Issue and
revision record
|
|
|
|
|
|
|
|
|
|
|
|
Date |
Originator |
Checker |
Approver |
Description |
|
Rev. A |
Jan 2010 |
Benny Liu/ Peter Wong |
|
Eric Ching |
Submission to IEC
for comment |
Rev. B |
Jan 2010 |
Benny Liu/ Peter Wong |
|
Eric Ching |
Submission to EPD |
This document contains
confidential information and proprietary intellectual property. It should not
be shown to other parties without consent from us and from the party which
commissioned it.
This
document is issued for the party which commissioned it and for specific
purposes connected with the above-captioned project only. It should not be
relied upon by any other party or used for any other purpose.
We accept no responsibility for the
consequences of this document being relied upon by any other party, or being
used for any other purpose, or containing any error or omission which is due to
an error or omission in data supplied to us by other parties
Content
Chapter Title Page
List of Figures
Figure 1.1 Layout plan of the Project
Figure 2.1 Locations of Baseline Air Quality Monitoring Stations
Figure 3.1 Locations of Baseline Noise Monitoring Stations
Figure 4.1 Locations of Baseline Water Quality Monitoring Stations
Figure 6.1 Landscape Resources (Plan)
Figure 6.2 Landscape Character Areas (Plan)
List of Appendices
Appendix A. Calibration Record
Appendix B. Baseline Monitoring Schedule
Appendix C. Baseline Air Quality Monitoring Results
Appendix D. Baseline Noise Monitoring Results
Appendix E. Baseline Water Quality Monitoring Results
Appendix F. Updates of Landscape Resources
Appendix G. Weather Information from HKO
Mott MacDonald Hong Kong Ltd. (MMHK)
has been commissioned by the Heng Shung Construction Co. Ltd. to undertake the
Environmental Team (ET) services to carry out environmental monitoring and
audit for the construction of the Proposed Comprehensive Development at Wo
Shang Wai, Yuen Long.
This Baseline Monitoring Report is
required under the approved EM&A and is submitted to fulfil Conditions 4.4
of the Environmental Permit No. EP-311/2008 issued pertaining to this
designated project Proposed Comprehensive Development at Wo Shang Wai, Yuen
Long
Baseline Air Quality Monitoring
Baseline air quality monitoring was
carried out prior to construction period. The locations of monitoring stations
were proposed in accordance with the EM&A Manual and were agreed with EPD
and IEC before commencement of monitoring.
The monitoring was carried out from
1 December to 14 December 2009 at the monitoring stations. Since there are no
major activities near the designed monitoring stations during baseline
monitoring, the baseline air quality monitoring data established in this
monitoring period are considered representative of the baseline condition for
the Project.
The Action Levels for 24-hr and 1-hr
TSP during impact monitoring are established based on the measured baseline TSP
levels for assessing the impact and compliance during the construction of the
Project.
Baseline Noise Monitoring
Baseline noise monitoring was
carried out prior to construction period. The locations of monitoring stations
were proposed in accordance with the EM&A Manual and were agreed with EPD
and IEC before commencement of monitoring.
The monitoring was conducted between
1 December and 16 December 2009 at the monitoring stations. Monitoring was
suspended on 8 December 2009 due to heavy rain.
Results of Leq for the 4
stations ranged from 50 to 61 dB(A). The measured baseline noise levels (Leq,
30min) between 0700 and 1900 hours are therefore well within 75dB(A), which is
daytime construction noise limit under Environmental Impact Assessment
Ordinance (EIAO).
During baseline monitoring period,
no major activities were observed; therefore the baseline noise monitoring data
is considered representative of the baseline condition for the Project. Action
and Limit Levels for Construction Noise follow the Levels defined in the
EM&A Manual.
Baseline Water Quality Monitoring
Water quality measurement was
carried out at 6 designated monitoring stations (MP1 to MP6) from 16 November
to 11 December 2009. Monitoring for Dissolved Oxygen (DO), temperature, pH,
suspended solids (SS) and Biological Oxygen Demand (BOD) were undertaken. DO,
temperature and pH were measured in-situ whereas SS and BOD were analysed in a
laboratory. The interval between any two sets of monitoring was not less than
36 hours.
Dissolved oxygen level at MP1 and
MP2 recorded were particularly low. SS levels for all monitoring stations were
ranged from medium to high.
No construction activities in the
vicinity of the monitoring points were observed during the baseline monitoring.
Baseline Ecological Monitoring
Ecological baseline monitoring was
conducted during the preparation of the Ecological Impact Assessment for the
approved EIA report of the project.
Baseline Landscape and Visual
Monitoring
The baseline monitoring for
landscape and visual resources was conducted in November 2009. The baseline
condition of landscape resources, landscape character areas and visually
sensitive receivers identified in the EIA report were reviewed and updated.
The baseline monitoring observed
that one of the landscape resources within the project site LR34 Banana Trees on Site was removed.
However its removal did not substantially affect the landscape and visual
baseline or outcome of the assessment for its low sensitivity to change.
No substantial changes in all other
landscape and visual resources were recorded. Changes to the landscape and
visual baseline originally identified in the EIA study are therefore judged to
be insignificant.
In March 2005, the Project Proponent, Profit Point Enterprises Limited, acquired the development site in Yuen Long at Wo Shang Wai. An Environmental Impact Assessment (EIA) was carried out under EIAO since then and the Environmental Permit for construction of the comprehensive development in Wo Shang Wai was granted by EPD on 9 September 2008.
Mott MacDonald Hong
Kong Ltd. (MMHK) has been
commissioned by the Heng Shung Construction Co. Ltd. to undertake the
Environmental Team (ET) services to carry out environmental monitoring and audit for the construction of the
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long.
This Baseline monitoring report is required under the approved EM&A and is submitted to fulfil Conditions 4.4 of the Environmental Permit No. EP-311/2008 issued pertaining to this designated project Proposed Comprehensive Development at Wo Shang Wai, Yuen Long
The purpose of this Baseline monitoring report is to establish the baseline levels of air quality (dust), noise, water quality, ecology, and landscape and visual in accordance with the EM&A Manual.
These levels are intended as the basis for assessing environmental impact and compliance during construction phase of the Project. This report presents the baseline monitoring requirements, methodologies and results of baseline measurements in accordance with the requirements, where applicable, in the EM&A Manual.
This Baseline Monitoring Report presents the monitoring works conducted from 24 November 2009 to 16 December 2009. A layout plan of the Project is provided in Figure 1.1.
