Current Works (updated:21 July 2016)

 
     
 
  • Temporary site formation
  • Adaptive management in the Wetland Restoration Area (remove unwanted / invasive species)
  • Continuing monitoring of the instruments for the ground improvement works
  • Maintenance of strip planting along southern perimeter of site (as landscape and visual impact mitigation measures)
 
 

 
 
  • Weekly environmental site inspection
  • Monthly environmental monitoring and auditing
  • Monthly ecological monitoring at Wetland Restoration Area
 
   
--------------------------------------------------------------------------------------------------------------------------------------------------------