been installed along the southern and western boundaries of the site in
accordance with the contract requirements.
Their design complies with the mitigation requirements, with upper 6
to 7m portion of the barrier being made from a translucent material with
green tinted (to match with the environment). Supporting GMS structure,
likewise, has been painted green. (Appendix
M Photo 4 – Table 2.14 CM6 refers) |
|
|
Night-time
lighting |
No night-time
works were reported to have been carried out during the monitoring period |
|
|
Landscape and
wetland treatments generally |
Continuous belt of screen planting along the southern and western
boundaries of the site has been completed.
The formation, soiling and water control structures of the wetland restoration
area have been completed. (Appendix M
Photo 3 – Table 2.14 CM6 refers) The wetland areas
are being established, with the ponds are being seasonally filled with rain
water. Planting of areas around the
WRA cells is complete. No
construction was carried out at the wetland restoration area after 15
November 2010. (Appendix M Photo 2
– Table 2.14 CM2 refers) |
|
|
Soiling, etc. |
The soiling for
the advance planting strip has been completed. The soil placement and grading for each of
the wetland restoration areas has been completed. |
|
|
Plant supply |
The plant material used in the Advance Planting Strip and in the WRA
are all commonly available species and came from commercial sources. Transplanted reeds (Phragmites australis) at the wetland habitat
came from the temporary holding nursery onsite. |
|
|
Planting |
The total number of trees that will reach a minimum of 10m in the
advance planting strip meets the contract requirements. The tree species are all from the approved
list. This planting should achieve
the required screening effect within the required time period. (Appendix
M Photo 3 – Table 2.14 CM6 refers) Some of the trees that were identified as dead in previous month or
having defects (i.e. extensive bark damage, cavities, fungal growths, etc.)
still need to be replaced with new specimens. Some of the recently planted
trees are still in poor condition, but are showing small signs of graduate
improvement Seedling trees and
shrubs, have been established at the margins of the
wetland cells. Some additional fill-in planting has been undertaken. |
|
|
Establishment Works |
|