The structure of the report is as follows:
· Section 1 - Introduction, background, purpose and the structure of the report
· Section 2 - Air Quality with description of the baseline air quality monitoring requirements, methodology and results
· Section 3 - Noise with description of the baseline noise monitoring requirements, methodology and results
· Section 4 - Water quality with description of the baseline water quality monitoring requirements, methodology and results
· Section 5 - Ecology
· Section 6 - Landscape and visual, with description of the baseline monitoring requirements, methodology and results
· Section 7 - Comments and Conclusions
In accordance with the EM&A Manual, baseline
1-hour and 24-hour TSP levels at 4 air quality monitoring stations are to be
established. Baseline 1-hour and 24-hour TSP monitoring were conducted for 14
consecutive days from 1 December to 14 December 2009 inclusive of both days
prior to commencement of construction of the Project.
Continuous 24-hour TSP air quality monitoring was conducted using High Volume Sampler (HVS) (Model: GMWS-2310 Accu-vol) located at designated monitoring station shown in Figure 2.1. The HVS meets all the requirements of the EM&A Manual. Portable direct reading dust meters were used to carry out the 1-hour TSP monitoring. Table 2-1 summarizes the equipment used in the baseline air quality monitoring. Copies of the calibration certificates for the HVS and portable dust meters are attached in Appendix A.
Table 2‑1 TSP Monitoring Equipment
Equipment |
Model |
24-hr TSP monitoring |
|
High Volume
Sampler |
GMWS 2310
Accu-vol |
Calibrator |
GMW 25 |
1-hr TSP monitoring |
|
Portable direct
reading dust meter |
8520 Dust Track Aerosol
Monitor |
Table 2-2 summarizes the monitoring parameters,
frequency and duration of baseline TSP monitoring. Baseline 1-hour and 24-hour TSP
monitoring was scheduled at 4 stations from 1 December to 14 December 2009 for
14 consecutive days. Detailed baseline air quality monitoring schedule is
provided in Appendix B.
Table 2‑2 Air Quality Monitoring Parameters,
Frequency and Duration
Parameter |
Frequency and Duration |
|
ASR1, ASR2A, ASR3 & ASR4 |
24-hour TSP |
Daily, for 14
consecutive days |
1-hour TSP |
3 times a day, for
14 consecutive days |
Four monitoring stations (ASR1, ASR2A, ASR3 and ASR4) were proposed in the EM&A Manual. Upon review of site constraints and agreement with property owners around the site, the actual locations of these stations were slightly altered following the criteria set in the EM&A Manual. The renewed locations of air quality monitoring stations were agreed with the IEC and EPD prior to the baseline monitoring. Locations of the monitoring stations are given in Table 2-3 and are shown in Figure 2.1.
Table 2‑3 Air monitoring stations
Monitoring Stations |
Locations |
ASR1 |
Works Site
Boundary |
ASR2A |
At the rooftop of
refuse collection point, which is located at the southwest of the project
area |
ASR3 |
At the commercial
centre at |
ASR4 |
Works Site
Boundary |
24-hour TSP Monitoring
Installation
The HVS was installed in the vicinity of the air sensitive receiver. The following criteria were considered in the installation of the HVS.
· A horizontal platform with appropriate support to secure the sampler against gusty wind was provided.
· The distance between the HVS and any obstacles, such as buildings, was at least twice the height that the obstacle protrudes above the HVS.
· A minimum of 2 meters separation from walls, parapets and penthouse was required for rooftop sampler.
· A minimum of 2 meters separation from any supporting structure, measured horizontally was required.
· No furnace or incinerator flues or building vent were nearby.
· Airflow around the sampler was unrestricted.
· The sampler has been more than 20 metres from any drip line.
· Permission was obtained to set up the samplers and to obtain access to the monitoring stations.
· A secured supply of electricity is needed to operate the samplers.
Preparation
of Filter Papers
· Glass fibre filters, were labelled and sufficient filters that were clean and without pinholes were selected.
· All filters were equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature was around 25 °C and not variable by more than ±3 °C with relative humidity (RH) < 50% and was not variable by more than ±5 %. A convenient working RH was 40%.
Field
Monitoring
· The power supply was checked to ensure the HVS works properly.
· The filter holder and the area surrounding the filter were cleaned.
· The filter holder was removed by loosening the four bolts and a new filter, with stamped number upward, on a supporting screen was aligned carefully.
· The filter was properly aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.
· The swing bolts were fastened to hold the filter holder down to the frame. The pressure applied should be sufficient to avoid air leakage at the edges.
· The shelter lid was closed and was secured with the aluminium strip.
· The HVS was warmed-up for about 5 minutes to establish run-temperature conditions.
· A new flow rate record sheet was set into the flow recorder.
· The flow rate of the HVS was checked and adjusted at around 1.1 m3/min. The range specified in the EM&A Manual was between 0.6-1.7 m3/min.
· The programmable timer was set for a sampling period of 24 hrs + 1 hr, and the starting time, weather condition and the filter number were recorded.
· The initial elapsed time was recorded.
· At the end of sampling, the sampled filter was removed carefully and folded in half length so that only surfaces with collected particulate matter were in contact.
· It was then placed in a clean plastic envelope and sealed.
· All monitoring information was recorded on a standard data sheet.
· Filters were sent to a HOKLAS accredited laboratory for analysis.
Maintenance
and Calibration
· The HVS and its accessories are maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.
· HVSs were calibrated prior to the commencement of baseline monitoring.
· Calibration records for HVSs are shown in Appendix A.
1-hour TSP Monitoring
Field
Monitoring
The measuring procedures of the 1-hour dust meter are in accordance with the Manufacturers Instruction Manual as follows:
·
Set POWER to ON, push
· Push the knob at MEASURE position.
· Push O-ADJ button. (Then meters indication is 0).
· Push the knob at SENSI ADJ position and set the meters indication to S value described on the Test Report using the trimmer for SENSI ADJ.
· Pull out the knob and return it to MEASURE position.
· Push START button.
Maintenance
and Calibration
· The 1-hour dust meter would be checked at 3-month intervals and calibrated at 1-year intervals throughout all stages of the air quality baseline monitoring.
· Calibration records for HVS and direct dust meters are shown in Appendix A.
Weather
Condition
· The weather conditions, including wind data, during the monitoring period were recorded and provided in Appendix G.
The baseline air quality monitoring results at the 4 stations are summarized in Table 2-4. Detail 1-hour and 24-hour TSP monitoring results are presented in Appendix C.
Table 2‑4 Summary of Average
Baseline Air Quality Monitoring Results
Monitoring Station |
Average
24-hour TSP Concentration (mg/m3)/
(Range) |
Average
1-hour TSP Concentration (mg/m3)/
(Range) |
ASR1 |
148 (93 212) |
197 (92 312) |
ASR2A |
127 (74 184) |
165 (80 280) |
ASR3 |
115 (69 172) |
166 (80 286) |
ASR4 |
165 (91 234) |
188 (88 322) |
The weather condition during the baseline
monitoring period was mostly sunny and fine at the start and end of the
monitoring but the weather were rainy and cloudy for a few days in between. No
major activities were observed in the Project Area during the monitoring
period. The major dust sources were from road traffic along
The Action and Limit levels (
Table 2‑5 Derivation
of Action and Limit Levels for Air Quality
Parameter |
Action
Level |
Limit
Level |
24-hour TSP Level
in mg/m3 |
·
For baseline
level ≤ 200 mg/m3, Action level = (Baseline level x
1.3 + Limit level)/2 ·
For baseline
level > 200 mg/m3, Action level = Limit level |
260 |
1-hour TSP Level
in mg/m3 |
·
For baseline
level ≤ 384 mg/m3, Action level = (Baseline level x
1.3 + Limit level)/2 ·
For baseline
level > 384 mg/m3, Action level = Limit level |
500 |
Following the criteria shown in Table 2-5, the
AL Levels for 24-hour and 1-hour TSP for the 4 monitoring stations are derived
and presented in Table 2-6 & Table 2-7 respectively.
Table 2‑6 Action and Limit Levels for 24-hour
TSP
Monitoring
Station |
Action
Level (mg/m3) |
Limit
Level (mg/m3) |
ASR1 |
226 |
260 |
ASR2A |
213 |
260 |
ASR3 |
205 |
260 |
ASR4 |
237 |
260 |
Table 2‑7 Action
and Limit Levels for 1-hour TSP
Monitoring
Station |
Action
Level (mg/m3) |
Limit
Level (mg/m3) |
ASR1 |
378 |
500 |
ASR2A |
357 |
500 |
ASR3 |
358 |
500 |
ASR4 |
372 |
500 |
Should non-compliance of the air quality criteria occurs during construction stage, actions in accordance with the Event and Action Plan in Table 2-8 below should be carried out.
Table 2‑8 Event and Action Plan for Air Quality
Event |
Action |
|||
ET Leader |
IEC |
ER |
Contractor |
|
Action Level |
|
|
|
|
1.
Exceedance for one sample |
1.
Identify source, investigate the causes of exceedance
and propose remedial measures. 2.
Inform IEC and ER. 3.
Repeat measurement to confirm finding. 4.
Increase monitoring frequency to daily. |
1.
Check monitoring data submitted by ET. 2.
Check Contractors working method. |
1.
Notify Contractor. |
1.
Rectify any unacceptable practice. 2.
Amend working methods if appropriate. |
2.
Exceedance for two or more consecutive samples |
1.
Identify the
source. 2.
Inform IEC and ER. 3.
Advise ER on the
effectiveness of the proposed remedial measures 4.
Repeat measurements to confirm findings. 5.
Increase monitoring frequency to daily. 6.
Discuss with IEC and the Contractor on remedial actions
required. 7.
If exceedance continues, arrange meeting with IEC and ER. 8.
If exceedance stops, cease additional monitoring. |
1.
Check monitoring data submitted by ET. 2.
Check the Contractors working method. 3.
Discuss with ET Leader and the Contractor on possible
remedial measures. 4.
Advise ER on the effectiveness of the proposed remedial
measures. 5.
Supervise implementation of remedial measures. |
1.
Confirm receipt of notification of exceedance in writing. 2.
Notify the Contractor. 3.
Ensure remedial measures properly implemented. |
1.
Submit proposals for remedial actions to IEC within 3
working days of notification. 2.
Implement the agreed proposals. 3.
Amend proposal if appropriate. |
Limit Level |
|
|
|
|
1.
Exceedance for one sample |
1.
Identify source, investigate the causes of exceedance and
propose remedial measures. 2.
Inform ER and EPD. 3.
Repeat measurement to confirm finding. 4.
Increase monitoring frequency to daily. 5.
Assess effectiveness of Contractors remedial actions and
keep IEC, EPD and ER informed of the results. |
1.
Check monitoring data submitted by ET. 2.
Check the Contractors working method. 3.
Discuss with ET Leader and the Contractor on possible
remedial measures. 4.
Advise ER on the effectiveness of the proposed remedial
measures. 5.
Supervise implementation of remedial measures. |
1.
Confirm receipt of notification of exceedance in writing. 2.
Notify the Contractor. 3.
Ensure remedial measures properly implemented. |
1.
Take immediate action to avoid further exceedance. 2.
Submit proposals for remedial actions to IEC within 3
working days of notification. 3.
Implement the agreed proposals. 4.
Amend proposal if appropriate. |
2.
Exceedance for two or more consecutive samples |
1.
Notify IEC, ER, EPD and the Contractor. 2.
Identify the source. 3.
Repeat measurements to confirm findings. 4.
Increase monitoring frequency to daily. 5.
Carry out analysis of the Contractors working procedures
to determine possible mitigation to be implemented. 6.
Arrange meeting IEC and ER to discuss the remedial actions
to be taken. 7.
Assess effectiveness of the Contractors remedial actions
and keep IEC, EPD and ER informed of the results. 8.
If exceedance stops, cease additional monitoring. |
1.
Discuss amongst ER, ET Leader and the Contractor on the
potential remedial actions. 2.
Review the Contractors remedial actions whenever
necessary and advise ER accordingly. 3.
Supervise the implementation of remedial measures. |
1.
Confirm receipt of notification of exceedance in writing. 2.
Notify the Contractor. 3.
In consultation with IEC, agree with the remedial measures
to be implemented. 4.
Ensure remedial measures are properly implemented. 5.
If exceedance continues, consider what activity of the
work is responsible and instruct the Contractor to stop that activity of work
until the exceedance is abated. |
1.
Take immediate action to avoid further exceedance. 2.
Submit proposals for remedial actions to IEC within 3
working days of notification. 3.
Implement the agreed proposals. 4.
Resubmit proposals if problem still not under control. 5.
Stop the relevant activity of works as determined by ER
until the exceedance is abated. |
Following the requirements in the EM&A Manual for noise, baseline noise monitoring has been carried out prior to the commencement of the construction works. No construction activities in the vicinity of the stations were observed during the baseline monitoring. Continuous baseline noise monitoring for the A-weighted levels Leq, L10 and L90 was carried out daily for a period of at least two weeks. The schedule on the baseline monitoring was approved by IEC and EPD before the monitoring started.
Integrating Sound Level Meter was used for noise monitoring.
It was a Type 1 sound level meter capable of giving a continuous readout of the
noise level readings including equivalent continuous sound pressure level (Leq)
and percentile sound pressure level (Lx). They comply with
International Electrotechnical Commission Publications 651:1979 (Type 1) and
804:1985 (Type 1). Table 3-1 summarizes the noise monitoring equipment model
being used.
Table 3‑1 Noise
Monitoring Equipments
Monitoring locations |
Equipment
Model |
|
Integrating
Sound Level Meter |
Calibrator |
|
NSR1 |
B&K 2238 |
Rion NC-73 |
NSR3 |
Rion NL-14 |
|
NSR5 |
Rion NA27 |
|
NSR7 |
B&K 2238 |
Table 3-2 summarizes the monitoring parameters, frequency and
duration of noise monitoring. It was proposed that the baseline noise in
A-weighted levels Leq, L10 and L90 were
recorded in a 30-minute interval between 0700-1900 during the 14-day monitoring
period at the designated monitoring stations shown in Figure 3.1. The baseline noise monitoring
schedule is provided in Appendix B.
Table 3‑2 Noise Monitoring
Parameters, Period and Frequency
Period |
Parameters |
1 December to 16
December 2009 with sampling period of
30 minutes between 0700 and 1900. |
Leq, L90
& L10 |
Due to rainfall on 8
December 2009, the monitoring was suspended on 8 December 2009 and restarted on
9 December 2009. The monitoring period was extended to 16 December 2009.
Four monitoring stations (NSR1, NSR3, NSR5 and NSR7) were
proposed in the EM&A Manual. Access to some of these monitoring locations
stated were rejected or not available. Therefore, alternative locations were
proposed and agreed by the IEC and EPD. The locations of the monitoring
stations are described in Table 3-3 and shown in Figure 3.1.
Table 3‑3 Locations of Noise Monitoring Stations
Monitoring Station |
Locations |
Type of measurement |
NSR1 |
Noise monitoring
equipment was set up near the boundary wall at |
Free-field |
NSR3 |
The monitoring station
was located next to the guard house at |
Facade |
NSR5 |
The monitoring station
was located within the work site boundary. |
Free-field |
NSR7 |
The monitoring station
was located near the boundary wall of the house of Mai Po San Tsuen. |
Free-field |
* For free-field
measurement, +3dB(A) was added to the measured results.
Field Monitoring
· The Sound Level Meter was set on a tripod at a height of at least 1.2 m above the ground.
· Faηade and free-field measurements were made at the monitoring locations.
· The battery condition was checked to ensure the correct functioning of the meter.
· Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:
- frequency weighting: A
- time weighting: Fast
- time measurement: 30 minutes intervals (between 0700 and 1900)
· Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94 dB at 1 kHz. If the difference in the calibration level before and after measurement was more than 1 dB, the measurement would be considered invalid has to be repeated after re-calibration or repair of the equipment.
· During the monitoring period, the Leq, L10 and L90 were recorded. In addition, any site observations and noise sources were recorded on a standard record sheet.
Maintenance and
Calibration
· The microphone head of the sound level meter and calibrator is cleaned with soft cloth at quarterly intervals.
· The meter and calibrator are sent to the supplier or HOKLAS laboratory to check and calibrate at yearly intervals.
· Calibration records are shown in Appendix A.
The noise monitoring results are summarized in Table 3‑4. Detailed noise monitoring results are presented in Appendix D. A few questionable results of Leq
(e.g. noise levels that are unusually high or low) are excluded to provide a
more representative set of data.
Table
3‑4 Summary of Baseline Daytime Noise
Monitoring Results
Normal weekdays, 30 minutes between 0700 - 1900
hrs |
Mean
& Range of Noise Levels, dB(A) |
||
L90 |
L10 |
Leq |
|
NSR1 |
46.6 (36.5 51.0) |
51.6 (43.0 61.0) |
50.7 (43.6 57.5) |
NSR3 |
47.9 (37.1 53.4) |
51.6 (39.9 56.0) |
50.3 (39.6 55.3) |
NSR5 |
51.7 (41.6 56.1) |
57.3 (43.7 72.6) |
58.5 (42.8 67.3) |
NSR7 |
57.4 (45.1 61.0) |
62.1 (57.0 65.0) |
60.5 (56.4 63.6) |
The measured baseline noise levels (Leq, 30min) between 0700 and 1900 hours are well within 75dB(A), which is daytime construction noise limit under Environmental Impact Assessment Ordinance (EIAO). The noise levels are also within the daytime construction noise criteria during examination periods (65 dB(A). Results of Leq for the 4 stations ranged from 50 to 61 dB(A) which show that the area are under a low ambient noise condition. It is noted that the Leq of NSR5 is larger than L10. This is a reflection of the intermittent noise impact from trucks going into and out of the open storage area near the site while NSR5 was located close to the access road.
The noise levels of NSR1 and NSR3 were significantly lower than that of NSR5 and NSR7 as they are farther away from highway traffic and therefore are subjected to lower ambient noise.
The weather condition during the monitoring period was mainly
sunny and fine. However, the monitoring was suspended on 8 December 2009 due to
rainfall. There were vehicles passing through the access road to open storage
which also contributed to the noise source. No major activities in the Project
were undertaken during baseline monitoring period, and therefore the baseline
noise monitoring data is representative of the baseline condition for the
Project. The weather condition during the monitoring period is provided in Appendix G.
The Action and Limit Levels (
Table 3‑5 Action
and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
NSR1 |
||
0700 1900 hours on
normal weekdays |
When one documented complaint
is received from any one of the sensitive receivers |
75 dB(A) |
NSR3 |
||
0700 1900 hours on
normal weekdays |
When one documented
complaint is received from any one of the sensitive receivers |
75 dB(A) |
NSR5 |
||
0700 1900 hours on normal
weekdays |
When one documented
complaint is received from any one of the sensitive receivers |
75 dB(A) |
NSR7 |
||
0700 1900 hours on
normal weekdays |
When one documented
complaint is received from any one of the sensitive receivers |
75 dB(A) |
In case the Action and Limit Levels are not complied during construction stage, the following Event and Action Plan should be followed:
Table 3‑6 Event and Action Plan for Construction Noise
Event |
Action |
|||
ET Leader |
IEC |
ER |
Contractor |
|
Action Level |
1.
Notify IEC and the Contractor. 2.
Carry out investigation. 3.
Report the results of investigation to IEC and the Contractor. 4.
Discuss with the Contractor and formulate remedial measures. 5.
Increase monitoring frequency to check mitigation measures. |
1.
Review with analysed results submitted by ET. 2.
Review the proposed remedial measures by the Contractor and advise ER
accordingly. 3.
Supervise the implement of remedial measures. |
1.
Confirm receipt of notification of exceedance in writing. 2.
Notify the Contractor. 3.
Require the Contractor to propose remedial measures for the analysed
noise problem. 4.
Ensure remedial measures are properly implemented. |
1.
Submit noise mitigation proposals to IEC. 2.
Implement noise mitigation proposals. |
Limit Level |
1.
Identify the source. 2.
Notify IEC, ER, EPD and the Contractor. 3.
Repeat measurement to confirm findings. 4.
Increase monitoring frequency. 5.
Carry out analysis of Contractors working procedures to determine
possible mitigation to be implemented. 6.
Inform IEC, ER, and EPD the causes & actions taken for the
exceedances. 7.
Assess effectiveness of the Contractors remedial actions and keep
IEC, EPD and ER informed of the results. 8.
If exceedance stops, cease additional monitoring. |
1.
Discuss amongst ER, ET Leader and the Contractor on the potential
remedial actions. 2.
Review the Contractors remedial actions whenever necessary to assure their
effectiveness and advise ER accordingly. 3.
Supervise the implementation of remedial measures. |
1.
Confirm receipt of notification of exceedance in writing. 2.
Notify the Contractor. 3.
Require the Contractor to propose remedial measures for the analysed
noise problem. 4.
Ensure remedial measures are properly implemented. 5.
If exceedance continues, consider what activity of the work is
responsible and instruct the Contractor to stop that activity of work until
the exceedance is abated. |
1.
Take immediate action to avoid further exceedance. 2.
Submit proposals for remedial actions to IEC within 3 working days of
notification. 3.
Implement the agreed proposals. 4.
Resubmit proposals if problem still not under control. 5.
Stop the relevant activity of works as determined by the ER until the
exceedance is abated. |
In accordance with Section 4.5 of the EM&A Manual, baseline water quality monitoring has been carried out to establish ambient conditions prior to the commencement of the works; and to demonstrate the suitability of the proposed impact and reference monitoring points.
The Water Quality Monitoring Equipments and Analytical Methods applied to Water Quality Samples are given in Table 4-1 and Table 4-2 respectively. Details of which are discussed below.
Table 4-1 Water Quality Monitoring Equipments
Equipment |
Model |
Equipment /Serial Number |
Dissolved oxygen, temperature & pH Measuring Meter |
YSI 556 MPS |
ENO 008/ 07L100507 |
Turbidimeter |
Hach 2100P |
ENO 010/ 07030C021728 |
Global Positioning System (GPS) |
Garmin eTrex |
ENO 007 |
Table 4-2 Analytical Methods applied to Water
Quality Samples
Determinant, unit |
Standard Method |
Total Suspended Solids, mg/L |
In house method based on APHA 2540D; ALS Method Code: EA-025 |
Biochemical Oxygen Demand (BOD), mg/L |
In house method based on APHA 5210B; ALS Method Code: EP-030 |
All in-situ monitoring instruments were checked, calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use.
Dissolved Oxygen (DO), temperature and pH measuring
equipment
A portable, weatherproof multiparameter instrument YSI 556 MPS was used in the baseline monitoring. It can be capable for measuring dissolved oxygen (DO), pH, and temperature simultaneously with the following limits:
· a dissolved oxygen level in the range of 0-50 mg/L and 0-500 % saturation;
· a temperature of -5 to 45 degree Celsius; and
· pH value of 0-14 with 0.1 as the base unit.
Turbidity Measurement Instrument
Portable and weatherproof turbidity meter (HACH model 2100P) was used during impact monitoring. It has a photoelectric sensor capable of measuring turbidity between 0-1000 NTU. Response of the sensor was checked with certified standard turbidity solutions before the start of measurement.
Global Positioning System
A hand-held GPS navigator (Garmin eTrex
Suspended Solids and
BOD Measurements (Sample Containers and Storage)
Water samples for SS
analysis were stored in high density polythene bottles with no preservative
added, packed in ice (cooled to 4oC without being frozen), delivered
to the laboratory, and analysed as soon as possible after collection. Analysis
was carried out in a HOKLAS accredited laboratory.
In accordance with Section
4.2 of the EM&A Manual, monitoring for Dissolved Oxygen (DO), temperature,
pH, suspended solids (SS) and Biological Oxygen Demand (BOD) were undertaken at
6 designated monitoring locations as described in Section 4.4 below. DO,
temperature and pH were measured in-situ whereas SS and BOD were analysed in a
laboratory.
Monitoring Duration and Period
Following the requirement established in the EM&A Manual,
the measurements were taken at all designated monitoring stations, 3 days per
week, for 4 weeks prior to the commencement of construction works. In-situ measurement was carried out at each
location from 16 November to 11 December 2009 according to the schedule
of monitoring shown in Appendix B. The
interval between any two sets of monitoring was not less than 36 hours. No
construction activities over water in the vicinity of the points were observed
during the baseline monitoring.
The water quality monitoring points presented in the EM&A Manual were reviewed. All monitoring points were still applicable. No addition or alternation to the proposed monitoring stations in the EM&A Manual was considered to be required. The water quality monitoring locations listed in Table 4-3 were adopted during baseline monitoring and they are shown in Figure 4.1.
Table 4-3 Water Quality Monitoring Stations
ID |
Easting |
Northing |
MP1 |
838 730.50 |
822 862.25 |
MP2 |
838 933.26 |
823 247.41 |
MP3 |
839 107.17 |
823 596.84 |
MP4 |
839 286.14 |
823 638.55 |
MP5 |
839 134.35 |
823 722.99 |
MP6 |
839 063.02 |
823 842.25 |
In situ
measurement
All pH meters, DO/
temperature meters had been checked and calibrated prior to use. Standard buffer
solution of at least 2 pH levels (either pH 4 and pH 7 or pH 7 and pH 10) had
been used for calibration of the instrument before and after use.
DO meters had been
calibrated by a laboratory accredited under HOKLAS or any other international
accreditation scheme, and subsequently re-calibrated at 3 monthly intervals
throughout all stages of the water quality monitoring. Responses of sensors and
electrodes had been checked with certified standard solutions before each use.
Wet bulb calibrations for all DO meters had been carried out before measurement
at each monitoring location. For the on site calibration of field equipment, BS
127:1993, "Guide to field and on-site test methods for the analysis of
waters" had been observed.
Measurements shall be
at 3 water depths, namely, 1m below water surface, mid-depth and 1m above
stream bed/pond bed, except where the water depth less that 6m, the middepth
station maybe omitted. Should the water depth be less than 3m, only the
mid-depth station will be monitored.
Replicates in-situ
measurements and samples collected from each independent monitoring event are
required for all parameters to ensure a robust statistically interpretable
dataset.
Water Samples
Preparation and Analysis
For collection of
water sampling within the water courses, a 500ml clean plastic beaker was used.
After collection, the water samples were stored in high-density polythene
bottles. The sample container was rinsed with a portion of the water sample. The water sample
was then transferred to the container, labelled with a unique sample ID and sealed with a
screw cap. The water samples were stored in a cool box maintained at 4oC.
The water samples were then delivered to a local HOKLAS-accredited laboratory (ALS) on the same day for
analysis.
The testing methods
of testing parameters as recommended by EIA or required by EPD, with the QA/QC
results are in accordance with the requirement of HOKLAS or international accredited scheme.
Detection Limit
The limits of detection for the in-situ
and laboratory measurements are shown in Table 4-4.
Table 4-4 Detection
Limits for Water Quality Determinants
Determinant |
Limit of
Detection |
Dissolved Oxygen |
0.1 mg/L |
Temperature |
0.1 degree
Celsius |
pH |
0.01 unit |
Turbidity |
0.1 NTU |
Suspended Solids |
1 mg/L |
BOD |
2 mg/L |
Details of site Equipment used for In-situ
measurement
The calibration certificates for equipments used for in-situ
monitoring of water quality are attached in Appendix A.
No major activities were observed in the Project Area during the monitoring period. The baseline water quality monitoring results are provided in Appendix E. The summary of results for Dissolved Oxygen (DO), Turbidity and Suspended Solids (SS) are tabulated below. Graphical presentations of baseline water quality monitoring and results of other parameters at the locations are provided in Appendix E.
Table 4-5 Summary of Water Quality monitoring
results
Monitoring
Stations |
Dissolved Oxygen
(mg/L) |
|||
Average |
Range |
5%-ile |
1%-ile |
|
MP1 |
2.71 |
(1.15 4.65) |
1.23 |
1.17 |
MP2 |
4.57 |
(0.85-7.10) |
1.04 |
0.89 |
MP3 |
8.92 |
(6.60-11.90) |
6.85 |
6.65 |
MP4 |
5.69 |
(3.80-10.05) |
3.91 |
3.82 |
MP5 |
5.52 |
(3.80-8.60) |
4.13 |
3.87 |
MP6 |
6.20 |
(4.50-9.10) |
4.61 |
4.52 |
Monitoring
Stations |
Turbidity (NTU) |
|||
Average |
Range |
95%-ile |
99%-ile |
|
MP1 |
79 |
(10-178) |
173 |
177 |
MP2 |
46 |
(17-171) |
132 |
163 |
MP3 |
53 |
(39-68) |
64 |
67 |
MP4 |
42 |
(23-65) |
60 |
64 |
MP5 |
56 |
(26-84) |
81 |
84 |
MP6 |
65 |
(33-96) |
94 |
96 |
Monitoring
Stations |
Suspended Solids
(mg/L) |
|||
Average |
Range |
95%-ile |
99%-ile |
|
MP1 |
104 |
(13-316) |
231 |
299 |
MP2 |
60 |
(18-219) |
170 |
209 |
MP3 |
50 |
(35-66) |
65 |
66 |
MP4 |
37 |
(24-54) |
50 |
53 |
MP5 |
48 |
(28-70) |
66 |
69 |
MP6 |
54 |
(24-76) |
75 |
75 |
pH |
|
|||
Average |
Range |
|
||
MP1 |
7.3 |
(7.1-7.5) |
|
|
MP2 |
7.4 |
(7.3-7.7) |
|
|
MP3 |
8.2 |
(7.7-8.6) |
|
|
MP4 |
7.3 |
(7.1-7.6) |
|
|
MP5 |
7.3 |
(7.1-7.5) |
|
|
MP6 |
7.4 |
(7.2-7.5) |
|
|
Monitoring Stations |
BOD (mg/L) |
|
||
Average* |
Range |
|
||
MP1 |
3.0 |
(<2-5.5) |
|
|
MP2 |
2.8 |
(<2-5.0) |
|
|
MP3 |
10.8 |
(5.0-16.5) |
|
|
MP4 |
4.2 |
(<2-8.5) |
|
|
MP5 |
5.0 |
(<2-10.5) |
|
|
MP6 |
4.3 |
(<2-9.5) |
|
Note: Only 1 sample was taken at each monitoring
stations every time since water depths were below 3m for all monitoring
stations.
* In the average calculation, the detection limit 2
mg/L is adopted for all values smaller than 2 mg/L.
Dissolved Oxygen (DO) ranged from 0.85 to 11.9 mg/L for the 6 monitoring stations, with MP1 and MP2 having lower DO levels. The minimum DO level suggested in the Water Quality Objective is 4 mg/L. Results of MP3, MP4, MP5, and MP6 show compliance with the Objective. However, the measured DO level of MP1 was well below the required DO level.
Turbidity and SS also appeared to perform poorer at MP1 and MP2. Although all stations show a similar level of SS, the fluctuations in SS levels at MP1 and MP2 were larger.
pH values at MP3 were constantly higher than that of the other monitoring stations, though all pH values were within acceptable limits. On the other hand, BOD results at MP3 were also higher than that of the other stations.
There appeared to be
local impact near the monitoring stations MP1 and MP2 (water ditch at the west
of
Action/Limit (A/L) Levels for Water Quality Monitoring Parameters are determined according to the EM&A Manual.
Determination of Action and Limit
Level
The Action and Limit (AL) Levels for
water quality for construction phases
are defined in Tables
4-2 of the EM&A Manual and are shown in Table 4-6.
Table 4-6 Action and Limit (
Parameters |
Action Level |
Limit Level |
DO in mg/L |
5 percentile of baseline data |
≤2 or 1-percentile of
baseline data |
pH |
< 5.5 or > 7.5 |
< 4.0 or > 8.0 |
Turbidity in NTU |
95
percentile of baseline data |
99
percentile of baseline data |
SS in
mg/L |
95 percentile of baseline data |
99 percentile of baseline data |
BOD |
For Surveillance only |
For Surveillance only |
Table 4-7 shows the Action and Limit Levels of
Water Quality according to the baseline monitoring data.
Table 4-7 Action and Limit (
Parameters |
DO in mg/L |
Turbidity in NTU |
SS in mg/L |
pH |
||||
|
Action Level |
Limit Level |
Action Level |
Action Level |
Limit Level |
Limit Level |
Action Level |
Limit Level |
MP1 |
1.23 |
1.17 |
173 |
177 |
231 |
299 |
< 5.5 or > 7.5 |
< 4.0 or > 8.0 |
MP2 |
1.04 |
0.89 |
132 |
163 |
170 |
209 |
||
MP3 |
6.85 |
6.65 |
64 |
67 |
65 |
66 |
||
MP4 |
3.91 |
3.82 |
60 |
64 |
50 |
53 |
||
MP5 |
4.13 |
3.87 |
81 |
84 |
66 |
69 |
||
MP6 |
4.61 |
4.52 |
94 |
96 |
75 |
75 |
The actions in accordance with the
Event and Action Plan in Tables 4-8 below should be carried out if the water
quality assessment criteria are exceeded at any designated monitoring points.
Table 4-8 Event and Action Plan for Water
Quality for construction phrase
Event |
Action |
|||
ET Leader |
IEC |
ER |
Contractor |
|
Action Level |
|
|
|
|
1. Exceedance for one sample |
1. Repeat
in-situ measurement to confirm finding; 2. Identify
source(s) of impact; 3. Inform
IEC and Contractor; 4. Check
monitoring data, all plant, equipment and Contractors working methods; 5. Discuss
mitigation measures with IEC and Contractor; and 6. Repeat
measurement on next day of exceedance. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC on the proposed mitigation measures; and 2. Make
agreement on the mitigation measures to be implemented. |
1. Inform
the ER and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and propose mitigation measures to IEC and ER; and 6. Implement
the agreed mitigation measures. |
2. Exceedance for two or more consecutive samples |
1. Repeat
in-situ measurement to confirm finding; 2. Identify
source(s) of impact; 3. Inform
IEC and Contractor; 4. Check
monitoring data, all plant, equipment and Contractors working methods; 5. Discuss
mitigation measures with IEC and Contractor; 6. Ensure
mitigation measures are implemented; 7. Prepare
to increase the monitoring frequency to daily; and 8. Repeat
measurement on next day of exceedance. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC on the proposed mitigation measures; 2. Make
agreement on the mitigation measures to be implemented; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Inform
the Engineer and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and propose mitigation measures to IEC and ER within 3
working days; and 6. Implement
the agreed mitigation measures. |
Limit Level |
|
|
|
|
1. Exceedance for one sample |
1. Repeat
in-situ measurement to confirm finding; 2. Identify
source(s) of impact; 3. Inform
IEC, Contractor and EPD; 4. Check
monitoring data, all plant, equipment and Contractors working methods; 5. Discuss
mitigation measures with IEC, ER and Contractor; 6. Ensure
mitigation measures are implemented; and 7. Increase
the monitoring frequency to daily until no exceedance of Limit level. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC, ET and Contractor on the proposed mitigation measures; and 2. Request
Contractor to critically review the working methods; 3. Make
agreement on the mitigation measures to be implemented; and 4. Assess
the effectiveness of the implemented mitigation measures. |
1. Inform
the Engineer and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and ER and propose mitigation measures to IEC and ER within 3
working days; and 6. Implement
the agreed mitigation measures. |
2. Exceedance for two or more consecutive samples |
1. Repeat
in-situ measurement to confirm finding; 2. Identify
source(s) of impact; 3. Inform
IEC, Contractor and EPD; 4. Check
monitoring data, all plant, equipment and Contractors working methods; 5. Discuss
mitigation measures with IEC, ER and Contractor; 6. Ensure
mitigation measures are implemented; and 7. Increase
the monitoring frequency to daily until no exceedance of Limit level for two
consecutive days. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER accordingly;
and 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC, ET and Contractor on the proposed mitigation measures; and 2. Request
Contractor to critically review the working methods; 3. Make
agreement on the mitigation measures to be implemented; 4. Assess
the effectiveness of the implemented mitigation measures; and 5. Consider
and instruct, if necessary, the Contractor to slow down or to stop all or
part of the marine work until no exceedance of Limit Level. |
1. Inform
the ER and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and ER and propose mitigation measures to IEC and ER within 3
working days; 6. Implement
the agreed mitigation measures; and 7. As
directed by the Engineer, to slow down or to stop all or part of the marine
work or construction activities. |
As stated in Section 7.3.1 of the EM&A Manual,
baseline ecological monitoring was conducted during the preparation of the
Ecological Impact Assessment for the EIA report of the project. Data collected
during these surveys would be used as the baseline for evaluation of the
success in achieving numerical targets for the Target Species of the WRA.
The detailed results of the baseline surveys could
be referred to Section 8.6 of the EIA Report (ref. no. EIA-144/2008).
In accordance with Section 10.4 of the EM&A
Manual, a baseline monitoring for landscape and visual resources was conducted
in November 2009.
Baseline monitoring for landscape and visual resources
is defined in reference to the Landscape & Visual Impact Assessment (LVIA)
and EM&A Manual of the EIA report for the Project.
In accordance with Section 10.4.2 of the EM&A
Manual, Baseline monitoring for the landscape and visual resources will comprise
checking and updating of: the landscape resources identified in the EIA report
and elements of particular concern are to be re-checked and any changes
identified.
The landscape and visual baseline is confirmed with
the followings:
‘
any Tree Survey Report
prepared;
‘
habitat maps in
the EIA; and
‘
landscape and
visual impact assessments included in the EIA Report, to include updated photos
of each LCA and landscape resources which have been changed since the EIA was
carried out.
For
clarity, the numbering system for landscape and visual resources from the EIA
report is maintained.
LRs identified within the proposed project site
include:
‘
LR29 Drainage Channel at east of Site;
‘
LR30 Freshwater Marsh;
‘
LR32 Grassland with Seasonal Marsh Patches and
Soils on Site;
‘
LR33 Tree Group on Site;
‘
LR34 Banana Trees on Site;
‘
LR36 Trees in Open Storage Area; and
‘
LR39 Trees along
Based on the site visit findings; and review of the
tree survey report, habitat maps and LVIA of the EIA report, the status of all
the LRs have been checked and updated.
No substantial change in landscape resources of
LR29, LR30, LR32, LR33, LR36 and LR39 was identified. The only change between
the baseline monitoring and EIA report is the removal of LR34.
LR34 Banana
Trees on Site was found to be removed during the baseline monitoring.
According to the approved EIA report, this LR comprised a group of
approximately 10 nos. of 4m high banana trees (Musa sp.). As the sensitivity of this LR is Low. Its removal does
not cause any significant change in the landscape baseline. Updated photos
showing the change are presented in Appendix F.
The landscape resources beyond the project site
limit have no records of substantial changes.
Plan of Landscape Resources is illustrated in Figure 6.1.
The project site lies wholly within on distinct
landscape character area:
‘
LCA2 Tsing Lung Tsuen Plain
This LCA is a low-lying and predominantly rural
landscape. Occasional densely clustered villages, such as Wing Ping Tsuen, Fan
Tin Tsuen, Mai Po San Tsuen, Mai Po Lo Wai and On Lung Tsuen are situated
across the plain. Around the villages lie areas of active and disused
agricultural land and there are a number of open storage areas, giving the
landscape a slightly incoherent and degraded quality.
No substantial change in the baseline condition of the
LCA was found.
The landscape character areas beyond the project
site limit have no records of substantial changes.
Plan of Landscape Character Areas is illustrated in
Figure 6.2.
The VSRs identified in the EIA report are listed
below:
Residential VSRs:
‘
R1 Residents in Royal Palms (those most
affected are approximately 21 properties on Ventura Avenue and approximately 8
properties on Santa Monica Avenue which are the only properties which directly
face the site);
‘
R2
Residents in Palm Springs (those most affected are approximately 17properties
in Camellia Path and approximately 32 properties on Narcissus Path which are
the only properties which directly face the site);
‘
R3 Residents
in Wo Shang Wai;
‘
R4
Residents in Cottage Area South of Mai Po San Tsuen;
‘
R5
Residents in Mai Po San Tsuen and Mai Po Lo Wai;
‘
R6
Residents in Tam Kon Chau
Occupational VSRs:
‘
O1 Workers
in Fishponds in and around Mai Po
‘
O2 Workers
in Industrial / Storage Areas north of Royal Palms
‘
O3 Workers
in Industrial / Storage Areas east of Royal Palms
Travelling VSRs:
‘
T1
Motorists on
‘
T2
Motorists on
‘
T3
Motorists on
‘
T4
Pedestrians on San Tin Highway Footbridge
Recreational VSR:
‘
RE1 Visitors
to Mai Po Nature Reserve
Based on the site visit findings, no substantial
change in the baseline condition of all the VSRs was observed.
Plan of VSRs is illustrated in Figure 6.3.
Based on the baseline monitoring conducted in
November 2009, and review of the previously approved EIA report, it is
considered that the baseline landscape resources, landscape character areas and
visually sensitive receivers originally identified in the EIA study are
generally unchanged and remain valid.
The removal of the LR34 Banana Trees on Site did not substantially affect the landscape and
visual baseline or outcome of the assessment for its low sensitivity to change,
as detailed in Section 6.3 above.
Changes to the landscape and visual baseline are
therefore judged to be insignificant.
Change in locations of monitoring stations was required for air and noise monitoring. The procedures of alternation of locations of monitoring stations in the EM&A Manual were followed. Justifications for alternation and the proposed alternative air quality and noise monitoring stations for baseline and construction phase had been submitted to IEC for agreement before commencement of monitoring. This proposal has also been agreed by EPD.
Due to the revisions of monitoring locations mentioned above, the EM&A Manual will be updated for submission.
Baseline monitoring was carried out prior to the commencement of construction works for air quality (dust), noise and water quality in accordance with the requirements in the EM&A Manual for the Project. The weather during the baseline period was generally sunny and fine, however rainfall was recorded during two days of this period. All monitoring equipment used were properly calibrated and have valid calibration certificates.
Air quality monitoring was conducted at four air quality
monitoring for 14 consecutive days. There were no major observations of note
during monitoring. The major dust sources were from road traffic along
Noise monitoring was carried out at four noise monitoring stations for 14 consecutive days. However, monitoring was suspended for one day during this period due to rainfall, and the monitoring period was extended to make up for this interruption. A few noise levels recorded which were unusually high or low were removed to give a more representative set of data. The measured results are considered representative of the ambient background noise conditions prior to the commencement of works.
Water quality monitoring was carried out at 6 designated monitoring stations at 3 days per week for 4 weeks. Parameters including Dissolved Oxygen and Suspended Solids, Turbidity, pH, temperature and BOD were recorded during the baseline monitoring period. The measured results of the monitoring parameters are considered representative of the pre-construction ambient conditions prior to the commencement of the works.
The ecological baseline monitoring was conducted during the preparation of the Ecological Impact Assessment for the approved EIA report of the project. Therefore the ecological baseline is considered unchanged and valid.
Baseline landscape and visual monitoring was conducted in November 2009 to review and update all the landscape and visual resources previously identified in the EIA report. Monitoring results showed that there are no substantial changes in landscape resources, landscape character areas and visually sensitive receivers.
Action and Limit Levels of the relevant parameters at each monitoring location were derived from the baseline monitoring results and these will be adopted for impact environmental monitoring.
In conclusion, the Contractor is advised to be aware of any site practice that may give rise to significant pollution to the existing environment. Implementation of necessary remedial measures should be instigated to rectify the potential impact on sensitive receivers located in the vicinity of the construction area.
Appendix A. Calibration Record
Appendix B. Baseline Monitoring Schedule
Appendix C. Baseline Air Quality Monitoring Results
Appendix D. Baseline Noise Monitoring Results
Appendix E. Baseline Water Quality Monitoring Results
Appendix F. Updates of Landscape Resources
Appendix G. Weather Information from HKO